HomeMy WebLinkAbout94-170 Resolution No. 94-170
RESOLUTION
AUTHORIZING EXECUTION OF AMENDMENT NO. 1 TO AN AGREEMENT
WITH HAMPTON LENZINI & RENWICK, INC . FOR THE
NATIONAL STREET IMPROVEMENT PROJECT
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF ELGIN,
ILLINOIS, that Richard B. Helwig, City Manager, and Dolonna
Mecum, City Clerk, be and are hereby authorized and directed
to execute Amendment No. 1 to an agreement on behalf of the
City of Elgin with Hampton, Lenzini & Renwick, Inc. for
engineering services in connection with the National Street
improvement project, a copy of which is attached hereto and
made a part hereof by reference.
s/ George VanDeVoorde
George VanDeVoorde, Mayor
Presented: June 22, 1994
Adopted: June 22, 1994
Omnibus Vote: Yeas 7 Nays 0
Attest:
s/ Dolonna Mecum
Dolonna Mecum, City Clerk
•
n
Agenda Item No.
j" • /Oiyl
o '.• ern 0l
y n
A�R�llD i�e1
June 2, 1994
•
•
TO: Mayor and Members of the City Council
FROM: Richard B. Helwig, City Manager
SUBJECT: Amendment No. 1 to Engineering Services Agreement
with Hampton, Lenzini and Renwick, Inc. for
Construction Engineering Services for National
Street Improvements
PURPOSE
This memorandum will provide the Mayor and Council with
information to consider authorizing an Amendment No. 1 with
Hampton Lenzini and Renwick for construction engineering
services for the National Street improvements.
BACKGROUND
The City Council entered into an engineering agreement with
Hampton, Lenzini and Renwick at the October 27 , 1993 council
meeting for the preparation of plans and specifications for
National Street Improvement project.
On May 25, 1994, City Council awarded a construction contract
to Tri-On Construction for these improvements.
This Amendment No. 1, increases the scope of the original
agreement to add construction engineering related services.
Such services are detailed in the Amendment No. 1, but
generally include: coordination of the work, on-site full
time inspection, review of the work, rejection of defective
work, testing of materials, shop drawing approvals,
monitoring of the work schedule, conducting week progress
meetings, record keeping, payment reviews, change order
reviews, etc.
The Amendment No. 1 provides for two full time on-site
inspectors, six days per week, 12 hours per day, in addition
to normal project engineering time for other construction
related activities.
Addendum No. 1
Engineering Services Agreement
HLR for Inspection Services
National St. Improvements
June 2, 1994
Page 2
FINANCIAL IMPACT
The Construction Inspection will add $290,335.00 to the
original Engineering Services agreement of $131,675 .00
bringing the total cost of Engineering Services to
$422,010.00. Funds are budgeted in the 1993 General
Obligation Bond issue (Account 392-0000-795.93-80, Project
339533) .
LEGAL IMPACT
None.
RECOMMENDATION
It is recommended that the City Council approve the Amendment
No. 1 and authorize the City Manager to execute Amendment No. 1
at a cost not to exceed $290,335.
Respectfully submitted,
R chard B. Helwig
City Manager
JE/do
Attachment
r
Amendment No. 1
This Amendment No. 1 entered into this 3nS day of9,4,4,L,t1994,
by and between the City of Elgin, an Illinois municipal
corporation (hereinafter referred to as "CITY" ) and Hampton,
Lenzini and Renwick, Inc. (hereinafter referred to as
"ENGINEER" ) , shall modify that Agreement dated 29 October 1993,
whereby the ENGINEER was engaged by CITY to perform certain
professional services in connection with the preparation of
plans, specifications and estimates of cost for the National
Street Improvements (hereinafter referred to as "PROJECT" ) .
Whereas the CITY desires to expand the scope of services of the
ENGINEER to include the furnishing of certain professional
services in connection with the construction administration,
observation and quality control of the construction phase of the
PROJECT.
In response to these additional services, certain revisions must
be made to the Agreement. In compliance, therefore, the terms
and conditions of the Agreement are modified as specifically set
out below. All other parts of the Agreement remain unchanged.
I. Scope of Services:
Paragraph I .B is amended to include the following
additional service:
I .B In general, the additional services to be provided for
the project shall consist of Construction Phase related
activities .
Paragraph I . is further amended to add the following
additional paragraphs I .G, I .H and I . I :
G. Construction Phase. The ENGINEER shall furnish or cause
to be furnished a project engineer, construction
observers and other technical personnel to perform the
following:
1 . Continuous observation of the work and the
Contractor' s operations for compliance with the plans
and specifications as construction proceeds, but the
ENGINEER does not guarantee the performance of the
contract by the Contractor.
2 . Establishment and setting of lines and grades .
-2-
3. Maintain a daily record of the Contractor' s
activities throughout construction including
sufficient information to permit verification of the
nature and cost of changes in plans and authorized
extra work.
4 . Supervision of construction observers, proportioning
engineers and other engineering technical personnel
and the taking and submitting of material samples .
5 . Revise contract plans to provide record drawings of
the improvement for permanent record.
6 . Preparation and submission to the CITY in the
required form and number of copies, all partial and
final payment estimates, change orders, records and
reports required by the CITY.
7 . The ENGINEER has not been retained or compensated to
provide design and construction review services
relating to the Contractor' s safety precautions or to
means, methods, techniques or procedures the
Contractor elects to use to complete his work.
Omitted services include, but are not limited to,
shoring, scaffolding, underpinning, temporary
retainment or excavations and any erection methods
and temporary bracing.
H. A more Detailed scope of services entitled "Duties of
the Construction Engineer" is attached to this Amendment
No. 1 as "Attachment A" .
I . That nothing contained in this Agreement shall create a
contractual relationship with or a cause of action in
favor of a third party against either the CITY or the
ENGINEER. The ENGINEER's services under this Agreement
are being performed solely for the CITY' s benefit, and
no other entity shall have any claim against the
ENGINEER because of this Agreement or the performance or
nonperformance of services hereunder.
IV. PAYMENTS TO THE ENGINEER
Paragraphs IV.A and IV.E are amended to include additional
payments to the ENGINEER for Construction Phase services :
A. For services under paragraphs IG and IH, above, the
ENGINEER shall be reimbursed at the rate of 2 . 81 times
the direct hourly rate of personnel employed on this
PROJECT, with the Construction Phase fee not to exceed
two hundred ninety thousand three hundred thirty-five
dollars ($290, 335 . 00) and the total Agreement, inclusive
of this Amendment No. 1, not to exceed four hundred
twenty two thousand ten dollars ($422, 010 . 00) , unless
-3-
further modifications to the Agreement are authorized in writing
by the CITY.
E. The CITY shall make periodic payments to the ENGINEER,
based upon actual progress, within 30 days after receipt
of invoice. Said periodic payments to the ENGINEER shall
not exceed the amounts shown in the following schedule,
and full payments for each task shall not be made until
the task is completed and accepted by the DIRECTOR.
Preliminary Phase $ 10,925. 00
Design Phase 119,300.00
Bid Phase 1,450. 00
Construction Phase 290,335.00
TOTAL $ 422,010 . 00
Paragraph IV. is further amended to add the following
additional paragraph IV. H:
H. The Construction Phase fee has been calculated based
upon Construction Phase services to be furnished by the
ENGINEER for 140 calendar days as determined during the
negotiation meeting, the results of which are attached
hereto as "Attachment B" .
The date of the first calendar day for this Agreement
shall be the date services are first requested by the
CITY. In the event PROJECT construction is suspended as
recorded on the "Report of Starting and Completion
Date, " the calendar days for this Agreement will also be
suspended for a like amount of time. In the event the
engineering services are not completed upon expiration
of the stated calendar days and remaining funds are not
sufficient to complete the PROJECT, adjustments in total
compensation to the ENGINEER shall be determined through
negotiation between the parties of this Agreement.
-4-
IN WITNESS WHEREOF, the undersigned have placed their hands and
seals upon and executed this Amendment No. 1 in triplicate as
though each copy hereof was an original and that there are no
other oral agreements that have not been reduced to writing in
this statement.
For the City:
ATTEST: THE CITY OF ELGIN
By /, ; I 7
City Clerk City Manager
(SEAL)
For the Engineer:
Dated thistAay of JUI,.)67 , A.D.
1994 .
ATTEST: Hampton, enzini and Renwi, k, Inc.
II
By Pa.kakt-S By / 4 ►' 4
Scretary President
(SEAL)
ATTACHMENT A
DUTIES OF THE
CONSTRUCTION ENGINEER
GENERAL
The Construction Engineer serves as the City' s on-site field
representative for the construction project. Services will
include field observation, design interpretation and contract
administration to determine compliance with contract drawings
and specification. The Construction Engineer will work closely
with and report to the Director.
SPECIFICATIONS AND RESPONSIBILITIES
A. Liaison and Contract Control :
Assist the contractors in understanding the
intent of the contract documents . Serve as the
owner's representative with the contractors
working principally through the contractor's
Project Engineer and on-site Superintendent.
Serve as the City' s liaison with other local
agencies such as utility companies, businesses,
etc. keeping them advised of the day-to-day
activities .
B. Review of Work, Rejection of Defective Work,
Inspection and Testing:
1 . Conduct on-site observations of the work in
progress to determine that the project is
proceeding in accordance with the contract
documents and that completed work will conform
to the requirements of the contract documents .
2 . Advise Director of any work believed to be
unsatisfactory, faulty or defective or not
conforming to the requirements of the contract
documents, or not meeting the requirements of
any inspections, tests or approvals required
to be made; and advise Director of action to
be taken and if any special testing or
inspection will be required.
3 . Verify that tests are conducted as required
by the contract documents; observe, record
and report to Director appropriate details
relative to the test procedures .
4 . Advise the City of all required field tests
such as concrete tests, asphalt tests and soil
compaction tests . Analyze the results of the
field and laboratory tests and advise the City
of the suitability of the materials tested.
-2-
5 . Accompany visiting inspectors representing
public or other agencies having jurisdiction
over the project, record the outcome of these
inspections and report to Director.
C. Contractor Suggestions and Requests :
Consider and evaluate suggestions and requests
for modifications in drawings and specifications
which may be submitted by the contractor and make
recommendations to the Director with any time or
cost implications for final decision.
D. Shop Drawings :
1 . Review and approve shop drawings and samples,
the results of tests and inspections and other
data which any contractor is required to
submit, but only for conformance with the
design concept of the project and compliance
with the information given in the contract
documents; advise the City on the
acceptability of substitute materials and
equipment proposed by contractor and receive
and review ( for general content as required by
the specifications) maintenance and operating
instructions , schedules, guarantees, bonds and
certificates of inspection which are to be
assembled by contractor(s) in accordance with
the contract documents .
2 . Record and maintain a shop drawing submittal
and approval log and notify contractor
whenever submittals are lacking or untimely.
E. Schedules :
1 . Works with contractor to ensure that a
workable construction schedule is developed
and monitor schedule as construction
progresses . Report progress and schedule
deviations to Director.
2 . Review construction schedule, schedule of shop
drawing submissions and schedule of values
prepared by the contractor. Be alert to the
construction schedule and to conditions which
may cause delay in completion and report same
to Director in sufficient time to make
adjustments .
-3-
F. Conferences:
1 . Conducts periodic progress meetings (weekly)
with all parties to review construction
progress, design interpretations and overall
progress .
2 . Arrange a schedule of on-site job work
meetings with the general contractor and
sub-contractors to review day-to-day
requirements and problems . Maintain and
circulate copies of minutes thereof.
G. Contract Administration and Records :
1 . Maintain at the job site orderly files for
correspondence, reports of job conferences,
shop drawings and samples submissions,
reproductions of original contract documents
including all addenda, change orders, field
orders, additional drawings issued subsequent
to the execution of the contract documents,
progress reports, and other project related
documents .
2 . Keep a diary or log book, recording
contractors ' hours on the job site, weather
conditions, data relative to questions of
extras or deductions, list of visiting
officials, daily activities, decisions,
observations in general and specific
observations in more detail as in the case of
observing test procedures .
3 . Record names, addresses and telephone numbers
of all contractors, sub-contractors and major
suppliers of equipment and materials .
H. Reports :
Furnish Director written reports as identified in
the IDOT Construction Manual .
I . Contractor Payment Requisitions :
Review applications for payment with contractor
for compliance with the established procedure for
their submission and forward them with
recommendations to Director, noting particularly
their relation to the schedule of values, work
completed and materials and equipment delivered
at the site.
-4-
J. Change Orders :
Perform initial evaluation of change orders and
submit same to Director with recommendation and
cost estimate breakdown for final approval and
processing.
K. Record Drawings :
Maintain an accurate record of all field
conditions and upon completion of the project
ensure that the design drawings are revised to
show the as constructed condition.
L. Final Completion:
1 . Together with the Director conduct a pre-final
inspection and prepare and give to the
contractor a pre-final punch list. Notify the
Director in writing when all work is completed.
2 . Together with the Director and contractor
conduct a final inspection. Prepare a final
punch list. Notify the Director in writing
when all work is completed and ready for final
payment.
ATTACHMENT B
CONSTRUCTION ENGINEERING NEGOTIATION MEETING
PROJECT: National Street — City of Elgin
MEETING DATE: May 5, 1994
IN ATTENDANCE:
Jim Kristiansen Elgin
Joe Evers Elgin
Doug Paulus HLR
Bob Lenzini HLR
Manhours
Required
Per Item
1. Calendar Days Services are to be Provided:
20 Weeks x 7 = 140 Days
2. Work Days:
Total Days 140
Minus Sundays 20
Minus Saturdays 20
Total Weekdays 100 Each
Saturdays 20 Each
3. Hours Required Per Day for Construction Observation:
Weekdays 8 Regular + 4 Overtime = 12
(Use 14 hours to account for overtime pay.)
Saturdays 8 Overtime
(Use 12 hours to account for overtime pay.)
4. Number of Construction Observers to be Provided: 2 Full Time 3,280
0 Part Time 0
5. Project Engineer Time:
Weekdays 4 Hours/Day
Saturdays 4 Hours/Day 480
6. Project Principal Time: 0 Hours/Week 0
- 1 -
ATTACHMENT B
Manhours
Required
Per Item
7. Provide Construction Staking 3 Man Crew 792
8. Preconstruction Meeting
Project Principal 0 Hours
Project Engineer 6 Hours
Project Observer 6 Hours 12
9. Documentation Requirements:
Daily 1.5 Hours
Payment Estimate 3 Hours/Month
Change Orders 1 Hour/Month
Shop Drawings 12 Hours 181
10. Final Quantities
Measurement 52 Hours
Computation 35 Hours 87
11. Closing Documentation Requirements:
Payment Estimate 7 Hours
Other Documents 440 Hours
Record Drawings 12 Hours 459
12. Project Administration 2 5% of above subtotal 132
13. Conferences 3.0% of above subtotal 158
14. Clerical 3.0% of above subtotal 158
15. Total Manhour Requirements 5,739
16. Quality Control: By City of Elgin (TSC)
(Include in HLR agreement _ Yes X No)
17. Provide $20,000 allowance for scheduling subconsultant.
- 2 -