RESOLUTION
APPROVING CHANGE ORDER NO. 1 IN THE CONTRACT WITH
•
B. SCAVELLI , INC. FOR THE FOX LANE RECONSTRUCTION PROJECT
WHEREAS, the City of Elgin has heretofore entered into a
contract with B. Scavelli, Inc. for the Fox Lane Reconstruc-
tion Project; and
WHEREAS, it is necessary and desirable to modify the
terms of the contract as is described in Change Order No. 1,
attached hereto.
r . .
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE
CITY OF ELGIN, ILLINOIS, that Larry L. Rice, City Manager, be
and is hereby authorized and directed to execute Change Order
No. 1, a copy of which is attached hereto and made a part
hereof by reference.
s/ George VanDeVoorde
George VanDeVoorde, Mayor
Presented: December 2, 1992
Adopted: December 2, 1992
Omnibus Vote: Yeas 7 Nays 0
Recorded:
Attest:
s/ Dolonna Mecum
Dolonna Mecum, City Clerk
A..., •
ELGIN, ILLINOIS
FOX LANE RECONSTRUCTION
PROJECT #3083
CHANGE ORDER NO. 1
SCOPE: This Change Order No. 1 will provide additional items
necessary to complete the project in an acceptable manner.
The general contractor for this project is B. Scavelli, Inc .
from Franklin Park, Illinois .
REASONS FOR CHANGE: This Change Order is required for the
addition of items to complete the drainage system, pavement
repairs and landscape restoration. The pavement design was
revised to include a course of Leveling Binder and to allow only
crushed aggregate to be used in the asphalt mix.
SUMMARY OF CHANGES IN CONTRACT AMOUNT: The awarded contract
will be changed to include additional items and to revise
contract quantities in accordance with the attached "Estimate
Number 2 and Final" .
The present contract with B. Scavelli, Inc . is for $138,447 .50 .
By reason of this Change Order No. 1, the contract for Fox Lane
Reconstruction will be decreased in the amount of two thousand
seventy two and 86/100 dollars ( $2 , 072 . 86 ) , the total contract
value being one hundred thirty six thousand three hundred
seventy four and 64/100 dollars ( $136 , 374 . 64 ) .
The circumstances which necessitate this change were not
reasonably foreseeable at the time the contract was signed.
-1 •
CHANGE ORDER NO. 1
November 3, 1992
Page 2
PROVISIONS: All other contract provisions shall
OTHER CONTRACTO
remain the same.
. il
Agreed to this / day of Ajave'wri , 1992 .
Recommended:
ENGIN RING IVISION
By: /�
Title: l�io-
Date: /, 41/1Z
Accepted:
B. Scavelli, Inc.
Party of the Second Part (Contractor)
By:
Title: P(.2 f}5
Date: /7 (7 f
Approved:
CITY OF ELGIN
Party of the - art (Owner)
By: _ ___ �C
Title: C ei
Date: Q-C-L-462-x 9
R
CITY OF ELGIN
KANE COUNTY, ILLINOIS 1992 RESURFACING
FOX LANE
ENGINEER'S PAYMENT ESTIMATE CITY COST CENTER 3083
ESTIMATE NO. 2 & FINAL FROM MAY 1, 1992 TO OCTOBER 22, 1992
PAYABLE TO: B. SCAVELLI, INC.
3450 N. RIVER RD.
FRANKLIN PARK
ILLINOIS
60131
ITEMS AWARDED ADDED DEDUCTED COMPLETED
QUANITIY VALUES QUANTITY QUANTITY QUANTITY UNIT PRICE VALUES
1. BITUMINOUS MIXTURE COMPLETE (B-5 MOD.) 1250.00 $28,750.00 0 1250 0.00 $23.00 $0.00
2. BITUMINOUS MATERIALS, PRIME COAT (MC-30) 1300.00 $1,430.00 875 0 2175.00 $1.10 $2,392.50
3. COMBINATION CURB AND GUTTER, B6.18 2600.00 $25,480.00 4 0 2604.20 $9.80 $25,521.16
4. BARRIER CURB REMOVAL 210.00 $525.00 0 5 205.00 $2.50 $512.50
5. P.C.C. BARRIER CURB 335.00 $2,847.50 0 143 192.00 $8.50 $1,632.00
6. AGGREGATE BASE COURSE, TYPE B, 12", CA-6 2700.00 $27,000.00 474 0 3173.95 $10.00 $31,739.50
7. CRUSHED STONE, CA-6 (DRIVEWAYS) 100.00 $1,400.00 0 0 100.00 $14.00 $1,400.00
8. EARTH EXCAVATION 1500.00 $15,750.00 0 0 1500.00 $10.50 $15,750.00
9. SODDING 4000.00 $15,200.00 0 1000 3000.00 $3.80 $11,400.00
10. REINFORCE CONCRETE HEADWALL, COMPLETE
(POURED IN PLACE) 1.00 $2,200.00 0 0 1.00 $2,200.00 $2,200.00
11. CONCRETE RIP-RAP 40.00 $320.00 0 0 40.00 $8.00 $320.00
12. BITUMINOUS DRIVE WAY PAVEMENT REMOVAL 340.00 $1,360.00 0 0 340.00 $4.00 $1,360.00
13. P.C.C. DRIVEWAY PAVEMENT - 8" 390.00 $7,800.00 88 0 478.00 $20.00 $9,560.00
14. P.C.C. DRIVEWAY PAVEMENT REMOVAL 35.00 $140.00 26 0 61.00 $4.00 $244.00
15. BITUMINOUS MATERIALS, PRIME COAT SS-1 1300.00 $1,495.00 0 1300 0.00 $1.15 $0.00
16. CRUSHED STONE, CA-1 • 600.00 $6,000.00 0 600 0.00 $10.00 $0.00
17. MANHOLES TO BE ADJUSTED 3.00 $450.00 1 0 4.00 $150.00 $600.00
18. CATCH BASINS TO BE ADJUSTED 2.00 $300.00 5 0 7.00 $150.00 $1,050.00
1v1'ALS $138,447.50 $105,681.66
MISCELLANEOUS EXTRAS AND CREDITS VALUES
BITUMINOUS MIXTURE COMPLETE B-5 MOD. WITH CRUSHED AGGREGATE 546.34 TON @ $25.00/TON $13,658.50
LEVELING BINDER 646 TON @ $24.00/TON $15,494.88
EXTRA LABOR & BOBCAT $543.60 LUMP SUM $543.60
EXTRA NEW FRAMES TYPE 1,2 EA. @ $100.00 $200.00
EXTRA CATCH BASIN FRAMES 1 EA. @ $325.00 $325.00
CURB 6 GUTTER REMOVAL 157 L.F. @ $3.00/L.F. $471.00
TOTAL MISCELLANEOUS EXTRAS AND CREDITS $30,692.98
TOTAL VALUE OF COMPLETED WORK $136,374.64
MISCELLANEOUS DEBITS VALUES
TOTAL OF DEBITS $0.00
NET COST OF SECTION $136,374.64
PREVIOUS PAYMENTS $129,555.91
NET AMOUNT DUE $6,818.73
(1
2)
SIGNED Ai-AM /� , 1992 �-cPi"
�j�J/ / PROJECT ENGIN R APROVED /Ud/ /J'.1 �/, , 199/ ��� L" 1 ie‘2(e
(5
CITY ENGINEER
Elm
Agenda Item No . E.
r r
"
November 5, 1992
MEMORANDUM
TO: Mayor and Members of the City Council
FROM: Larry L. Rice, City Manager
SUBJECT: Authorization of Change Order #1,
Final Payment and Acceptance of
Fox Lane Reconstruction (ST-37)
PURPOSE: This memorandum will provide the Mayor and Council
with information to consider approval of Change Order #1, accep-
tance of the subject improvements and authorizing the final
payment.
Ilk
BACKGROUND: The City Council awarded to B. Scavelli, Inc. the
contract for the Fox Lane Reconstruction Project on July 8,
1992 . The project generally included the removal of the exist-
ing roadway and replacement with new curb and gutter and pave-
ment structure. B. Scavelli, Inc. has completed the project in
compliance with the plans and specifications as verified by the
City's Engineering Staff.
Attached for your consideration is Change Order #1 . Additional
items, unforeseen at that time the contract was awarded, were
necessary in order to complete the project. The most signifi-
cant change was the deletion of the bid item Bituminous Mixture
Complete (B-5 MOD) which would have permitted the use of smooth
rounded aggregate and the addition of the Bituminous Mixture
Complete B-5 MOD with crushed aggregate which would provide for
a much more stable and durable surface material . These items are
addressed on the attached change order and on the final pay
estimate.
FINANCIAL IMPACT: The awarded contract was $138,447 .50 and
the final cost, inclusive of Change Order #1, is $136,374 . 64, a
decrease of $2,072 . 86 . A copy of the final pay estimate is
attached for your consideration.
•
Mayor and Members of
the City Council
November 5, 1992
Page 2
RECOMMENDATION: It is recommended that the City Council approve
Change Order #1 and direct staff to execute the change order
document. It is further recommended that the City Council ac-
cept the co ted project and authorize the final payment of
$6, 818 . 7 to elli, Inc.
Lar L. Rice, City Manager