HomeMy WebLinkAbout09-182 Resolution No. 09-182 RESOLUTION APPROVING CHANGE ORDER NO. 1 IN THE CONTRACT WITH TENNIS SURFACES COMPANY FOR TENNIS COURT RESURFACING AT ST. FRANCIS PARK WHEREAS, the City of Elgin has heretofore entered into a contract with Tennis Surfaces Company for tennis court resurfacing at St. Francis Park; and WHEREAS, it is necessary and desirable to modify the terms of the contract as is described in Change Order No. 1, attached hereto. NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF ELGIN, ILLINOIS,that Sean R, Stegall, City Manager,be and is hereby authorized and directed to execute Change Order No. 1,a copy of which is attached hereto and made a part hereof by reference. s/Ed Schock Ed Schock, Mayor Presented: August 12, 2009 Adopted: August 12, 2009 Omnibus Vote: Yeas: 7 Nays: 0 Attest: s/Diane Robertson Diane Robertson, City Clerk Change Order No. 1 for Tennis Court Improvements July 16, 2009 Page 3 ELGIN, ILLINOIS PROJECT 509831 CHANGE ORDER No. 1 CONTRACT: Tennis Court Improvements (Bid No. 09-029) SCOPE: This change order includes two additional tennis courts to be resurfaced. In addition to the six courts at Judson University, the resurfacing project will include the two courts at St Francis Park. REASONS FOR CHANGE: The bid submitted by Tennis Surfaces Company was $11,000 below the amount budgeted for this work. Therefore there are enough funds in the budget to cover the cost of two additional tennis courts in need of resurfacing at St Francis Park. This change order is in the best interests of the City of Elgin and authorized by law. SUMMARY OF CHANGES IN CONTRACT AMOUNT: The original contract will be amended as to scope and costs to include the improvements outlined above. ORIGINAL CONTRACT AMOUNT $14,900 CHANGE ORDER No. 1 $ 6,000 TOTAL REVISED CONTRACT AMOUNT: $20,900 The original amount of the contract with Tennis Surfaces Company is $14,900. Change Order No.1 will increase the original contract amount by a total of$6,000, which represents approximately forty percent (40%) of the original contract amount. The new contract amount, inclusive of all change orders, is $20,900. OTHER CONTRACT PROVISIONS: All other contract provisions remain the same. CHANGE ORDER No. 1 July 16,2009 -► Change Order No. 1 for Tennis Court Improvements July 16, 2009 Page 4 Agreed to this liCacty of , 2009. Recommended by: Parks and Recreation Department A3,..0‘.., b5.91\04:2— By: Title: T..itc- vo•/ CD ''A1‘ Date: ii'IA O"\ Signature: IRJ,1- ->)( '' Accepted by: Tennis Surfaces Company Party of the Second Part (Contractor) By: I) \L L Atd ,,,,i, Title: {, Woe j Date: \,ti 1-71 '1-0417 Signature: N- \ J\ C J LJ Approved by: CITY OF ELGIN Party of the First Part(Owner) By: Sean Stegall Title: City Manager Date: /a, goal Signature: 4 t rx Zi 4 y1t ; raw.•-.s =-..s .;,� ..`` i t�: . July 16,2009 , 4 TO: Mayor and Members of the City Council jY ' �triaupai;Lris�rrr. trrd FROM: Sean R. Stegall, City Manager cup do nmn,r s fa,,lrr ir Randy Reopelle, Parks and Recreation Director SUBJECT: Change Order No. 1 to Contract with Tennis Surfaces Company PURPOSE The purpose of this memorandum is to provide the Mayor and members of the City Council with information to consider Change Order No.1 with Tennis Surfaces Company for the resurfacing of the tennis courts at St. Francis Park. RECOMMENDATION It is recommended that the City Council approve Change Order No.1 with Tennis Surfaces Company in the amount of$6,000,making the total contract amount$20,900. BACKGROUND The City Council approved a contract with Tennis Surfaces Company in the amount of$14,900 in order to resurface six tennis courts at Judson University, which will be available to the residents of Elgin. The 2009 budget has allocated $26,000 for this work. Since the actual contract award was approximately $11,000 less than the budget allocated, and the two tennis courts at St. Francis Park were in need of being resurfaced,it was recommended that they should be resurfaced as part of this contract. The amount of the change order is reasonable considering that the cost per court of$3,000 for these additional courts is lower than other recent bids received for court resurfacing. The change order reflects a 40 percent increase to the original contract. COMMUNITY GROUPS/INTERESTED PERSONS CONTACTED None. Change Order No. 1 for Tennis Court Improvements July 16, 2009 Page 2 FINANCIAL IMPACT The cost of Change Order No. 1 with Tennis Surfaces Company totals $6,000. There are sufficient funds budgeted ($26,000) and available ($11,100) in the Park Development Fund, account number 340-0000-795.92-32, project number 509831, Tennis Court Improvements to pay for the change order. LEGAL IMPACT None. ALTERNATIVES 1. The City Council may choose to approve Change Order No. 1 with Tennis Surfaces Company in the amount of$6,000. 2. The City Council may choose not to approve Change Order No. 1 with Tennis Surfaces Company in the amount of$6,000. Respectfully submitted for Council consideration. pb Attachments ��4 OF Ft. Gi Memorandum 1, , 2 ,C- City of Elgin % ' ,1p: qRATCDV - Date: August 17, 2009 To: Randy Reopelle, Parks and Recreation Director From: Jennifer Quinton, Deputy City Clerk Subject: Resolution No. 09-182, Adopted at the August 12, 2009, Council Meeting Enclosed you will find the agreement listed below. Please retain a copy for your records. If you have any questions please feel free to contact our office 847-931-5660 and we will do our best to assist you. Thank you. • Change Order No. 1 in the Contract with Tennis Surfaces Resurfacing at St. Francis Park