Loading...
95-17 Resolution No. 95-17 RESOLUTION APPROVING CHANGE ORDER NO. 2 IN THE CONTRACT WITH ATEC & ASSOCIATES, INC. WHEREAS, the City of Elgin has heretofore entered into a contract with ATEC & Associates, Inc. for the design and installation of a groundwater remediation system for 206-280 South Grove Avenue; and WHEREAS, it is necessary and desirable to modify the terms of the contract as is described in Change Order No. 2, attached hereto. NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF ELGIN, ILLINOIS, that Richard B. Helwig, City Manager, be and is hereby authorized and directed to execute Change Order No. 2, a copy of which is attached hereto and made a part hereof by reference. s/ George VanDeVoorde George VanDeVoorde, Mayor Presented: January 25, 1995 Adopted: January 25, 1995 Vote: Yeas 7 Nays 0 Attest: s/ Dolonna Mecum Dolonna Mecum, City Clerk ELGIN, ILLINOIS ADDITIONAL SERVICES FOR 206 - 280 SOUTH GROVE AVENUE CHANGE ORDER NO. 2 SCOPE: This Change Order No. 2 covers additional services related to the installation of a groundwater remediation system at the City of Elgin properties located at 206-280 South Grove Avenue under a con- tract awarded on February 10, 1994 . The Contractor for this project is ATEC Associates, Inc. of Downers Grove, Illinois . REASONS FOR CHANGE: This Change Order is required for the additional costs necessary to implement and complete the corrective action plan submitted to the Illinois Environmental Protection Agency ( IEPA) . All of the following tasks which have been or will be completed pursuant to this change order have been or will be constructed in accordance with the as- built plans dated January 17 , 1995, which are attached hereto and made a part hereof by this reference as Exhibit "A" . TASKS: 1. Measure Water Levels and Sample Groundwater from Monitor- ing Wells ATEC performed groundwater sampling of the monitoring wells at the South Grove Avenue property. Due to damage of two monitoring wells, sampling could not be performed resulting in a reduction of $3,684 . 75 to this task. 2 . Perform Slug Tests on Six Monitoring Wells ATEC performed slug tests on the monitoring wells at 280 South Grove Avenue (former Bunge Tire) , however the datalogger and computer were not operative and thus was not charged to the project. This resulted in a reduction of $715 . 00 to this task. 3 . Perform Geotechnical Soil Testing ATEC collected soils samples for geotechnical soil test- ing during well installation at 280 South Grove Avenue (former Bunge Tire) . This lowered the cost incurred for this task since a drill rig and crew were not charged to this task. This resulted in a reduction of $2,646 .00 to this task. 4 . Additional Design of Groundwater Remediation System ATEC originally budgeted 300 hours for this task for the design of the groundwater remediation system (original contract) . At the time of the authoriza- tion from the City Council, the amount of hours for design was based upon a design of a groundwater interceptor trench and two groundwater extraction wells . ATEC completed the design of the system, and discussed the design and installation with the City of Elgin and Elgin Riverboat Resort. Elgin Riverboat Resort expressed concern with caving of the trench walls due to their experience with the installation of a deep sanitary sewer along the river. Since the CAP approval from the IEPA would take several weeks, and the groundwater remediation system needed to be installed prior to the opening of the Grand Victoria Casino, all parties felt that a different system may be more prudent. The concern was that if difficulties were experienced with the installation, there would not be sufficient time for a resubmittal of the CAP and construction, and thus the opening of the Grand Victoria Casino would be delayed. ATEC then designed a groundwater system consisting of two trenches and five ground water extraction wells. This design was presented to be installed to the City Council as Change Order No. 1. Since ATEC had completed the original design, most of the hours budgeted had been utilized. Since it was necessary not to delay the opening of the Grand Victoria Casino, the additional design work was completed by ATEC and the CAP was submitted to the IEPA and was subsequently approved. At the time of the submittal of Change Order No. 1, ATEC was still in the process of design work and was awaiting IEPA comments and changes . Therefore, the additional hours were not included with Change Order No. 1. Subsequent to the second revision, concerns we raised regarding system annual operating costs, it was necessary to revise the groundwater remediation system after the approval of Change Order No. 1. The revised groundwater remediation system design included two groundwater piping headers, and a valving system that allowed water extracted from the wells to move into either pipe, creating discharge options . After the approval from the IEPA, it was necessary to receive two additional major permits from the IEPA water section and FRWRD. Additional time ( 100 hours) was necessary for the preparation of the permits. Due to involvement of the agencies, it was mandated that additional safety features to be built into the system. This included making the system explosion proof, and the installation of lower explosive level (LEL) meters into each of five well vaults, two meter vaults and the sanitary sewer discharge point. One additional precast concrete sampling manhole was also installed at the request of FRWRD. ATEC' s original estimate of 256 hours of engineering time was exceeded by 660 hours (for a total of 916 hours) . This time was exceeded due to the prepara- tion of three groundwater designs (rather than one) , and the submittal of two Corrective Action Plans and associated correspondence to the IEPA. It should be noted that the second and subsequent third design was more technically involved requiring more time than the preceding design. These design changes resulted in an addition of $45,696 .35 to this task. 5. Install Nine Groundwater Monitoring Wells ATEC and their subcontractor drillers were able to complete the installation of the groundwater moni- toring wells in less time than anticipated. In addition, a modification was made in the protective coverings for the wells which reduced the cost for this task by $5,708.75. It should be noted that a mathematical error of $10,530.00 was added into this task. The total of these changes resulted in a reduction of $23,310.47 to this task. 6 . Install One Extraction Well and Perform Pump Test Due to the increased flow rate encountered in Ex- traction Well #1, additional time was required to perform the pump test and to determine the flow rate. The type and size of the pump also changed resulting in an additional cost. The total of these changes resulted in an addition of $772 .45 to this task. 7 . Install Four Extraction Wells Due to the increased flow rates anticipated, the extraction well size was increased. In place of 4-inch diameter stainless steel wells, 6-inch stain- less steel wells were installed. Additional costs for material and labor were incurred. Due to the increased sizes of the wells, increased costs were incurred to develop the wells. Drilling and over- sight costs increased, as well as cutting and devel- opment water disposal costs . The total of these changes resulted in an addition of $9 ,213.42 . B . Construct Groundwater Piping and Electrical Trenches Following the installation of the groundwater ex- traction wells, the remaining portions of the groundwater remediation system were installed. Due to the change in the groundwater remediation system design, additional costs were incurred. a) Excavation of the groundwater piping trench was increased in length by 270 feet. The design approved in Change Order 1 called for two and another trenches, one of approximately of 335 feet in length, with one groundwater extraction pipe in the trench. The revised groundwater remediation system was constructed with one continuous trench. This as-built trench was now increased to a length of 875 feet. Two pipes were installed in the trench, three to four times the larger than originally proposed. Due to the increase in the number and size of the pipes, the width of the trench was also increased. Excavation was necessary under a water main, which made it necessary to use piping that met specifications for con- struction of water and sewer mains in Illinois . b) Since the revised groundwater remediation system design included two groundwater piping headers, and a valving system to add flexibili- ty in discharge options, material amounts and installation costs increased. c) Due to the time constraints of installing the groundwater system prior to the opening of the Grand Victoria Riverboat, the installation of the system include overtime and weekend work, which increased labor and equipment costs. d) Due to the additional length and width of the groundwater remediation trench, additional soils were removed from the site, increasing the cost of the project. The amount of soil excavated and disposed increased to 1025 cubic yards from the original estimate of 400 cubic yards . Additional backfill was also required. e) Due to the increased power required for the larger pumps, the wire and conduit sizes in- creased. Additional electrical costs were incurred due to the necessary installation of LEL meters in each of the vaults, installation of a 200 Amp (vs . 100 Amp) service. The total of these changes resulted in an addition of $138,754 .20 to this task as shown on the accompa- nying sheet. 9 . Construction Preparation and Construction Oversight Due to the change in the design of the groundwater remediation system, the time necessary to complete the installation of the system increased due to the complexity and additional work necessary. ATEC' s staff time necessary for construction preparation and construction oversight was increased. In addi- tion, due to time constraints, the material for construction had to be scoped out and ordered by ATEC during the construction. This additional time increased ATEC's time from 360 hours to 855 hours . The total of these changes resulted in an addition of $38, 164 . 15 to this task as shown on the accompa- nying sheet. 10 . Prepare 0 & M Manual Due to the addition of meters and the change in the design of the groundwater remediation system, addi- tional time will be necessary to complete the Opera- tion and Maintenance (0 & M) Manual . The total of these changes resulted in an addition of $1, 300.00 to this task as shown on the accompanying sheet. SUMMARY OF CHANGES IN CONTRACT AMOUNT: The project was contracted with a total of 10 tasks . Task 1 through Task 4 were the original contract (development of CAP) . Task 5 through Task 10 were Change Order No. 1 (imple- mentation of CAP) . The amount of contract will be revised as follows : ITEM COST CHANGE Task 1 Subtract $ 3,684 .75 Task 2 Subtract $ 715 .00 Task 3 Subtract $ 2,646 .00 Task 4 Add $ 45,696 . 35 Task 5 Subtract $ 23,310 .47 Task 6 Add $ 772 .45 c ' Task 7 Add $ 9,213.42 Task 8 Add $ 138,754 .20 Task 9 Add $ 38, 164 . 15 Task 10 Add $ 1,300 .00 Total Add $ 203,544 .35 The present contract with ATEC is for $260,447 .75 . By reason of Change Order No. 2 the contract for the additional services will be increased in the amount of Two Hundred Three Thousand Five Hundred Forty Four and 35/100 Dollars ($203,544 .35) . The new revised contract Thousand total Twenty be Two aandnt r 10/ 00 Sixty Dollars ($464,022 . 10) . OTHER CONTRACT PROVISIONS: All other contract provisions of the original contract agreement of February 9, 1994, shall remain the same and in full force and effect for the addition- al work to be performed under this change order. Agreed to this ':7t4_ day of January, 1995 . Recommended: City of 'n By: Date: Accepted: ATEC Associates, Inc. Party of the Second P?artn (Contractor) By: Title: Date: Approved: City of Elgin Party of the First Part (Owner) By: -� ��S k•��� Title: Date: • n Agenda Item No. �. January 20, 1995 TO: Mayor and Members of the City Council FROM: Richard B. Helwig, City Manager SUBJECT: Change Order No. 2 for Revisions to the Groundwater Remediation System Installed at 206-280 South Grove Avenue Properties PURPOSE The purpose of this memorandum is to forward to the Mayor and City Council Change Order No. 2 for revisions to the Groundwa- ter Remediation System installed at 206-280 South Grove Ave- nue. BACKGROUND As part of a request for specific soil cleanup objectives submitted to the Illinois Environmental Protection Agency ( IEPA) for 210 South Grove Avenue and 240 South Grove Avenue, the City of Elgin stated that it would continue to investigate the site through groundwater studies and design, construct and operate a groundwater remediation system. ATEC Associates, Inc. (ATEC) was awarded a contract to develop a groundwater corrective action plan for the City of Elgin properties locat- ed along South Grove Avenue (206-280 South Grove Avenue for $38,374 .50) . ' Change Order No. 1 in the amount of $222, 103 .25 was awarded to ATEC to solicit bids and install a groundwater remediation system. In a memo dated October 27, 1994, Council was advised that modifications were required to the groundwa- ter remediation system and that additional costs would be incurred. Under the initial contract, ATEC budgeted 300 hours for the design of the groundwater remediation system. At the time of the authorization from the City Council, the amount of hours for . design was based upon a design of a groundwater intercep- tor trench and two groundwater extraction wells. ATEC com- pleted the design of the system, and discussed the design and installation with the City of Elgin and Elgin Riverboat Re- sort. Elgin Riverboat Resort expressed concern with caving of the trench walls due to their experience with the installation of Mayor and Members of the City Council January 20, 1995 Page 2 a deep sanitary sewer along the river. Since the CAP approval from the IEPA would take several weeks, and the groundwater remediation system needed to be installed prior to the opening of the Grand Victoria Casino, all parties felt that a differ- ent system may be more prudent. The concern was that if difficulties were experienced with the installation, there CAP and would notion sufficient and thus time the opening s of the 1 of construe Grand e Victoria , Casino would be delayed. ATEC then designed another groundwater system consisting of two trenches and five ground water extraction wells. This design was presented to the City Council as Change Order No. 1. Since ATEC had completed the original design, most of the hours budgeted had been utilized. The additional design work was completed by ATEC and the CAP was submitted to the IEPA and was subsequently approved. At the time of the submittal of Change Order No. 1, ATEC was still in the process of design work and al hours gwereAnot comments ncluded d with nChange Therefore, Order No. the addition 1 . As part of the installation of the groundwater remediation system, one groundwater extraction well was installed est revealed subsequently subjected to a pump test. The pump more than a higher yield rate of 310 gallons per minute (gp m) , was utilized for the original calculations preparation of the Corrective Action Plan (CAP) submitted July 21, 1994 . The CAP design was based upon slug tests performed atAthersite which revealed a groundwater yield rate of 27 gpm. pump test was performed, discussions with the Fox River Water Reclamation District (FRWRD) revealed the possibility of an increased user charge which would greatly increase the opera- tion cost of the system. Due to the increased yield rate and the possible rate change from FRWRD, the viability of FRWRD as a discharge point for groundwater was questioned. Because of the above-mentioned issues, it was necessary to change the design of the groundwater remediation system. The decision was made between the City of Elgin, Ries Environmen- tal, Inc. and ATEC Associates, Inc . to build flexibility into the groundwater system to allow discharge from the groundwater remediation system to points other than the sanitary sewer (i.e. a future on-site treatment system and/or the Fox River) . The rate increase being considered by FRWRD at that time would have resulted in an annual disposal cost in excess of by ;1,000,000 . The flexibility of thhethatsconsistedsofdtwo designing and installing a piping header groundwater piping systems, and a valving system that allowed water extracted from each well to move into either pipe thus allowing the additional discharge options . Mayor and Members of the City Council January 20, 1995 Page 3 The IEPA was notified of the change in the design and a re- vised CAP was submitted to the IEPA on August 29, 1994 and subsequently approved by the IEPA in early September. ATEC began the installation of inground elements of the system on continuously until 6eptember 20, 1994 . Th e Due to the additional design work, and the costs incurred with the installation of the revised groundwater remediation system installation, Change Order No. 2 is necessary. The attached design drawings provide detail on the system that was origi- nally proposed and ultimately constructed. ATEC has charged all subcontractor costs on this project at cost (no markup or handling charge to the City of Elgin) . Since this project needed to be installed prior to the opening of the Grand Victoria Casino, ATEC brought in specialists from Michigan to install the piping system. ATEC paid for the cost of lodging, travel and meals of the specialists ($3,376 .66) , and will not charge the City of Elgin for these costs . In an effort to limit the amount of this change order, ATEC by also reduced the number of hours charged to this project hours, resulting in a reduction in costs of $18,407 .50 to the City of Elgin. In addition, per the request of the City of Elgin, as part of the acceptance of Change Order No. 2, ATEC will prepare an submit the reimbursement package to the IEPA at no charge to the City of Elgin. The estimated cost to prepare and submit request to the IEPA is $4 ,400 .00 . The City the reimbursement is not eligible for reimbursement from the State until the necessary documentation is properly submitted. All invoices im- must be paid in advance IEPAbY the ATECi has prior to ethe bursement from th preparation of the reimbursement package. Attached is Change Order No. 2 from ATEC regarding additional services related to the installation of the system that was approved by the ct•of $203 , 544 . 35 .he change order includes ten items with a total os ATEC will be present you mayehave regarding January thech change order. answer any ques Y COMKuNITY GROUPS/INTERESTED PERSONS CONTACTED None. FINANCIAL IMPACT The change will result in a $203,544 . 35 increase in the con- tract with ATEC from $26 1,4througho Item ,10 2 are eligible i for ties described in Item Mayor and Members of the City Council January 20, 1995 Page 4 reimbursement from the Illinois Leaking Underground Storage Tank Fund (LUST) . The eligibility of the additional costs incurred has been discussed with the Illinois Environmental Protection Agency ( IEPA) . The approval of the revised collec- tive action plan by the IEPA indicated that additional expens- es related to the revised system are eligible for reimburse- ment through the Lust Fund. Expenses related to the costs of the installation of the groundwater remediation system will be charged to fund 260-000-791-45-99 , Project No. 179511 . The total budgeted expenditure in the South Grove TIF Fund is $404 ,725, to be funded from the property tax increment ($260, 000) and land lease payments ( $100, 000 ) . LEGAL IMPACT None. RECOMMENDATION It is recommended the City Manager be authorized to execute Change Order No. 2 . Respectfully submitted, i W,, Raymond H. Moller Director of Business Services and Properties Richard B. Helwig City Manager RHM/sg SOD k TOPSDIL -. SOD. TOPSOIL k BY OTHERS COMPACTED SOIL '-7T7T PEA GRAVEL OR COMPACTED SANG -•3.0' \� ` /� NATIVE MATERIALS ATIVE MATERIALS ..•4.0' A� / 4.0' PVC PIPE AND RI RIGID METAL TAL C V U11DUli O �` IN OF RUES. E / E TRENCH VARIES, SEE \� \ PEA CRa�F=L ELECTRICAL PLAN VIEW) \\ � � BEDDING PEA GRAVEL 6" SDP 26 PVC PIPES / BEDDING \\\ 6" OR B" SDR 26 PVC PIPE CROSS 9ECT10N OF OROUNDWA CROSS SECTION._OF 14L AND ELECTRICAL_IMNKtIITY�P�) PpNQ&4P AS-BUR T FINAL DESIGN PROP0.SPD DESIQN 25* I 37.5' I SIDEWALK Hf 0. GROUND SURFACE Ti iT/TTT>iii�TT / �.�. FROM EXTRACTION WELLS rnoM EXmACT10H wEU ♦.0' AND METER VAULT AND METER VAULT SANITARY / wf HF 4 �**\\ L=3 WAR / __ MANHOLE SEWE REDUCERS IN SAMPLING�CLEA/ OIE 17•SOR 2 Ma - NOT to SCALE PRESSURE PIPE GROUNDWATER- SANITARY / GROUHDMATER IIr Son= DIS04ARGE PR MANHOLE DISCHARGE PIPE ESKh� (SH. AO PVC) S.5911 ES C]ROINDWATER PrV413 AND PRSSRRE PPE soor se o i PPE DRAIN ANNULAR REQUIRED VAT" � SANITARY UK ELECTF CAL TENCH DETAIL S ANN" SPACE . / GROUTED / CpIAPAR190N GROUTED CITY OF ELOld �L.- — T- / CMILI 7 %� DWATER TIEATWNT i// sysTEM DEa1oN 6.0' --- r---- 6 0' -- ---i DATE: 1 17 95 FILE: 5107-9a-0000• DRAWN Nt Rn�Aw�Erf/[y Es.�w er MANIEY cuo FU: EtsEgt FIGURE . .—__._ E_AND�-l�TQ SAI�Qt►[3T. �MA_I�LE IT7P_J TIE-IM 7Q�JylTL�flY_�INEH_ .E 1T�1 2777 Finley Road. Suite N6 ATEC AS-BUILT FINAL DESIGN PROPOSED_DESIGN Downers Grove, Illinois 60515 PA (708) 916-7272 -►&X: (708) 916-7013 WPLT .IwLT N�LT YIIfRGItCtlA►wL;.r R&MAGELM�L V![LT iB 4~— r .s.w A r Rnia.r n P.•Rw � nciw L —f..•IwWP WL•wcw J rPw��w�rw�.r WwI/rla.l m`wr M. ii P Y�0 Yw rt rrcPrrw �_ A Al_-i m_. r _...__ it .�2 1` !�7-7 l� r��7-77� r77 r r>r r r7 lFQFNQ I R[DU«. WALL vALK NORMALLY OPCv AafLT A►a4LT H LL vLK NORMALLY CLOS[3 N CN[CN VALVE U O FLOW LOW / Mwwwa wRw+, ��•rNw OKOXER /s.P rr ur S4ai.. / T -- /T� now wauTaL ror,uz[A SAYPL[PONT wjw10. \ f • '.mow // w r w w. /�/ O RYP(PARM NOCATOR PN[SSUN[MpCATON rw71 \\\�—�jj1J lL`AL MpCATOR CONTROL f A•w�.w� _ __ —s.m � !Y y®., S[wS0 &so —1 Gummy VKVF (--NQ / 1 / O PII[SS-SEAL 6ASRET / wrr r am.er ; swr a.ss IK.P1 / :. //i j/ % �ATBC ASSOCIATES. INC. nft w Mr M. VOW Of METER AND i.s VAIN DETALS OOUrARISON ..o w. / _ r. w.... cm Sd11bGt%m WELL VALLT[MJ �pL►pNp1WTE�1r�a�TrR nnr RAN VlY/�. tM�O1. eRwAan � /T� _ f��YPw""'^ DRAYM BY: BK APPRO D BY: MJK f"OPOSED DE'JK]IV 17 DATE: 1 17 95 FILE: SI07-9A-Tloow 'AF Memorandum October 27, 1994 p3"A • TO: Richard B. Helwig, City Manager FROM: Raymond H. Moller, Director of City Properties SUBJECT: Revisions to the Groundwater Remediation System , South Grove Avenue The original system that was designed and presented to the City Council for groundwater remediation at the South Grove riverboat redevelopment site called for - the direct discharge of contaminated groundwater into the sanitary sewer system. Following the approval of the plan and the authorization to proceed, some concern developed regarding the possibility that the Fox River Water Reclamation District may raise the rates that they were charging to treat the discharge of con- taminated materials into their system. In anticipation of a possible change in this area, a number of modifications were made to the originally designed sys- tem. The consultant, ATEC i Associates, was asked to design flexibility into the system. The revised groundwater remediation system that has been installed provides for the following: l. Direct discharge into the sanitary sewer system. 2. Discharge into an as yet constructed optional treatment system, which then would allow for discharge into the' Fox River. 3. Direct discharge of the groundwater into the Fox River. The increased flexibility of design has resulted in added material costs for piping, wiring and other related hardware, and also additional excavation of contaminated soils and the necessary fill for the excavation that was created. The cost of the system that was originally designed was ap- proximately $222,000. The current estimate for the revised system is $350,000. a j :tichard B. Helwig October 27, 1994 Page Z The Illinois Environmental Protection Agency (IEPA) has ap- proved the installation of the revised system and it is antic- ipated that the increased costs will be reimbursable from IEPA. . The impending opening of the riverboat development required the prompt installation of the revised system. It also should be noted that it is anticipated that the annual operat- ing costs of the groundwater treatment system could be re- duced if Option 3 of the design system is implemented, that being direct discharge into the Fox River. The system would have to be up and operating for a given period of time and the groundwater treated before permits could be sought from the appropriate state agencies for direct discharge into the river. Raymonf H. Moller Directbr of City Properties RHM:amp ELGIN, ILLINOIS ADDITIONAL SERVICES FOR 206 - 280 SOUTH GROVE AVENUE CHANGE ORDER NO. 2 SCOPE: This Change Order No. 2 covers additional services related to the installation of a groundwater remediation system at the City of Elgin properties located at 206-280 South Grove Avenue under a con- tract awarded on February 10, 1994 . The Contractor for this project is ATEC Associates , Inc . of Downers Grove, Illinois . REASONS FOR CHANGE: This Change Order is required for the additional costs necessary to implement and complete the corrective action plan submitted to the Illinois Environmental Protection Agency ( IEPA) . All of the following tasks which have been or will be completed pursuant to this change order have been or will be constructed in accordance with the as- built plans dated January 17 , 1995, which are attached hereto and made a part hereof by this reference as Exhibit "A" . TASKS: 1 . Measure Water Levels and Sample Groundwater from Monitor- ing Wells ATEC performed groundwater sampling of the monitoring wells at the South Grove Avenue property. Due to damage of two monitoring wells, sampling could not be performed resulting in a reduction of $3,684 .75 to this task. 2 . Perform Slug Tests on Six Monitoring Wells ATEC performed slug tests on the monitoring wells at 280 South Grove Avenue (former Bunge Tire) , however the datalogger and computer were not operative and thus was not charged to the project. This resulted in a reduction of $715 .00 to this task. 3. Perform Geotechnical Soil Testing ATEC collected soils samples for geotechnical soil test- ing during well installation at 280 South Grove Avenue (former Bunge Tire) . This lowered the cost incurred for this task since a drill rig and crew were not charged to this task. This resulted in a reduction of $2,646 .00 to this task. 4 . Additional Design of Groundwater Remediation System ATEC originally budgeted 300 hours for this task for the design of the groundwater remediation system (original contract) . At the time of the authoriza- tion from the City Council, the amount of hours for design was based upon a design of a groundwater interceptor trench and two groundwater extraction wells . ATEC completed the design of the system, and discussed the design and installation with the City of Elgin and Elgin Riverboat Resort. Elgin Riverboat Resort expressed concern with caving of the trench walls due to their experience with the installation of a deep sanitary sewer along the river. Since the CAP approval from the IEPA would take several weeks, and the groundwater remediation system needed to be installed prior to the opening of the Grand Victoria Casino, all parties felt that a different system may be. more prudent. The concern was that if difficulties were experienced with the installation, there would not be sufficient time for a resubmittal of the CAP and construction, and thus the opening of the Grand Victoria Casino would be delayed. ATEC then designed a groundwater system consisting of two trenches and five ground water extraction wells . This design was presented to be installed to the City Council as Change Order No. 1 . Since ATEC had completed the original design, most of the hours budgeted had been utilized. Since it was necessary not to delay the opening of the Grand Victoria Casino, the additional design work was completed by ATEC and the CAP was submitted to the IEPA and was subsequently approved. At the time of the submittal of Change Order No. 1, ATEC was still in the process of design work and was awaiting IEPA comments and changes . Therefore, the additional hours were not included with Change Order No. 1 . Subsequent to the second revision, concerns we raised regarding system annual operating costs, it was necessary to revise the groundwater remediation system after the approval of Change Order No. 1 . The revised groundwater remediation system design included two groundwater piping headers, and a valving system that allowed water extracted from the wells to move into either pipe, creating discharge options . Alter the approval from the IZPA, iz was necessary to receive two additional major permits from the IEPA water section and FRWRD. Additional time ( 100 hours) was necessary for the preparation of the permits . Due to involvement of the agencies, it was mandated that additional safety features to be built into the system. This included making the system explosion proof, and the installation of lower explosive level (LEL) meters into each of five well vaults, two meter vaults and the sanitary sewer discharge point. One additional precast concrete sampling manhole was also installed at the request of FRWRD. ATEC' s original estimate of 256 hours of engineering time was exceeded by 660 hours ( for a total of 916 hours ) . This time was exceeded due to the prepara- tion of three groundwater designs (rather than one) , and the submittal of two Corrective Action Plans and associated correspondence to the IEPA. It should be noted that the second and subsequent third design was more technically involved requiring more time than the preceding design. These design changes resulted in an addition of $45,696 . 35 to this task. 5 . Install Nine Groundwater Monitoring Wells ATEC and their subcontractor drillers were able to complete the installation of the groundwater moni- toring wells in less time than anticipated. In addition, a modification was made in the protective coverings for the wells which reduced the cost for this task by $5,708.75. It should be noted that a mathematical error of $10,530. 00 was added into this task. The total of these changes resulted in a reduction of $23,310 .47 to this task. 6 . Install One Extraction Well and Perform Pump Test Due to the increased flow rate encountered in Ex- traction Well #1, additional time was required to perform the pump test and to determine the flow rate. The type and size of the pump also changed resulting in an additional cost. The total of these changes resulted in an addition of $772.45 to this task. 7 . Install Four Extraction Wells - Due to the increased flow rates anticipated, the extraction well size was increased. In place of 4-inch diameter stainless steel wells, 6-inch stain- less steel wells were installed. Additional costs for material and labor were incurred. Due to the increased sizes of the wells, increased costs were incurred to develop the wells . Drilling and over- sight costs increased, as well as cutting and devel- opment water disposal costs . The total of these changes resulted in an addition of $9,213 .42 . 8 . Construct Groundwater Piping and Electrical Trenches Following the installation of the groundwater ex- traction wells, the remaining portions of the groundwater remediation system were installed. Due to the change in the groundwater remediation system design, additional costs were incurred. a) Excavation of the groundwater piping trench was increased in length by 270 feet. The design approved in Change Order No. 1 called for two trenches, one of approximately 270 and another of 335 feet in length, with one groundwater extraction pipe in the trench. The revised groundwater remediation system was constructed with one continuous trench. This as-built trench was now increased to a length of 875 feet. Two pipes were installed in the trench, three to four times the larger than originally proposed. Due to the increase in the number and size of the pipes, the width of the trench was also increased. Excavation was necessary under a water main, which made it necessary to use piping that met specifications for con- struction of water and sewer mains in Illinois . b) Since the revised groundwater remediation system design included two groundwater piping headers, and a valving system to add flexibili- ty in discharge options, material amounts and installation costs increased. C) Due to the time constraints of installing the groundwater system prior to the opening of the Grand Victoria Riverboat, the installation of the system include overtime and weekend work, which increased labor and equipment costs . d) Due to the additional length and width of the groundwater remediation trench, additional soils were removed from the site, increasing the cost of the project. The amount of soil excavated and disposed increased to 1025 cubic yards from the original estimate of 400 cubic yards. Additional backfill was also required. e) Due to the increased power required for the larger pumps, the wire and conduit sizes in- creased. Additional electrical costs were incurred due to the necessary installation of LEL meters in each of the vaults, installation of a 200 Amp (vs . 100 Amp) service. The total of these changes resulted in an addition of $138,754 . 20 to this task as shown on the accompa- nying sheet. 9 . Construction Preparation and Construction Oversight Due to the change in the design of the groundwater remediation system, the time necessary to complete the installation of the system increased due to the complexity and additional work necessary. ATEC' s staff time necessary for construction preparation and construction oversight was increased. In addi- tion, due to time constraints, the material for construction had to be scoped out and ordered by ATEC during the construction. This additional time increased ATEC' s time from 360 hours to 855 hours . The total of these changes resulted in an addition of $38, 164 . 15 to this task as shown on the accompa- nying sheet. 10 . Prepare 0 & M Manual Due to the addition of meters and the change in the design of the groundwater remediation system, addi- tional time will be necessary to complete the Opera- tion and Maintenance (0 & M) Manual . The total of these changes resulted in an addition of $1, 300 . 00 to this task as shown on the accompanying sheet. SUMMARY OF CHANGES IN CONTRACT AMOUNT: The project was contracted with a total of 10 tasks . Task 1 through Task 4 were the original contract (development of CAP) . Task 5 through Task 10 were Change Order No. 1 (imple- mentation of CAP) . The amount of contract will be revised as follows : ITEM COST CHANGE Task 1 Subtract $ 31684.75 Task 2 Subtract $ 715.00 Task 3 Subtract $ 2,646 .00 Task 4 Add $ 45,696 .35 Task 5 Subtract $ 23,310.47 Task 6 Add $ 772 .45 i e�ao 9,213 .4 2 Task 8 Add $ 138,754 .20 Task 9 Add $ 38, 164 . 15 Task 10 Add $ 1,300.00 Total Add $ 203,544 . 35 The present contract with ATEC is for $260,447 . 75 . By reason of Change Order No. 2 the contract for the additional services will be increased in the amount of Two Hundred Three Thousand Five Hundred Forty Four and 35/100 Dollars ( $203,544 . 35). The new revised contract total will be an amount of Four Hundred Sixty Four Thousand Twenty Two and 10/100 Dollars ($464 , 022 . 10) . OTHER CONTRACT PROVISIONS: All other contract provisions of the original contract agreement of February 9, 1994 , shall remain the same and in full force and effect for the addition- al work to be performed under this change order. Agreed to this day of January, 1995 . Recommended: City of Elgin By: Date: Accepted: ATEC Associates, Inc. Party of the Second Part (Contractor) By: Title: Date: Approved: City of Elgin Party of the First Part (Owner) By. Title: Date: �ity of Elgin - South Grove Avenue Properties ;roundwater Corrective Action Plan Estimated/Actual Cost Comparison Estimated Actual Item Cost cost Task 1 - Measure and Sample Water ATEC Costs Principal Engineer/Scientist $95.00 $0.00 Project Engineer/Scientist $260.00 $130.00 Staff En ineer $2,750.00 $2,681.25 Vehicle $165.00 $110.00 Disposable Bailer $136.00 $56.00 Sample Shippin $255.00 $105.00 BTEX An sis (Water) $990.00 $330.00 PNA Analysis Water $1,188.00 $594.00 Lead Analysis (Water $66.00 $33.00 Metals Anal sis (Water $1,078.00 $924.00 Semi-Volatile Analysis Water $2,255.00 $1,353.00 Volatile Analysis (Water) $907.50 $544.50 Hardness/Alkalinity (Water) $300.00 - $0.00 Material and Supplies $100.00 $0.00 Total Cost - Task 1 $10.545.50 S6 860.75 Task 2 - Perform Slug Tests ATEC Costs Principal Engineer/Scientist $95.00 $95.00 Project Engineer/Scientist $130.00 $0.00 Staff En ineer $2,200.00 $2,275.00 Datalogger & Transducers $400.00 $0.00 Portable Computer & Software $150.00 $0.00 Slug & Water Level Equi ment $100.00 $0.00 Decontamination E ui ment $50.00 $0.00 Vehicle $110.00 $150.00 Total Cost - Task 2 $3,235.0011 $2,520.00 Task 3 - Perform Geotechnical Soil Testing Subcontractor Costs Mob/Demob $162.00 $0.00 Drillin $486.00 $0.00 Steam Cleanin $216.00 $0.00 Steam Cleaner $108.00 $0.00 Grout Bori s $162.00 $0.00 Shelb Tubes $60.00 $0.00 Failing Head Permeabilit $880.00 $0.00 Sieve/H drometer Analysis $302.50 $300.00 Atterber Limits $192.50 $88.00 ATEC Costs Principal Engineer/Scientist $95.00 $0.00 Project Engineer/Scientist $130.00 $130.00 Staff Engineer $550.00 $390.00 Vehicle $55.00 $0.00 OVM $75.00 $0.00 Sample Shipping $30.00 $0.00 Material and Supplies $50.00 $0.00 Total Cost -Task 3 $3,SS4.001 $908.00 ity of Elgin - South Grove Avenue Properties Groundwater Corrective Action Plan Estimated/Actual Cost Comparison Estimated Actual Item Cost Cost_ Task 4 - Submit CAP for IEPA Approval ATEC Costs Principal Engineer/Scientist $3,800.00 $3,413.75 Senior Project Engineer/Scientist $1,440.00 $2,625.00 Project Engineer $13,000.00 $58,171.25 CAD Draftsman $2,400.00 $1,920.00 Clerical 00.00 $62.50 Material 00.00 $543.85 Total Cost - Task 4 j$2j1,040.00 $66,736.35 Task 5 - Monitoring Well Installation Subcontractor Costs Mobilization/Demobilization $500.00 $890.00 Drilling $5,250.00 $2,739.50 2" dia., Schedule 304 SS Screen $3,795.00 $2,851.00 2" dia., Schedule 304 SS Riser $1,202.50 $942.13 2' dia., Schedule 304 SS Plug and Ca $333.00 $318.00 Sand Pack $978.75 $566.00 Bentonite Pellet Seal $1,134.00 $839.30 Volclay Grout $240.00 $75.60 Expandable Cap , $110.25 $30.00 Steam Cleaner $500.00 $410.00 Decontamination $1,170.00 $527.25 Well Installation $3,510.00 $2,935.00 Handholes $6,750.00 $1,041.25 Drums $270.00 $340.00 Well Abandonment $1,500.00 Subcontractor Subtotal Task 5 $25,743.50 $16,005.03 ATEC Costs Well Installation Principal Engineer/Scientist $760.00 $0.00 Project Engineer/Scientist 1 $5,850.00 $5,380.00 Vehicle $675.00 $225.00 OVM $1,125.00 $0.00 r::3�ell Development/Sampling Staff Engineer/Scientist 1 ! _$2,750-00, _$4,771.25 Dedicated Bailer $1,293.75 $25.50 Vehicle $375.00 $150.00 H, Temp., Conductivity Equipment $150.00 $240.00 Laboratory Analysis Attachment A Constituents $6,885.00 $6,120.00 Sample Shipping $90.00 $0.00 ATEC Subtotal Task 'S $30,483.75 $15,91. 1.75 rotal'Cost - Task 5 $56,227.25 $32,916.78 ity of Elgin - South Grove Avenue Properties ,roundwater Corrective Action Plan Estimated/Actual Cost Comparison Estimated Actual Item Cost Cosh. Task 6 - Install Deep Well and Perform Pum Test Mobilization/Demobilization $250.00 $1,770.00 HSA w/CSSS $1,435.00 $1,702.00 4' dia., Schedule 304 SS Screen $1,687.50 $725.00 4' dia., Schedule 304 SS Riser $330.00 $228.00 4' dia., Schedule 304 SS Plu $43.00 $20.00 Ca PVC $15.75 $0.00 Sand Pack $283.50 $283.50 Bentonite Pellet Seal $126.00 $0.00 Volclay Grout $96.00 $0.00 Steam Cleaner $100.00 $100.00 Decontamination $130.00 $0.00 Well Pump and Controller $5,000.00 $1,121.74 Well Installation $390.001 $0.00 Drums $30.001 $90.00 Well Vault $1,850.001 $2,594.32 Subcontractor Subtotal Task 6 $11,766.75 $8,634.56 ATEC Costs Well Installation Principal Engineer/Scientist $190.00 $0.00 Project Engineer/Scientist 1 $780.00 $600.00 Vehicle $75.00 $75.00 OV M $125.00 $0.00 Well Develop ment/Samplin Staff Engineer/Scientist I $330.00 $2,268.75 Dedicated Bailer $143.75 $0.00 Vehicle $75.00 $95.90 H, Temp., Conductivity Equipment $30.00 $0.00 Perform Pump Test Principal Engineer/Scientist $300.00 $0.00 Project Engineer/Scientist 1 $3,120.00 $5,525.00 Vehicle $300.00 $0.00 Equipment for Pump Test $1,000.00 $1,808.74 ATEC Subtotal Task S $6,468.75 $10,373.39 Total Cost - Task 6 $18,235.50 $19,007.95 ity of Elgin — South Grove Avenue Properties Groundwater Corrective Action Plan Estimated/Actual Cost Comparison Estimated Actual Rem Cost Coa1tR' Task 7 — Install Four Extraction Wells Mobilization/Demobilization $250.00 $1,200.00 HSA w/CSSS $4,305.00 $2,462.50 4' dia., Schedule 304 SS Screen $6,075.00 $5,400.00 4' dia., Schedule 304 SS Riser $687.50 $925.00 4' dia., Schedule 304 SS Plug $172.00 $0.00 Cap PVC $63.00 $96.00 Sand Pack $1,029.00 $582.00 Bentonite Pellet Seal $504.00 $0.00 VoIclay Grout $120.00 $0.00 Steam Cleaner $400.00 $300.00 Decontamination $520.00 $390.00 Well Pump and Controller $5,000.00 $4,487.00 Well Installation $2,080.00 $10,082.90 Drums $120.00 $0.00 Well Vaults $7,400.00 $10,377.27 Subcontractor Subtotal Task 7 $28,725.50 $36,802.67 ATEC Costs Well Installation Principal En ineer/Scientist $570.00 $0.00 Project Engineer/Scientist 1 $3,900.00 $6,906.25 Vehicle $300.00 $0.00 OVM $500.00 $0.00 ATEC Subtotal Task 7 $5,270.00 56,906.25 Total Cost — Task 7 $33,995.50 $43,208.92 Task 8 — Construct Groundwater Piping and Electrical Trenches Trenching (600'x2'x4' and 300'x1'x3') $6,000.00 $36,897.50 Soil Loading, Trans oration and Disposal $18,000.00 $47,891.25 Schedule 80 PVC Piping $10,000.00 $44,322.36 Backfill Trench $8,800.00 $12,576.41 Meter Vaults $3,700.00 $6,573.00 Instrumentation $12,000.00 $2,412.05 Electrical Contractor and Heat Tracing $16,000.00 $69,959.00 Stepdown Transformer 480/230 $5,000.00 $0.00 _ _ Insulation, $4,000.00 $1,6 2 2.63 Total Cost - Task 8 $83,500.00 $222254.20 r1ty of Elgin — South Grove Avenue Properties *;roundwater Corrective Action Plan Estimated/Actual Cost Comparison Estimated Actual ........ ..... Item Cost cost. Task 9 — Construction Preparation and Construction Oversight Principal Engineer/Scientist $4,800.00 $2,662.50 Project Engineer/Scientist II $19,500.00 $60,017.00 Draftsperson—CAD $1,600.00 $1,180.00 Clerical $120.00 $210.00 Vehicle $1,125.00 $1,239.65 Total Cost — Task 9 $27,145.00, $65.309-W Task 10 — Prepare 0 & M Manual Principal Engineer/Scientist $320.00 $320.00 Project Engineer/Scientist 11 $1,950.00 $3,250.00 Draftsperson—CAD $400.00 $400.00 Clerical $180.00 $180.00 Copies $150.0011 $150.00 Total Cost — Task 10 $3,000.0011 $4,300.00 Total Cost $260 477.775]1 $464,022._l OJ SOD k IOPSOIL - SOD. TOPSOIL COMPACTED SOIL Q_ BY OTHERS 1 ii COMPACTED SANG j�-T--PEA GRAVEL / OR GRAVEL NATIVE MATERIALS / \ ATIVE MATERIALS 4.0' .,.4.0' \� Ct 1-1/2" TO 2" SCH. 40 i. —I" AND 1-1/4" � PVC PIPE RIGID METAL CONDUIT U C\ NUMBER OF CONDUITS I �( N TRENCH VARIES, SEE PEA GRAVEL �y ELECTRICAL PLAN VIEW) \/ BEDDING PEA GRAVEL / \ � 6" SDP 26 PVC PIPE BEDDING � 6" OR 8" SDR 26 PVC PIPE SECTION 4E QPAX QWATER EPM AIMrf FL Fl`TFY[=�1 TW.NQI. r FqrmMNQ AND AS-BINL T FINAL &2QN PRQPOISED DESK]N 51DEUALK Ty LL MOUND SURFACE n aaa FROM EU111AC110N eRiiS FROM EXTRACTION WELL 4.0' -- — AND METER VAULT VAULT SA NITARY W 4 MANHOLE LAID aele SEVER VAULT e•U 12• MY�I IN. REDUCERS S/JIOUIIG AYD MR FvII. OUT YANH4E Ix'SGR I NOT TO SCALE PRESSURE PIPE GROUNDWATER SANITARY - GROUND—TER Ix'SDR xe DIS04ARGE PIPE MANHOLE OIS04-CE WK ►RESSUIE PIPE (SCH.s0 PVC)G.s0R xe DRAIN - QROUPIDWATER F'PNO AND --x•D L PIPf PMESS/RE PIPE EUPANDAOLE BDQT SANITARY I" SPACE ELECTRICAL TmNCM DETAL8 REQUIRED wm ANNULAR SPACE �. _ OR RIVED CMARAFrBON GROUTED CITY CF ELcm CMVY-0 MATER TREATMENT SYSTEM[MOON �— 6.0' 6.0' —� DATE: 1/17/9 -9+-0000+ M*fQLE_AW Tr--ft 1TY�1 IRE�1_iQ SANITaf1Y M nE:� noewr FIGURE lA 2777 Finley Road Suite 06 AT='-- FI/VAL_.Q€SIC N PROP0.SED DES1CiN Downers Grove. Illinois 60515 v PA(7N)vu-nn •Las:(7F8)11F-701 1 r A►�L1 A��LT ^04MLT 004RLT Y" JMf'ra+r A�r�n 4ID1000lJltiveLLl�IO was.r rrr n ausr er.PrA As•r w r ' IY ,..-r w,� . / wYly •:ii�r...A,wPw� / lu ..,.'ww w. wlW ,P� ,r.pA 1✓,W.rwA Mw. r • Y I,.IArwA op.A , 7♦/II.r wwrl L ? wr MlAlw , / ��, PAY � '/ �/ / � ��•�\\ 1 w, iw A� / '/J 1 Meg. _'r •..m '.•,n.s...i�., I r.�'traw— IL I _ rrLe wi ncrwi -F m �w .rarw� __.— ♦r w Kr Pier+ert - - rri�.o n\s--_-•--_. TT7TTT7T�r7Tl ucnAr. T7 s,nA 1 EMQ 4 rrEOLrarr AlSLT AMLT N PALL VALVE.NORMALLY OPEN •,•.•w.rrrPw. „r�r PALL VALVE•NORMALL Y CLOSE] N ONEC%VALVE wPrr•r n rAw Ta.+�wr wr. rAa.r w rrw .ter Mi"���iwi MOTOpt FLOW VACUUM MI[ArtU Rww .-.R..-rR r�F1 /� T � �ROrI IMpCA1p110IY1IE11 w AYw !w - �/ w a• '// ®®®®SAMPLE PONT rwra r TEMPERATURE PIOICATdI PRESW K OWCATOR LEVEL PrOICATM CONTWOL r�rr�,r.v r.r Aa Q LO".IS`, dr LAPT xnsa�error PUT7 ,VALK PP[ss-s[AL sASPEr srorr CLASS ..fir rair �i 'C r.- r°" - �- � / ! ATEC ASSOCIATES, INC. frn rry 1rL l�K www.Uwe t NErA wr..fwq saran►..1►srU Pn-nn raw / - —,,.wsA.e... 4- ---- -. __—�- - - - ----- — V r EW O ALTER AND i VAULT DETAILS COIrARISOW OEv Or LCM rLAK MRW )r RKjMLCnM WELL.YALLIffWJ a1101IOwIL7r111�1LTr1I M1K1 Tr r w r.c..a OOEM�tlI�W� / row... DRAWN BY: K APPFI 7- M00 � -�-- -y- QOE�Y DATE' 1 717195 FlLE: 5107-fs-000OA ,�.•'�� u.0 A AB'JAUI 110