HomeMy WebLinkAboutIDOT 25-0523 Illinois Department of Transportation
Office of Highways Project Implementation/Bureau of Construction
2300 South Dirksen Parkway/Springfield, Illinois 62764
May 23. 2025
SUBJECT: Notification to Maintain
Kimberly Dewis
City of Elgin
150 Dexter Court
Elgin, IL 60120
Dear City Clerk:
The following contract has been satisfactorily completed and accepted by the
Department of Transportation:
Route: FAU 1320
Contract: 62M23
County: Cook
Illinois Project: STP-G206 / 950 /
Section: 2020-185-SW&TS
The agreement entered into between the State of Illinois and the City of Elgin
details maintenance responsibilities for the completed improvement. Please
refer to the agreement for this information.
Sincerely,
Justan Mann
Engineer of Construction
cc: Jose Rios
Amy Eller Attn: Kyle Armstrong
. Bureau Chief of Local Roads and Streets
Construction Finals Accountant
DTGI2236:BCMR036 ILLINOIS DEPARTMENT OF TRANSPORTATION
05/22/25 13:20 :25 FINAL ACCEPTANCE OF IMPROVEMENT
IMPROVEMENT FUNDED BY: FEDERAL, STATE, ELGIN
TO CONTRACTOR:
H & H ELECTRIC COMPANY
2830 COMMERCE ST
FRANKLIN PARK IL 60131-2927
DESIGNATION BY DEPARTMENT OF TRANSPORTATION
ROUTE: FAU 1320
SECTION: 2020-185-SW&TS COUNTY: 031 COOK
PROJECT: STP-G206/950/
CONTRACT: 62M23 JOB: C-91-346-20
TYPE OF IMPROVEMENT:
TRAFFIC SIGNAL MODERNIZATION AND ADA CURB RAMP IMPROVEMENTS AT THE INTERSECTION
OF IL ROUTE 58 AT SHADY OAKS DRIVE IN ELGIN, COOK COUNTY.
TOTAL COST: 309, 109.68
May 22, 2025
THIS WORK HAS BEEN SATISFACTORILY COMPLETED IN REASONABLE CLOSE CONFORMITY
WITH ALL OF THE REQUIREMENTS OF THE CONTRACT AND IS HEREBY ACCEPTED BY THE
DEPARTMENT OF TRANSPORTATION.
(A , M
ENGINEER F CONSTRUCTION S
tv
COPIES TO:
BUREAU OF PROGRAMMING RENEE STANTON
ENGINEER OF DESIGN & ENVIRONMENT JACK ELSTON
REGIONAL ENGINEER, DISTRICT 01 JOSE RIOS & DST 1 LOC RD OFFICE
ENGINEER OF OPERATIONS KYLE ARMSTRONG
ENGINEER OF LOCAL ROADS
LOCAL AGENCY OFFICIAL ELGIN
FILE BC-107 (REV. 02/20)
BCMS2257:BCMR057 STATE OF ILLINOIS
05/22/25 11:48:20 DEPARTMENT OF TRANSPORTATION DOC ID: 0000 000000000
CONTRACTOR INVOICE
DOT VENDOR: C25500 CONTRACT NBR: 62M23
FROM DATE: 05/01/23
ROUTE: FAU 1320 TO DATE: 05/01/23
SECTION: 2020-185-SW&TS STATE JOB: C-91-346-20
PROJECT: STP-G206/950/ DIST/CNTY: 01 031-COOK
PAYEE: CONTR:
H & H ELECTRIC COMPANY H & H ELECTRIC COMPANY
2830 COMMERCE ST 2830 COMMERCE ST
FRANKLIN PARK IL 60131-2927 FRANKLIN PARK IL 60131-2927
PERCENT COMPLETED 100.00 % NET CHANGE TO DATE -1.51 % LOCAL AGENCY PART
CONTRACT I I ITOTAL ADJUSTED I TOTAL AMOUNT
FAS-ID I AWARDED AMT I ADDITIONS I DEDUCTIONS (CONTRACT VALUE I DUE TO DATE
Z23EUO1I 290,789.64 I 20,337.861 25,389.571 285,737.931 285,737.93
Z23EU02I 17,621.20 I 340. 15I 34 .00I 17, 927.351 17, 927.35
07POUO1I 5,451.70 I 1. 10 8.40I 5,444.401 5,444 .40
TOTAL I 313, 862 .54 I 20,679. 111 25,431.971 309, 109.681 309, 109.68
TOTAL RETAINAGE INCLD THIS EST 0.00
TOTAL DUE AFTER RETAINAGE 309, 109.68
TOTAL PAID INCLD THIS ESTIMATE 309, 109.68
PREVIOUS PAYMENTS TO CONTRACTOR -309, 109.68
PAYMENT TO CONTRACTOR THIS ESTIMATE > 0.00
ZERO PAYMENT
APPROPRIATION: 011-49442-7900-0021 7721 ZERO PAYMT 1 OF 1 $ 0.00<==
SCHEDULE:
FINAL ESTIMATE 5 TOTAL $ 0.00
*******************************************************
* FILE COPY *
*******************************************************
Illinois Department of Transportation
Office of Highways Project Implementation I Bureau of Construction
2300 South Dirksen Parkway/Springfield, Illinois 62764
May 23, 2025
SUBJECT: Notification to Maintain
Kimberly Dewis
City of Elgin
150 Dexter Court
Elgin. IL 60120
Dear City Clerk:
The following contract has been satisfactorily completed and accepted by the
Department of Transportation:
Route: FAU 1320
Contract: 62M23
County: Cook
Illinois Project: STP-G206 / 950 /
Section: 2020-185-SW&TS
The agreement entered into between the State of Illinois and the City of Elgin
details maintenance responsibilities for the completed improvement. Please
refer to the agreement for this information.
Sincerely.
Justan Mann
Engineer of Construction
cc: Jose Rios
Amy Eller Attn: Kyle Armstrong
, Bureau Chief of Local Roads and Streets
Construction Finals Accountant
DTGI2236:BCMR036 ILLINOIS DEPARTMENT OF TRANSPORTATION
05/22/25 13 :20:25 FINAL ACCEPTANCE OF IMPROVEMENT
IMPROVEMENT FUNDED BY: FEDERAL, STATE, ELGIN
TO CONTRACTOR:
H & H ELECTRIC COMPANY
2830 COMMERCE ST
FRANKLIN PARK IL 60131-2927
DESIGNATION BY DEPARTMENT OF TRANSPORTATION
ROUTE: FAU 1320
SECTION: 2020-185-SW&TS COUNTY: 031 COOK
PROJECT: STP-G206/950/
CONTRACT: 62M23 JOB: C-91-346-20
TYPE OF IMPROVEMENT:
TRAFFIC SIGNAL MODERNIZATION AND ADA CURB RAMP IMPROVEMENTS AT THE INTERSECTION
OF IL ROUTE 58 AT SHADY OAKS DRIVE IN ELGIN, COOK COUNTY.
TOTAL COST: 309, 109.68
May 22, 2025
THIS WORK HAS BEEN SATISFACTORILY COMPLETED IN REASONABLE CLOSE CONFORMITY
WITH ALL OF THE REQUIREMENTS OF THE CONTRACT AND IS HEREBY ACCEPTED BY THE
DEPARTMENT OF TRANSPORTATION.
ENGINEE' tF CONSTRLIEN
COPIES TO:
BUREAU OF PROGRAMMING RENEE STANTON
ENGINEER OF DESIGN & ENVIRONMENT JACK ELSTON
REGIONAL ENGINEER, DISTRICT 01 JOSE RIOS & DST 1 LOC RD OFFICE
ENGINEER OF OPERATIONS KYLE ARMSTRONG
ENGINEER OF LOCAL ROADS
LOCAL AGENCY OFFICIAL ELGIN
FILE BC-107 (REV. 02/20)