HomeMy WebLinkAbout99-34 Resolution No. 99-34
RESOLUTION
APPROVING CHANGE ORDER NO. 1 IN THE CONTRACT WITH
UTILITY DYNAMICS CORPORATION FOR THE
TROUT PARK LIGHTING PROJECT
WHEREAS, the City of Elgin has heretofore entered into a
contract with Utility Dynamics Corporation for the Elgin
Oaks/State Street Conduit Replacement Project; and
WHEREAS, it is necessary and desirable to modify the terms
of the contract to include the Trout Park lighting project as
is described in Change Order No. 1, attached hereto.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE
CITY OF ELGIN, ILLINOIS, that pursuant to Elgin Municipal Code
Section 5 . 02 . 020B( 6) the City Council hereby finds that an
exception to the requirements of the procurement ordinance is
necessary and in the best interests of the city; and
BE IT FURTHER RESOLVED BY THE CITY COUNCIL OF THE CITY OF
ELGIN, ILLINOIS, that Joyce A. Parker, City Manager, be and is
hereby authorized and directed to execute Change Order No. 1, a
copy of which is attached hereto and made a part hereof by
reference.
s/ Kevin Kelly
Kevin Kelly, Mayor
Presented: February 10, 1999
Adopted: February 10, 1999
Omnibus Vote: Yeas 6 Nays 0
Attest:
s/ Dolonna Mecum
Dolonna Mecum, City Clerk
•
..,
ELGIN, ILLINOIS
PROJECT 339581
CHANGE ORDER No. 1
SCOPE: This Change Order No. 1 will provide additional items
necessary to replace the antiquated electrical service and street
lights in Trout Park.
The general contractor for this project is Utility Dynamics
Corporation of Oswego, Illinois .
REASONS FOR CHANGE: This Change Order No. 1 will add additional
quantities to the contract for the replacement of the antiquated
electrical service and street lights in Trout Park. Elements of
this change order were not reasonably foreseeable at the time the
original contract was awarded.
SUMMARY OF CHANGES IN CONTRACT AMOUNT: The amount of the
contract will be revised as follows :
See Attachment A
The original contract with Utility Dynamics Corporation is
$96 , 981 . 50 . By reason of Change Order No. 1, the contract for
the Elgin Oaks Project will be increased in the amount of
thirty-four thousand and two hundred twenty-eight and 50/100
dollars ($34 , 228 . 50) . The new contract amount, inclusive of
Change Order No. 1 is one hundred thirty one thousand and two
hundred ten and 00/100 dollars ($131, 210 . 00)
CHANGE ORDER No. 1
Page 2 .
OTHER CONTRACT PROVISIONS: All other contract provisions shall
remain the same .
Agreed to thisgt;Bay of 7Q.( r ' 19911.
Recommended:
PARKS AND RECREATION DEPARTMENT
By: M& eWlah.
Title : Recreation & Facilities Supt .
Date : i i lc ( 611
Accepted:
UTILITY DYNAMICS CO'PORATION
Party of h- -co : Part (Contractor)
By;-- ,0 ' `A�j
Tit a Aj�r
2;t- : / h-
/
Approved:
CITY OF ELGIN
Partof the First P t (Owner)
By: 4.� Q .
i
Title: C.17)/ I L AA/4 (36W
Date : c,//„2/
CHNGORDR. 1/TEXT081/TROUTPRK
„,,,OF ECC.,
Agenda Item No. .--T
—City of Elgin
rCtp
°'
January 21, 1999
TO: Mayor and Members of the City Council
FROM: Joyce A. Parker, City Manager
SUBJECT: Revised Change Order No. 1 to the Elgin Oaks/
State Street Conduit Replacement Project for
Trout Park Lighting Improvements
PURPOSE
The purpose of this memorandum is to provide the Mayor and
members of the City Council with revised information relative
to Change Order No. 1 to the "Elgin Oaks Conduit Replacement
Contract” for Trout Park lighting improvements previously
approved by the City Council .
BACKGROUND
At the December 16 Committee of the Whole meeting, the Mayor
and members of the City Council approved a change order for
Trout Park lighting for $12, 171 .20 . This amount was for new
pay items such as light poles, new electrical services and
removal of existing equipment not included in the original
contract with Utility Dynamics for the Elgin Oaks conduit
replacement project . This change order should have included
approximately $22, 000 of additional cost covered by existing
contractual unit prices for conduit and fixtures . Overall,
the pricing included in the change order compare favorably
with bid awards for similar work.
The previous communication to the Mayor and members of the
City Council neglected to address the $22, 000 in additional
quantities. Therefore, the City Council should consider a
revised Change Order No. 1 totalling $34, 171 .20 .
COMMUNITY GROUPS/INTERESTED PERSONS CONTACTED
None .
FINANCIAL IMPACT
V(Ilik
The 1998 budget included $140, 000 for the Elgin Oaks street
light recabling project . The contract award was $96, 981 . 50,
leaving approximately $43, 000 to fund this change order.
Account number 395-1000-795 . 93-80, project number 509549, will
be charged.
Revised Change Order No. 1/Elgin Oaks
January 21, 1999
Page 2
LEGAL IMPACT
par
Approval of Change Order No. 1 under the terms of the City' s
Procurement Ordinance requires a two-thirds majority vote.
ALTERNATIVES
The City Council may choose to accept, deny or amend the
proposed change order.
RECOMMENDATION
It is recommended that the City Council approve Change Order
No. 1 for the Trout Park lighting project .
Re ectfully submitted,
a /Qui,
J ce . Parker
City Manager
amp
Attachment
r
r
•
UTILITY DYNAMICS CORPORATION
LIGHT &COMMERCE ROADS PHONE:
P.O. BOX#635 (630) 554-1722
OSWEGO, ILLINOIS 60543 FAX(630) 554-1195
ELECTRICAL CONTRACTORS • OVERHEAD LINE CONSTRUCTION • UNDERGROUND DISTRIBUTION SYSTEMS
November 5, 1998 7 ' *� , r„a( !q i s c?r,�� , Ut
City of Elgin
Lai
150 Dexter Court NOV 0 9 1998
Elgin, IL 601120-5555
CITY OF ELGIN
Attn: Charles Pitt FU."„LIC WORKS
Fax: 847-931-6041 (2 Pates Total)
Subject: Proposal - Trout Park Site Lighting
Charlie:
Utility Dynamics Corportion is pleased to provide the City of Elgin with our proposal for the
installation of the site-lightipg as indicated on the sketch provided to us during the site visit
rik. conducted.on-Noyember.;4th. . . ..... ...
In addition:to the applicable unit prices from.the ElginOaks project;the following unit prices shall
be utilized foi the Trout Park site lighting: .
1. Disconnect and remove the existing wood poles (7), overhead wire and
lighting L.S. $1680.00.
* Disposal of the removed equipment/material shall be by the City of Elgin.
* Add $510.00 if UDC is to supply a dumpster for the equipment/material disposal.
2. Install a new 120/240V underground service from the Corn Ed pole to the existing
meter pole L.S. $4150.00.
* Incl. directional bore under parking lot.
* Incl. 3 - 3/0 Cu. Type USE cable (good for 200A).
* Incl. the removal of the existing overhead service and riser.
* The City of Elgin shall be responsible for any Corn Ed fees.
3. Install a new 3 Wire underground service to Shelter#1 L.S. $2350.00.
* Incl. removal of the existing overhead service.
*.Incl. the removal and replacement of appx_ 12 S.F.: of the concrete floor in
the shelter, to facilitate the conduit riser at the wood beam/column.
*.Service shall tap:Off of.the pole closest to the shelter and is the same circuit as that
rik
which.feeds the new lights. .
. .
P.2 •
Utility Dynamics Corporation
Subject: Proposal - Trout Park Site Lighting
•
4. Added cost to pull an additional 1/C #8 to the shelter, if a 120/240V service
is required at this location $1.16/L.F. x 120F
$139. 20
5. Cost to install light pole and mast arm, furnished by the City of Elgin $310.00/ea. x 10=
* Pole shall match the bolt circle on the specified helix foundation. $3 , 100
* The cost for the pole wire and fusing is included in the luminaire unit price
from the Elgin Oaks project.
1
6. Cost to remove and reinstall the existing flood lights(2) on to the new:.
light poles $326.00/ea.x 2=
* The existing flood lights shall be capable of operating off of both 120 & 240V. $7 5 2. 0 0
Please note that the Elgin Oaks project has specified the use of uniduct with three (3) #8
conductors, with the lights operating at 240V. The City will need to determine the exact voltage
requirements at Trout Park. If 120/240 is required at Shelter#1, an additional wire will need to
ell°4 be installed from the meter pole to the shelter.
The City of Elgin will also need to determine the load requirements at the Park, specifically
related to the operation of the new lights and the existing Shelter#1. The#8 wire is rated at
appx. 50 amps. The fact that there will be some voltage drop will decrease the available
amperage. Please advise us if a larger wire size is required and we will be happy to provide the
City with a price for the added cost.
As a reminder, the unit prices do not include rock auguring/trenching/excavation. If rock is
encountered,additional costs would apply at a time and material basis.
Thank you for the opportunity to quote on this project. We trust that you will find our proposal
to be acceptable. We look forward to the prospects of working with the City of Elgin on this
project.
Please contact me if you have any questions or require additional information.
TOTAL $12, 171 . 20
Sincerely,
Utility Dynamics Corporation
Philip A. Whalen
A:\ELGTRTQT.WPD