HomeMy WebLinkAbout24-160 Resolution No. 24-160
RESOLUTION
AUTHORIZING EXECUTION OF A CHANGE ORDER NO. 1 AND FINAL WITH FIVE
STAR ENERGY SERVICES FOR THE YEAR 2 LEAD SERVICE LINE REPLACEMENT
PROGRAM —CONTRACT B
(BID NO. 23-012)
WHEREAS, the City of Elgin has heretofore entered into a contract with Five Star Energy
Services for the year 2 lead service line replacement program—contract B (Bid No. 23-012); and
WHEREAS,it is necessary and desirable to modify the terms of the contract as is described
in Change Order No. 1 and Final attached hereto.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF
ELGIN,ILLINOIS,that Richard G. Kozal,City Manager,be and is hereby authorized and directed
to execute Change Order No. 1 and Final, a copy of which is attached hereto and made a part
hereof by reference.
s/David J. Kaptain
David J. Kaptain, Mayor
Presented: June 26, 2024
Adopted: June 26, 2024
Omnibus Vote: Yeas: 9 Nays: 0
Attest:
s/Kimberly Dewis
Kimberly Dewis, City Clerk
OF(<C
City of Elgin Change Order
ELGIN,ILLINOIS
PROJECT#Bid No. 23-012
CHANGE ORDER No. I and Final
CONTRACT: Year 2 Lead Service Line Replacement Program—Contract B (Bid No. 23-012)
SCOPE: The Year 2 Lead Service Line Replacement Program—Contract B project has been completed
and final quantities are known. Change Order No. 1 and Final is the balancing change order to document
the final construction value.
REASONS FOR CHANGE:
The circumstances said to necessitate the change in performance were not reasonably foreseeable at the
time the contract was signed; the change is germane to the original contract as signed; and the change
order is in the best interests of the City of Elgin and is authorized by law.
SUMMARY OF CHANGES IN CONTRACT AMOUNT:
ORIGINAL CONTRACT AMOUNT: $4,898,913.00
CHANGE ORDER No. 1
SEE ATTACHMENT
TOTAL FOR CHANGE ORDER NO. 1 AND FINAL: SUBTRACT $1,280,544.78
PREVIOUS CHANGE ORDER(S):
None
TOTAL OF PREVIOUS CHANGE ORDERS: N/A
TOTAL REVISED CONTRACT AMOUNT: $3,618,368.22
The original amount of the contract with Five Star Energy Services is $4,898,913.00. Changc Order No.
1 will decrease the contract amount by a total of$1,280,544.78,that sum representing 26%of the origi-
nal contract amount. The revised contract amount, inclusive of all change orders is$3,618,368.22.
OTHER CONTRACT PROVISIONS: All other contract provisions remain the same.
CHANGE ORDER No. I AND FINAL
Agreed to this 26 day of June ,20 24
Recommended by:
Water Department
By: Nora Bertram
Title: Water Director
Date: ri I Z LI
Signature:
Engineering Enterp .es,Inc.
Party of the Second Part(Engineer)
By: Julie A.Morrison P.E.
Title: Vice President
Date: 5/30/23‘s.,A Signature: i\;�+ �
Accepted by:
Five Star Energy Services
Party of the Second Part(Contractor)
By: Mike Klumb
Title: President&CEO
Date: 06/12/2024
Signature:
Approved by:
CITY OF ELGIN
Party of the First Part(Owner)
By: Richard G.Kozal
Title:City Manager -
Date: 1u , 24
Signature:Legal Dept\Agrcemcnt\Five Star Energy-Change Order No1-Bid No 23-012-Contract B-Clean 05-22-24.doc.docx
CHANGE ORDER NO.1 AND FINAL
YEAR 2 LEAD SERVICE LINE REPLACEMENT PROGRAM-CONTRACT B
CITY OF ELGIN
REM NO. ITEMS UNIT CONTRACT ADJUSTED UNIT PRICE ADDITIONS DEDUCTIONS
QUANTITY QUANTITY QUANTITY COST QUANTITY COST
1 CONTRACTOR RESIDENT COORDINATION EA 434 . $400.00 8 $ 3.200.00
2 PRIVATE UTILITY LOCATE EA 434 - $300.00 32 $ 9.600.00
3 TREE ROOT PRUNING EA 10 $500.00 9 $ 4,500.00
4 TREE REMOVAL(6-15 UNIT DIAMETER) UNIT 30 $650.00 29 $ 18.850.00
5 TREE REMOVAL(15+UNIT DIAMETER) UNIT 40 6800.00 40 $ 32,000.00
8 REPLACEMENT TREE EA 5 0 $1,000.00 - 5 $ 5,000.00
7 ASBESTOS ABATEMENT EA 10 0 $250.00 10 $ 2,500.00
8 SELECT GRANULAR BACKFILL CY 6250 1406.67 624.00 2843.33 $ 68,239.92
9 POTHOLE EXISTING WATER SERVICE EA 434 26 $300.00 408 $ 122,400.00
10 WATER SERVICE CONNECTION AT B-BOX EA 20 78 $1,500.00 58 $ 87,000.00
11 WATER SERVICE CONNECTION AT MAIN-1' BA 434 307 $3,000.00 127 $ 381,000.00
12 WATER SERVICE CONNECTION AT MAIN-2 EA 5 0 $3,500.00 5 $ 17.500.00
13 TAPPING SADDLE.4' EA 65 53 $400.00 12 $ 4,800.00
14 TAPPING SADDLE.6' EA 261 0 $450.00 261 $ 117,450.00
15 TAPPING SADDLE.8- EA 66 1 $500.00 65 $ 32,500.00
18 TAPPING SADDLE.12 EA 22 0 $550.00 22 $ 12,100.00
17 TAPPING SADDLE,16' EA 22 0 $600.00 22 $ 13,200.00
18 WATER SERVICE PIPE INSTALLATION,TYPE K.1-INCH LF 21700 20292; $85.00‘, 1407.3 $ 91,474.50
19 WATER SERVICE PIPE INSTALLATION.TYPE K.2-INCH LF 250 0 $50.00 250 $ 12,500.00
20 WATER SERVICE CONNECTION AT METER EA 434 368 $1,500.00 88 $ 99,000.00
21 WATER SERVICE PIPE INSTALLATION.TYPE L 1-INCH LF 40 0 $40.00 40 $ 1,600.00
22 WATER SERVICE PIPE INSTALLATION,TYPE L 3/4-INCH LF 215 31 C $50.00 95 $ 4,750.00
23 GROUNDING EA 10 4 $100.0OA 6 $ 600.00
24 SANITARY SEWER REPAIR EA 10 1 $300.00 9 $ 2,700.00
25 PCC SIDEWALK REMOVAL SF 6200 4140.7 $2.00 2069.3 $ 4,118.60
28 PCC SIDEWALKREPLACEMENT5' SF 8200 4140.7 $12.00 2059.3 $ 24,711.60
27 COMBINED CURB AND GUTTER REMOVAL LF 600 97.7 - $2.0DO 5023 $ 1,004.60
28 COMBINED CURB AND GUTTER REPLACEMENT LF 800 97 7 $45.00A 502.3 $ 22,603.50
29 HOT MIX ASPHALT PAVEMENT REMOVAL SY 4830 2466.84 $6.00 2363.16 $ 14,178.96
30 HOT MIX ASPHALT PAVEMENT PATCH,4-INCH SY 966 0 $20.00 986 $ 19,320.00
31 HOT MIX ASPHALT PAVEMENT PATCH,6-INCH SY 966 _ $30.00\ 966 $ 28.980.00,
32 HOT MIX ASPHALT PAVEMENT PATCH,8-INCH SY 2898 244'.34 $40.00O 456.66 $ 18,266.40
33 PCC PAVEMENT REMOVAL SY 35 $9.00 36 $ 315.00
34 _PCC PAVEMENT PATCH,BINCH SY 35 $98.00 35 $ 3,430.00
35 PCC DRIVEWAY REMOVAL SY 458 176.6 $6.00 279.4 $ 1,876.40
36 PCC DRIVEWAY REPLACEMENT SY 456 '76.5 $98.00 279.4 $ 27.381.20
37 HMA DRIVEWAY REMOVAL SY 36 25.' $9.00G 0.9 $ 8.10
38 HMA DRIVEWAY REPLACEMENT SY 36 35.' $45.00 0.9 $ 40.50
39 CONTROLLED LOW-STRENGTH MATERIAL CY 360 $120.00 380 $ 43,200.00
40 NON-SPECIAL.NON-HAZARDOUS WASTE DISPOSAL TON 800 168 9 $70.00‘„ 631.1 , $ 44,177.00
41 TRAFFIC CONTROL AND PROTECTION LS 1 1 610,000.00
42 DUST CONTROL-MECHANICAL SWEEPING EA 5 0 $2.500.00‘ 5 $ 12,500.00
43 RESTORATION-SODDING.SPECIAL SY 370 0 $30.00 370 $ 11,100.00
44 RESTORATION-SEED AND BLANKET SY 7240 3586.5 $5.001 3653.5 $ 18,267.50
45 SUPPLEMENTAL WATERING UNIT 12 0 61.000.00 12 $ 12,000.00
46 POINT-OF-USE WATER FILTER AND CARTRIDGES EA 650 543 $80.00 107 $ 8,580.00
47 STOCKPILE STORAGE AREA PREPARATION LS 1 1 615.000.00
CO-1 HOT MIX ASPHALT PAVEMENT PATCH-10-1NCH SY 0 25.5 $52.00 25.5 $ 1,326.00
. - ,- ' 41ANAGFMFNT DISPOSAL IITPM NC.401 TON ^. 'Eo n 168.9 $ (5,087.00)
TOTAL ADDITIONS■ $ 88,009.00
TOTAL DEDUCTIONS' $(1,368,553.78)
ORIGINAL CONTRACT PRICE: $ 4,898,913.00
CURRENT CONTRACT PRICE ADJUSTED BY PREVIOUS CHANGE ORDER(S): $ •
AMOUNT OF CURRENT CHANGE ORDER: $(1280,544,78)
FNAL CONTRACT PRICE: $ 3,618,358.22