HomeMy WebLinkAbout26-50 Resolution No. 26-50 RESOLUTION AUTHORIZING EXECUTION OF A CHANGE ORDER NO. 1 WITH LAMP, INC. FOR WING PARK GOLF COURSE CLUBHOUSE (Bid No. 25-034) WHEREAS,the City of Elgin has heretofore entered into a contract LAMP, Inc. for Wing Park golf course clubhouse(Bid No. 25-034); and WHEREAS,it is necessary and desirable to modify the terms of the contract as is described in Change Order No. 1 attached hereto. NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF ELGIN,ILLINOIS,that Richard G.Kozal,City Manager,be and is hereby authorized and directed to execute Change Order No. 1, a copy of which is attached hereto and made a part hereof by reference. s/David J. Kaptain David J. Kaptain, Mayor Presented: March 25, 2026 Adopted: March 25, 2026 Omnibus Vote: Yeas: 9 Nays: 0 Attest: s/Kimberly Dewis Kimberly Dewis, City Clerk `(OF E(.C� `1. City of Elgin Change Order ELGIN, ILLINOIS PROJECT: WING PARK GOLF COURSE CLUBHOUSE CHANGE ORDER NO. 1 CONTRACT: Wing Park Golf Course Clubhouse—Bid No. 25-034 SCOPE: To accept and approve the purchase and installation of food service equipment for the new golf course clubhouse by Hargrave Builders in accordance with Alternate No. 4 of Bid No. 25-034. REASONS FOR CHANGE: In discussions with the city's selected operator for the clubhouse, it was determined that the installation of the food service equipment provided for in Alternate No. 4 would be necessary for the successful operation of food service at the clubhouse. The circumstances said to necessitate the change in performance were not reasonably foreseeable at the time the contract was signed; the change is germane to the original contract as signed; and the change order is in the best interests of the City of Elgin and authorized by law. SUMMARY OF CHANGES IN CONTRACT AMOUNT: The total construction costs for the project are being increased by $156,000. This will provide for the purchase of the food service equipment provided for in Alternate No. 4 for the new clubhouse. ORIGINAL CONTRACT AMOUNT: $3,790,164.50 CHANGE ORDER NO. 1 Foord Service Equipment—Alternate No.4 $156,000 TOTAL FOR CHANGE ORDER NO. 1 ADD $156,000 PREVIOUS CHANGE ORDER(S): N/A TOTAL REVISED CONTRACT AMOUNT: $3,946,164.50 The total construction costs under Bid No. 25-034 were in the total amount of$3,790,164.50. Change Order No. 1 approving Alternate No. 4 will increase the total construction costs by a total of$156,000, that sum representing 4.1%of the original total construction costs. The total amount of the construction costs under Bid No. 25-034, inclusive of all change orders, is $3,946,164.50. OTHER CONTRACT PROVISIONS: As a result of the change order and the approval of Alternate No. 4, the construction management fees for Lamp, Inc., the construction manager for the project pursuant to the construction management agreement between the parties will increase by $5,898.75. In addition, the design fees for FGM Architects, Inc., the architect for the project, will need to be increased by $7,285.00 under the engineering services agreement between the parties. All other contract provisions remain the same. CHANGE ORDER NO. 1 Agreed to this day of , 2026. Recommended by: Parks and Recreation Department By: Mike Lehman Title: Director of Golf Operations Date: 3-16-2026 Signature: 2 4 a— rnaof, Accepted by: LAMP, INC. Party of the Second Part (Contractor) By: Greg Bohlin VP of Construction Title: Date: 3/17/26 Signature: Approved by: CITY OF ELGIN Party of the First Part(Owner) By: Richard G. Kozal Title: City Manager Date: Marc 2026 Signatur : .1‘0e Legal DepWgreanmlChange Ordn No I.W,ng Perk OoU Came CluNwuae.Bid No 25-074 3.16'26 do.