HomeMy WebLinkAbout24-115 Resolution No. 24-115 RESOLUTION AUTHORIZING EXECUTION OF A CHANGE ORDER NO. 1 WITH SCHAEFGES BROTHERS, INC. FOR THE FESTIVAL PARK SPLASHPAD REHABILITATION (Bid No. 23-038) WHEREAS, the City of Elgin has heretofore entered into a contract Schaefges Brothers, Inc. for the Festival Park splashpad rehabilitation(Bid No. 23-038); and WHEREAS,it is necessary and desirable to modify the terms of the contract as is described in Change Order No. 1 attached hereto. NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF ELGIN,ILLINOIS,that Richard G.Kozal,City Manager,be and is hereby authorized and directed to execute Change Order No. 1, a copy of which is attached hereto and made a part hereof by reference. s/David J. Kaptain David J. Kaptain, Mayor Presented: April 24, 2024 Adopted: April 24, 2024 Omnibus Vote: Yeas: 9 Nays: 0 Attest: s/Kimberly Dewis Kimberly Dewis, City Clerk \0ortzci t`(6 �\l' . City of Elgin Change Order `4,,,, ELGIN, ILLINOIS PROJECT 322004 CHANGE ORDER No. 1 CONTRACT: Festival Park Splashpad Rehabilitation (Bid No. 23-038) SCOPE: The change order adds $18.303 to the Festival Park Splashpad Rehabilitation contract to allow for necessary sealing of the surge pit due to a condition which was unforeseen at the time of the initial contract approval. REASONS FOR CHANGE: • At the time the contract signed, leakage from the area surrounding the surge pit was a condition which was not known to any party. It is necessary to repair this condition in or- der to prevent sludge leakage into the surge pit and to provide the best possible product. • The circumstances said to necessitate the change in contract amount were not reasonably foreseeable at the time the contract was signed. • The change is germane to the original contract as signed. • The change order is in the best interests of the City of Elgin and is authorized by law. SUMMARY OF CHANGES IN CONTRACT AMOUNT: The contract is being increased by $18,303. This will allow the contractor to seal the surge pit preventing infiltration of sludge from the surrounding area. ORIGINAL CONTRACT AMOUNT: $924,427 CHANGE ORDER No. Funding for surge pit sealing $18,303 TOTAL FOR CHANGE ORDER NO. 1: ADD $18,303 TOTAL REVISED CONTRACT AMOUNT: $942,730 The original amount of the contract with Schaefges Brothers, Inc. is$924,427. Change Order No. I will increase the original contract amount by a total of$18,303,that sum representing 2 percent (2%)of the original contract amount. The new contract amount, inclusive of all change orders is$942,730. OTHER CONTRACT PROVISIONS: All other contract provisions remain the same. CHANGE ORDER No. l Agreed to this 24 day of April . 2024 . Recommended by: Parks and Recreation By: Greg Hulke �J j� (ii Title: I c�' �(r"1C� P� J �`��'nI'/'IIA( /". Date: 07 Z Signature: 7 Accepted by: [INSERT NAME OF CONTRACTOR) Party of the Second Part(Contractor) By: Ken Scheafges Title: President Date: April 17t1',2024 Signatu Approved by: CITY OF ELGIN Party of the First Part(Owner) By: Richard G. Kozal Title: City Manager Date: April , 24 Signature: 6 Legal Dept AarecmentlFestival Past Splash Pad Rehabilitation-I-Ch. c Order al I-Revised Clean 4-4.24 doex