Loading...
95-270 Resolution No. 95-270 RESOLUTION APPROVING CHANGE ORDER NO. 1 IN THE CONTRACT WITH EARTH, INC. FOR THE COOPER-SUMMIT WATER MAIN PROJECT WHEREAS, the City of Elgin has heretofore entered into a contract with Earth, Inc. for the Cooper-Summit water main project; and WHEREAS, it is necessary and desirable to modify the terms of the contract as is described in Change Order No. 1, attached hereto. NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF ELGIN, ILLINOIS, that Richard B. Helwig, City Manager, be and is hereby authorized and directed to execute Change Order No. 1, a copy of which is attached hereto and made a part hereof by reference. s/ Kevin Kelly Kevin Kelly, Mayor Presented: December 20, 1995 Adopted: December 20, 1995 Omnibus Vote: Yeas 7 Nays 0 Attest: s/ Dolonna Mecum Dolonna Mecum, City Clerk r N / ELGIN, ILLINOIS PROJECT#W35f CHANGE ORDER NO.1 SCOPE: This Change Order#1 will provide additional items necessary to finalize the project. The general contractor for this project is Earth, Inc. of Carol Stream, IL. REASONS FOR CHANGE: This Change Order #1 is required for the addition or change in items necessary to adjust payment for additional construction costs associated with the watermain installation. SUMMARY OF CHANGES IN CONTRACT AMOUNT: The amount of the contract will be revised as follows: ITEM ADD 1) X23 12" Corrugated Metal Pipe (Storm Sewer), 44 L.F. @ $32.00/L.F $1,408.00 2) X24 Flared End Section, 1 EA. @ $145.00/EA. $ 145.00 3) X25 Fence Removal and Replacement, L.S. $ 810.00 4) Adjustment to contract pay item quantities (+) $8,699.10 (See the attached final pay estimate) NET COST OF CHANGE ORDER #1 J' $ 11,062.10 The original contract with Earth, Inc. is $87,626.00. By reason of this Change Order #1, the contract for the Cooper-Summit Watermain Project will be increased in the amount of eleven thousand sixty two and 10/100 dollars ($11,062.10). The final contract amount, inclusive of change order #1 is ninety eight thousand six hundred eighty eight and 10/100 dollars ($98,688.10). r ' CHANGE ORDER NO.1 December 8, 1995 Page 2 OTHER CONTRACT PROVISIONS: All other contract provisions shall remain the same. Agreed to this g day of b-x,1995. Recommended: ENGINEERING DIVISION By: Date: 1 l Accepted: EARTH, INC. Party of the Second Part (Contractor) By: �� Title: . Date: /2 - g' Approved: CITY OF ELGIN Party of the First Part (Owner) By: _CC Title: Date: -)---/-2.-7 /c ,— Elm ion riE rvi Agenda Item No. November 30, 1995 TO: Mayor and Members of the City Council FROM: Richard B. Helwig, City Manager SUBJECT: Authorization of Change Order No. 1, Final Payment and Acceptance of the Cooper-Summit Water Main Project PURPOSE The purpose of this memorandum is to provide the Mayor and members of the City Council with information to consider approval of Change Order No. 1, acceptance of the subject improvements and authorization to make the final payment. BACKGROUND The City Council awarded to Earth, Inc. the contract for the Cooper-Summit Watermain project on August 23, 1995 . The project generally included the installation of 1900 feet of water main to eliminate dead end mains. The dead end mains eliminated are located on Page Street east of Preston, Slade Avenue east of Preston, Hiawatha Court north and west of Hiawatha Avenue and Enterprise Street east of Preston. Earth, Inc. has completed the project in compliance with the plans and specifications as verified by the City's Engineering staff. Attached for your additional consideration is Change Order No. 1 in the amount of (+) $11,062 . 10.. This change order adds various items necessary to complete the work, and decreases the quantities of various work items not used. The major components of the increased cost is due to greater quantities of sod and sidewalk to complete restoration. All items were unforeseen at the time the contract was awarded and were necessary in order to complete the project. These items are addressed on the attached change order and on the attached final pay estimate. COMMUNITY GROUPS/INTERESTED PERSONS CONTACTED None. Cooper-Summit Water Main Project November 30, 1995 Page 2 FINANCIAL IMPACT A. Project Funding: This project was included in the 1995 CIP budget as follows : . Account No. 395-4000-795 . 93-41, Project No. 39506F in the amount of $130,000 for water main upgrading. This project was one of five water distribution main up- grading projects which were budgeted in the aggregate amount of $820,000 . B. Project Final Expenditures: Only one contract was entered into under this project: . Earth, Inc. in the awarded amount of $87,626 .00 for the construction of a water main. . With Change Order No. 1 in the amount of (+) $11,062 . 10, the final project cost is in the aggregate amount of $98,688 . 10 . C. Final Contract Amount with Earth, Inc. : The final contract amount with Earth, Inc. is as follows: • . Original award • $ 87 ,626 . 00 . Change Order No. 1 • $ 11, 062 . 10 . Final Contract • $ 98,688 . 10 Payments made to Earth, Inc. to-date are in the amount of $85,955 . 93 leaving a final payment due of $12,732 . 17 . LEGAL IMPACT None. • C • Cooper-Summit Water Main Project November 30, 1995 Page 3 RECOMMENDATION It is recommended that the City Council authorize Change Order No. 1 in the amount of (+) $11, 062 . 10 and direct staff to execute the change order document. It Is further recommended that the City Council accept the completed project and authorize the final payment of $12,732. 17 to 1 Respectfull su mitted, / )*!/J . J 4attil L. Kristiansen Public Works Director 1� Richard B. Helwig City Manager DL/do Attachments e eft. • •