Loading...
03-42 Resolution No . 03-42 RESOLUTION APPROVING CHANGE ORDER NO. 1 IN T: E CONTRACT WITH J.J.L. , INC . FOR THE 2002 ROOF RE•LACEMENT PROJECT WHEREAS, the City of Elgin has heretofore entered into a contract with J.J.L. , Inc . for the 2002 Roof Replacement Project; and WHEREAS, it is necessary and desirable to modify the terms of the contract as is described in Change Order No. 1, attached hereto. NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF ELGIN, ILLINOIS, that Olufemi Folarin, Interim City Manager, be and is hereby authorized and directed uo execute Change Order No. 1, a copy of which is attached hereto Jnd made a part hereof by reference . s/ Ed Shock Ed Schoc , , Mayor Presented: February 26 , 2003 Adopted: February 26 , 2003 Omnibus Vote : Yeas : 6 Nays : 0 Attest : s/ Dolonna Mecum Dolonna Mecum, City Clerk CHANGE ORDER NO. 1 and F NAL This Change Order made and entered into this day of Jan ary, 2003, by and between the City of Elgin, an Illinois municipal corporation, and J.J.L., Inc. an Illi ois Corporation. ORIGINAL CONTRACT: Roof Repair and Replacement 2002 Invitation to Bid No. 02-059 Contract Date June 24, 2002 PROJECT NO. 379537 (Roof Repair and Replacement 2002) SCOPE: Additional repairs to The Hemmen's roofs as I sted. REASONS FOR CHANGE: Removal of the existing ro sting exposed additional damage to the roof decking or materials which could nit be seen prior to the roof removal thus, the circumstances said to necessitate thi'• change were not reasonably foreseeable at the time the original contract was signed and this change is germane to the original contract as signed. SUMMARY OF CHANGES IN CONTRACT AMOUNT: All work was done in accordance with the unit pricing requested at the time • the bid. The amount of the contract will be revised as follows: ITEM D:DUCT ADD New cast iron drain strainers $1,174.50 Remove damaged lightweight concrete $20,323.75 Replace rotted wood blocking $4,240.00 TOTAL AMOUNT OF CHANGE ORDER# 1 and FIN• $25,738.25 Original Contract Price Including Alternates $296,826.00 New Contract Amount $322,564.25 OTHER CONTRACT PROVISIONS: All other contract provisions shall remain the same. Agreed to this day of January, 2002. Recommended: BUILDING MAINTENANCE DEPARTMENT By: Title: 8k,&. t . T P r, Date: ///Va 3 Accepted: J.J.L., Inc. Party of the Second Part(Contractor) / By: 14Z: ./, . Title: let_-I• nt Date: 1/9/03 Approved: CITY OF ELGIN Party of the First Part (Owner) By: Title: Date: CHANGE ORDER NO. 1 and F NAL This Change Order made and entered into this day of Jan ary, 2003, by and between the City of Elgin, an Illinois municipal corporation, and J.J.L., Inc. an Illi ois Corporation. ORIGINAL CONTRACT: Roof Repair and Replacement 2002 Invitation to Bid No. 02-059 Contract Date June 24, 2002 PROJECT NO. 379537 (Roof Repair and Replacement 2002) SCOPE: Additional repairs to The Hemmen's roofs as I sted. REASONS FOR CHANGE: Removal of the existing ro•fing exposed additional damage to the roof decking or materials which could n• be seen prior to the roof removal thus, the circumstances said to necessitate thi change were not reasonably foreseeable at the time the original contract was signed and this change is germane to the original contract as signed. SUMMARY OF CHANGES IN CONTRACT AMOUNT: All work was done in accordance with the unit pricing requested at the time • the bid. The amount of the contract will be revised as follows: ITEM D:DUCT ADD New cast iron drain strainers $1,174.50 Remove damaged lightweight concrete $20,323.75 Replace rotted wood blocking $4,240.00 TOTAL AMOUNT OF CHANGE ORDER# 1 and FIN• $25,738.25 Original Contract Price Including Alternates $296,826.00 New Contract Amount $322,564.25 OTHER CONTRACT PROVISIONS: All other contract provisions shall remain the same. Agreed to this day of January, 2002. Recommended: BUILDING MAINTENANCE DEPARTMENT By: 62._ Title: &,/J. /ht,KT. SkpT, Date: //i't/o3 Accepted: J.J.L., Inc. Party of the Second Part(Contractor) By: Ai Title: id Date: 1/9/03 Approved: CITY OF ELGIN Party of the First Part (Owner) By: Title: Date: • '(OF f< ` I.b City of Elgin Agenda Item No. L E ./ February 7, 2003 G � � I pi N , ■?ice' TO: Mayor and Members of the City Council ` " FINANCIALLY STABLE CITYGOVERNMENT EFFICIENT SERVICES, AND QUALITY INFRASTRUCTURE FROM: Olufemi Folarin, Interim City Manager SUBJECT: Change Order No. 1 and Final Payment for 2002 Roof Replacement Project PURPOSE The purpose of this memorandum is to provide the Mayor and members of the City Council with information to consider the approval of Change Order No. 1 and final payment for the 2002 Roof Replacement Project . BACKGROUND During the 2002 budget process, roofs on the Hemmens and Wing Park Band Shell were identified for replacement . After a review of the roofs, a specification for the replacement project was prepared by Raths, Raths, and Johnson, Inc . A bid for the project was awarded to J.J.L. , Inc. (d/b/a American Roofing and Repair) at the June 12 , 2002 , City Council meeting. Upon removal of the existing roofing at the Hemmens building, damage to the roof decking was discovered that could not be seen prior to the roof removal . This damage required removal and replacement of additional materials on the roof deck. All damage and necessary repairs were verified by City staff and Raths, Raths, and Johnson, the City' s roofing consultant for this project . Unit pricing was requested at the time of the original bid. All work was completed in accordance to that unit pricing. The circumstances were not reasonably foreseeable at the time of the original contract . COMMUNITY GROUPS/INTERESTED PERSONS CONTACTED None. Change Order No. 1 & Final Payment for 2012 Roof Replacement Project February 7, 2003 Page 2 Calk___- FINANCIAL IMPACT Project #379537 Budget (Account Numbers 385-0000-795 93-36) $332, 025 Expenses: American Roofing & Repair: Original Contractor $296, 8 !5 Change Order No. 1 $ 25, 7. 0 $322, 565 Roth, Roth, & Johnson $ 9, 360 Suburban Newspapers $ 100 Total Expenses : $332, 025 Balance Remaining $ -0- EGAL IMPACT None. ALTERNATIVES 1 . Approve the change order and final pa, ent as recommended. 2 . Reject the change order and final pa ent . RECOMMENDATION It is recommended that the City Council .pprove Change Order No. 1 in the amount of $25, 738 .25 and final .ayment in the amount of $39, 808 for the 2002 Roof Repair Project . Respectfulli submitted, (n)2111! ; 'Mb.� � Olufemi Fo 1101110' Inte . im ger RH Attachments