HomeMy WebLinkAbout83-0622 McKeever Construction CITY OF ELGIN
ENGINEERING DIVISION
150 DEXTER COURT-ELGIN,ILLINOIS 60120-5555
T.Isphon.:(312) 695-6500
Ext. 245
TRANSMITTAL LETTER
Date July 22, 1983
To: Marie Yearman
City Clerk
Job: National Street Commuter Parking Lot
We transmit herewith for your—Information X
Approval
Files X
Correction
Return
Copy of
One (1) 0,4s`(6f Change Order No.1
Sheet Nos.
Remarks
CC: Mike Sarro Yours very truly,
CITY OF ELGIN
Ralph Ridley, Civil Engineer I
By c , eft
. ELGIN, ILLINOIS
COMMUTER PARKING FACILITIES
NATIONAL STREET COMMUTER PARKING LOT
CHANGE ORDER NO.1
SCOPE. This Change Order No.1 covers additions and modifications to the
above contract as follows:
Item 1. The bank on the west side of the parking lot shall be
excavated to a slope of 2:1 from stations 3+50 to 5+0. Included
in this item will be the deletion of the proposed landscaping
from stations 0+20 to 6+15 on the west side of the parking lot
and the substituion of Class III seeding, fertilizer, and paper
matting to retain the steep slopes.
Item 2. The seven parking lot lights shall be relocated to the
west side of the parking lot as directed by the engineer. The
light bases shall be extended to a height of 18 inches above the
back of curb.
Item 3. The contractor was directed to install B6.18 curb and
gutter along Walnut Avenue.
Item 4. The contractor shall install seven (7) inch P.C.C. drive-
way pavement through the approach area of the sidewalk at the
entrance to the parking lot.
Item 5. The contractor was directed to install a four (4) inch
perforated underdrain from stations 3+0 to 4+50 approximately
eighteen (18) inches east of the west curb. This work included
the connection to the new catch basin at station 3+0.
REASON FOR CHANGE
Item 1. After construction began it was found that the bank on the
West side of the parking lot was higher and closer to the parking
lot than shown on the plans. The original plan called for a 6:1
slope, but this type of slope would have taken excavation to the
C.&N.W. Railroad tracks west of the project. In order to keep the
work within the original project limits, our office directed the
contractor to excavate the bank to a 2:1 slope.
The Landscaping called for on the west bank from stations 0+20 to
6+15 is Day Lillies with wood bark mulch. In conversations with
two landscaping firms and the Parks Department a slope of 6:1 is
the maximum slope that the above type of landscaping can be expected
to maintain. A 2:1 slope requires seeding and matting.
Item 2. The RTA requested that we move the parking lot lights from
the east side of the parking lot to the west side because of the
lighting plans they have for their platform. Because of the slope
and the underdrain on the west side we kept the lights closer to
the back of the curb. In order to protect the poles the contractor
was directed to extend the foundations to eighteen (18) inches
above finished grade.
CO-1
Item 3. The drawings indicated a B6.12 curb & gutter along Walnut
Avenue. Excavation along the street found B6.18 curb & gutter. To
provide continuity and to assure the integrity of the street the
contractor was directed to place B6.18 curb & gutter along Walnut
Avenue.
Item 4. The plan called for four (4) inch P.C.C. sidewalk throughout
the project, including the drive approach to the lot from Walnut
Avenue. It has been our experience that an approach thickness of six
(6) to seven (7) inches is much more able to stand up to the traffic
we expect to experience in the parking lot.
Item 5. Because of wet subsoil there was water flowing over and
under the curb on the west side of the parking lot from stations
3+0 to 4+50. This condition made it extremely difficult to
guarantee that the pavement in that area would stand up to traffic.
The solution to the problem was to install a four (4) inch under-
drain eighteen (18) inches east of the curb and eighteen (18)
inches below finish grade.
SUMMARY OF CHANGES IN CONTRACT AMOUNT. The contract amount shall be revised
on the following basis:
ADD
Item 1 . Additional costs relating to
work on bank west of parking
lot:
Special Excavation 593 C.Y. @ $10.00 $5,930.00
Deleted Landscaping (6,699.60)
New Landscaping 6,116.00
Total $5,346.40 $5,346.40
Item 2. Additional 18 inches
for light foundations
7 each @ $87.20 $ 610.40 610.40
Item 3. Additional Cost for 86.18
curb & gutter.
102.6 Lineal Feet @ $1 .00 $ 102.60 102.60
Item 4. Additional Cost for 7 inch
P.C.C. Approach.
190 Square Feet @ $2.25 $ 427.50 427.50
Item 5. Additional Cost for 4 inch
underdrain.
160 Lineal Feet @ $8.60 $1 ,376.00 1 ,376.00
Total Addition to the Contract Amount $7,862.90
By reason of this Change Order No.1 , the contract cost shall be increased in
the amount of Seven Thousand Eight Hundred Sixty-two and 90/100 Dollars
($7,862.90).
C0-2
OTHER CONTRACT PROVISIONS. All other provisions of the contract shall remain
the same.
Agreed to this day of , 1983.
Recommended: Approved:
ENGINEERING DIVISION CITY OF ELGIN
c----� ��� Par of the rs Part (Owner)
ii
By L I �I E4,- By .- ., .At.\
Date: June 22, 1983 Title L ,,+ y
Accepted:
MCKEEVE: CONSTRUC ON COMPANY y
Party • the Se •• d Part (C. actor)
By „ 4. 1= ►��
Ti t l e" ?e f EiO
CO-3
July 5, 1983
MEMORANDUM
TO: Leo Nelson, City Manager �� n
FROM: Ralph Ridley, Civil Engineer I "
RE: National Street Commuter Parking Lot
During the construction of the above referenced project our office
has found several areas that were not adequately provided for in the plans
and specifications. We therefore have directed the contractor to make
certain changes in the work to expedite completion of the project. Our
office has prepared a Change Order No. 1 to cover all of the necessary
extra work that explains in detail the changes and the reasons for them
(copy attached).
We request that the Council approve this Change Order No.1 in the
amount of $7,862.90.
RR:dd
Attachment
cc: Mel Dahl
Gary Miller
Marie Yearman
Ery Jentsch
Dave Jepson
Mike Sarro
' ELGIN, ILLINOIS
COMMUTER PARKING FACILITIES
NATIONAL STREET COMMUTER PARKING LOT
CHANGE ORDER NO. 1
SCOPE. This Change Order No.1 covers additions and modifications to the
above contract as follows:
Item 1. The bank on the west side of the parking lot shall be
excavated to a slope of 2:1 from stations 3+50 to 5+0. Included
in this item will be the deletion of the proposed landscaping
from stations 0+20 to 6+15 on the west side of the parking lot
and the substituion of Class III seeding, fertilizer, and paper
matting to retain the steep slopes.
Item 2. The seven parking lot lights shall be relocated to the
west side of the parking lot as directed by the engineer. The
light bases shall be extended to a height of 18 inches above the
back of curb.
Item 3. The contractor was directed to install 86.18 curb and
gutter along Walnut Avenue.
Item 4. The contractor shall install seven (7) inch P.C.C. drive-
way pavement through the approach area of the sidewalk at the
entrance to the parking lot.
Item 5. The contractor was directed to install a four (4) inch
perforated underdrain from stations 3+0 to 4+50 approximately
eighteen (18) inches east of the west curb. This work included
the connection to the new catch basin at station 3+0.
REASON FOR CHANGE
Item 1. After construction began it was found that the bank on the
West side of the parking lot was higher and closer to the parking
lot than shown on the plans. The original plan called for a 6:1
slope, but this type of slope would have taken excavation to the
C.&N.W. Railroad tracks west of the project. In order to keep the
work within the original project limits, our office directed the
contractor to excavate the bank to a 2:1 slope.
The Landscaping called for on the west bank from stations 0+20 to
6+15 is Day Lillies with wood bark mulch. In conversations with
two landscaping firms and the Parks Department a slope of 6:1 is
the maximum slope that the above type of landscaping can be expected
to maintain. A 2:1 slope requires seeding and matting.
Item 2. The RTA requested that we move the parking lot lights from
the east side of the parking lot to the west side because of the
lighting plans they have for their platform. Because of the slope
and the underdrain on the west side we kept the lights closer to
the back of the curb. In order to protect the poles the contractor
was directed to extend the foundations to eighteen (18) inches
above finished grade.
CO-1
Item 3. The drawings indicated a B6.12 curb & gutter along Walnut
Avenue. Excavation along the street found B6.18 curb & gutter. To
provide continuity and to assure the integrity of the street the
contractor was directed to place B6.18 curb & gutter along Walnut
Avenue.
Item 4. The plan called for four (4) inch P.C.C. sidewalk throughout
the project, including the drive approach to the lot from Walnut
Avenue. It has been our experience that an approach thickness of six
(6) to seven (7) inches- is much more able to stand up to the traffic
we expect to experience in the parking lot.
Item 5. Because of wet subsoil there was water flowing over and
under the curb on the west side of the parking lot from stations
3+0 to 4+50. This condition made it extremely difficult to
guarantee that the pavement in that area would stand up to traffic.
The solution to the problem was to install a four (4) inch under-
drain eighteen (18) inches east of the curb and eighteen (18)
inches below finish grade.
SUMMARY OF CHANGES IN CONTRACT AMOUNT. The contract amount shall be revised
on the following basis:
ADD
Item 1 . Additional costs relating to
work on bank west of parking
lot:
Special Excavation 593 C.Y. @ $10.00 $5,930.00
Deleted Landscaping (6,699.60)
New Landscaping 6,116.00
Total $5,346.40 $5,346.40
Item 2. Additional 18 inches
for light foundations
7 each @ $87.20 $ 610.40 610.40
Item 3. Additional Cost for B6.18
curb & gutter.
102.6 Lineal Feet @ $1 .00 $ 102.60 102.60
Item 4. Additional Cost for 7 inch
P.C.C. Approach.
190 Square Feet @ $2.25 $ 427.50 427.50
Item 5. Additional Cost for 4 inch
underdrain.
160 Lineal Feet @ $8.60 $1 ,376.00 1 ,376.00
Total Addition to the Contract Amount $7,862.90
By reason of this Change Order No.1 , the contract cost shall be increased in
the amount of Seven Thousand Eight Hundred Sixty-two and 90/100 Dollars
($7,862.90).
CO-2
OTHER CONTRACT PROVISIONS. All other provisions of the contract shall remain
the same.
Agreed to this day of , 1983.
Recommended: Approved:
ENGINEERING DIVISION CITY OF ELGIN
C n Party of the First Part (Owner)
B � � �� � n By
Date: June 22, 1983 Title
Accepted:
MCKEEVER CONSTRUCTION COMPANY
Party of the Second Part (Contractor)
By
Title
CO.-3
-223,0-2A-i-1,,t24,-/2.wletn
• ' TELEPHONE 312/695-6500
!Itt ._`_. � 'f tig
III 150 DEXTER COURT ELGIN, ILLINOIS 60120-5555
g9p7,rFL i
June 29, 1983
Mr. Joe Serpico
McKeever Construction Company, Inc.
P.O. Box 50194
Cicero, IL 60650
Re: National Street Commuter Parking Lot
Dear Joe:
Your Company, with the exception of four (4) days of work done by
three (3) subcontractors, has not worked on the above referenced project
since May 29, 1983, when the asphalt paving was completed. It is our
intent that the parking lot be ready for use by July 15, 1983. You have
only to replace the damaged portion of the concrete approach. The land-
scaping and broken curb can be completed while cars are parking in the
lot.
•
The asphalt paving installed on May 29, 1983,, is unacceptable in two
respects. First, there are several roller marks in the pavement, pre-
dominately in the driving lane. Our inspector instructed your personnel
at the site to remove the marks by allowing the mat to cool and then
finish rolling them. These instructions were ignored and the marks
remain.
Secondly, the pavement in several areas has failed to pass the
minimum required compaction of 93%. In order to confirm or negate the
compaction failures our office will require four (4) random cores from
each of the three (3) areas shown on the attached drawing. The cores
obtained from this work should be made within two weeks of your receipt
of this letter and delivered immediately to our office. This work shall
be performed at no extra cost to the City of Elgin, as outlined in
Article 406. 15 of the "Standard Specifications. . . ".
Our office met with you in late May, 1983 to discuss payment number
two (2) . We have completed our payment estimate and await the following
• items:
1 . An invoice itemizing the quantities discussed.
.
2. Receipts for one (1 ) load of Bituminous Mixture and one (1 )
load of prime.
3. Sworn Statement.
4. Waivers from all subcontractors , suppliers and your company.
Mr. Joe Serpico June 29, 1983
Page 2
Finally, the contract requires that your company and all sub-
contractors working on this project submit a "Weekly Statement of
Compliance". We have received several unsigned copies of this
report from your company, but we do not have all of these reports.
We have no statements from any of your subcontractors. We will
require these forms immediately in order to meet the conditions of
the contract documents as set forth by U.S.D.O.T. , I .D.O.T. , and the
City of Elgin.
Your cooperation in completing the project and fulfilling the
contract provisions will be appreciated.
Sincerely,
CITY OF ELGIN
I
Ralph L. Ridley
Civil Engineer I
RLR:dd
Attachment
cc: Leo Nelson, City Manager
Mel Dahl , Public Works Director
Gary Miller, Engineering Supervisor
Ery Jentsch, Corporation Counsel
Marie Yearman, City Clerk
July 5, 1983
MEMORANDUM
TO: Leo Nelson, City Manager
FROM: Ralph Ridley, Civil Engineer I d
RE: National Street Commuter Parking Lot
During the construction of the above referenced project our office
has found several areas that were not adequately provided for in the plans
and specifications. We therefore have directed the contractor to make
certain changes in the work to expedite completion of the project. Our
office has prepared a Change Order No. 1 to cover all of the necessary
extra work that explains in detail the changes and the reasons for them
(copy attached).
We request that the Council approve this Change Order No.1 in the
amount of $7,862.90.
RR:dd
Attachment
cc: Mel Dahl
Gary Miller
Marie Yearman
Ery Jentsch
Dave Jepson
Mike Sarro
ELGIN, ILLINOIS
COMMUTER PARKING FACILITIES
NATIONAL STREET COMMUTER PARKING LOT
CHANGE ORDER NO. 1
SCOPE. This Change Order No.1 covers additions and modifications to the
above contract as follows:
Item 1 . The bank on the west side of the parking lot shall be
excavated to a slope of 2:1 from stations 3+50 to 5+0. Included
in this item will be the deletion of the proposed landscaping
from stations 0+20 to 6+15 on the west side of the parking lot
and the substituion of Class III seeding, fertilizer, and paper
matting to retain the steep slopes.
Item 2. The seven parking lot lights shall be relocated to the
west side of the parking lot as directed by the engineer. The
light bases shall be extended to a height of 18 inches above the
back of curb.
Item 3. The contractor was directed to install B6.18 curb and
gutter along Walnut Avenue.
Item 4. The contractor shall install seven (7) inch P.C.C. drive-
way pavement through the approach area of the sidewalk at the
entrance to the parking lot.
Item 5. The contractor was directed to install a four (4) inch
perforated underdrain from stations 3+0 to 4+50 approximately
eighteen (18) inches east of the west curb. This work included
the connection to the new catch basin at station 3+0.
REASON FOR CHANGE
Item 1 . After construction began it was found that the bank on the
West side of the parking lot was higher and closer to the parking
lot than shown on the plans. The original plan called for a 6:1
slope, but this type of slope would have taken excavation to the
C.&N.W. Railroad tracks west of the project. In order to keep the
work within the original project limits, our office directed the
contractor to excavate the bank to a 2: 1 slope.
The Landscaping called for on the west bank from stations 0+20 to
6+15 is Day Lillies with wood bark mulch. In conversations with
two landscaping firms and the Parks Department a slope of 6:1 is
the maximum slope that the above type of landscaping can be expected
to maintain. A 2:1 slope requires seeding and matting.
Item 2. The RTA requested that we move the parking lot lights from
the east side of the parking lot to the west side because of the
lighting plans they have for their platform. Because of the slope
and the underdrain on the west side we kept the lights closer to
the back of the curb. In order to protect the poles the contractor
was directed to extend the foundations to eighteen (18) inches
above finished grade.
CO-1
Item 3. The drawings indicated a B6.12 curb & gutter along Walnut
Avenue. Excavation along the street found 66.18 curb & gutter. To
provide continuity and to assure the integrity of the street the
contractor was directed to place B6.18 curb & gutter along Walnut
Avenue.
Item 4. The plan called for four (4) inch P.C.C. sidewalk throughout
the project, including the drive approach to the lot from Walnut
Avenue. It has been our experience that an approach thickness of six
(6) to seven (7) inches is much more able to stand up to the traffic
we expect to experience in the parking lot.
Item 5. Because of wet subsoil there was water flowing over and
under the curb on the west side of the parking lot from stations
3+0 to 4+50. This condition made it extremely difficult to
guarantee that the pavement in that area would stand up to traffic.
The solution to the problem was to install a four (4) inch under-
drain eighteen (18) inches east of the curb and eighteen (18)
inches below finish grade.
SUMMARY OF CHANGES IN CONTRACT AMOUNT. The contract amount shall be revised
on the following basis:
ADD
Item 1 . Additional costs relating to
work on bank west of parking
lot:
Special Excavation 593 C.Y. @ $10.00 $5,930.00
Deleted Landscaping (6,699.60)
New Landscaping 6,116.00
Total $5,346.40 $5,346.40
Item 2. Additional 18 inches
for light foundations
7 each @ $87.20 $ 610.40 610.40
Item 3. Additional Cost for B6.18
curb & gutter.
102.6 Lineal Feet @ $1 .00 $ 102.60 102.60
Item 4. Additional Cost for 7 inch
P.C.C. Approach.
190 Square Feet @ $2.25 $ 427.50 427.50
Item 5. Additional Cost for 4 inch
underdrain.
160 Lineal Feet @ $8.60 $1 ,376.00 1 ,376.00
Total Addition to the Contract Amount $7,862.90
By reason of this Change Order No.1 , the contract cost shall be increased in
the amount of Seven Thousand Eight Hundred Sixty-two and 90/100 Dollars
($7,862.90).
CO-2
OTHER CONTRACT PROVISIONS. All other provisions of the contract shall remain
the same.
Agreed to this day of , 1983.
Recommended: Approved:
ENGINEERING DIVISION CITY OF ELGIN
Party of the First Part (Owner)
t . By
Date: June 22, 1983 Title
Accepted:
MCKEEVER CONSTRUCTION COMPANY
Party of the Second Part (Contractor)
By
Title
CO-3
0
r
L.,
1 • Z ►-r m
9 co
�
O gg g 0
a• H rt M K
C°
a. Improvements to National Street W w rt
Commuter Parking Lot 0 0, m dao F. V 0
c w m = o
b 1 -+• •i
K =
F+ kA CD :--, H
0 W Z 1 N C
? -.• V 1 N
1 V
OD OD N
• N
V
O
O
4.----
Iy -..4. .-.-"'3
CD
$ 99,149.86 Ciceero r Constru
I) coon Co
1
a
$104,378.75 CD
z West H• Kuhn
-1 st Chicago I�c
41
7-----------------___
$105,801.41 LamF Incorpora
ted
—I
r
VI 1 C E.N. Melahn
m $108,105.25.25 -I
a
m
r►
c
o Sennett
$109,809.90 = Elgin, 17 uilders, Inc
rim,
$111,680.80 ? Wood Ex
$111,680.80
stock, Icing
r
3
Gi
$117,355.00 c Drs
ods Brothe
tock, 17
--
iv
•
$119,222.95 Z Lands
a FcoaPe
Con*
resljactors
Of
f" 7noi