Resolution No. 08-43
RESOLUTION
APPROVING CHANGE ORDER NO. 2 IN THE CONTRACT WITH
TURNKEY NETWORK SOLUTIONS, INC.
FOR INSTALLATION OF FIBER OPTIC CABLE
WHEREAS,the City of Elgin has heretofore entered into a contract with Turnkey Network
Solutions, Inc. for installation of fiber optic cable; and
WHEREAS,it is necessary and desirable to modify the terms of the contract as is described
in Change Order No. 2, attached hereto.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF
ELGIN,ILLINOIS,that Olufemi Folarin,City Manager,be and is hereby authorized and directed to
execute Change Order No.2,a copy of which is attached hereto and made a part hereof by reference.
s/Ed Schock
Ed Schock, Mayor
Presented: February 27, 2008
Adopted: February 27, 2008
Omnibus Vote: Yeas: 7 Nays: 0
Attest:
s/ Diane Robertson
Diane Robertson, City Clerk
CITY OF ELGIN
PROJECT RFP 07-055
CHANGE ORDER NO.2
CONTRACT:
Turn-Key Network Solutions, Inc. fiber optic cable installation
SCOPE:
This change order affects a contract entered into between the City of Elgin and Turn-Key
Network Solutions, Inc., dated June 13,2007.
This Change Order No. 2 will provide additional labor and materials to engineer an alternative
route from Airlite Water Treatment Plant to Hawthorn Hill Nature Center and Fire Station 7. A
net increase of 1950 linear feet.
REASON FOR CHANGE:
This Change Order No. 2 is in the best interests of the City of Elgin and is authorized by law.
The necessity for the changes was unforeseen at the time of the original agreement, and the
changes contemplated hereby are germane to the original agreement.
SUMMARY OF CHANGES IN CONTRACT AMOUNT:
The original contract will be amended as to scope and costs as provided below:
The original contract amount with Turn-Key Network Solutions, Inc. is for the amount of
$513,505. Change Order No. 1, dated October 10, 2007 increased the contract amount to
$553,805. By reason of this Change Order No. 2, the contract for the installation of fiber optic
cable will be increased by$31,335,which represents an increase of approximately 6.1%over the
original contract amount. The new contract amount, inclusive of Change Order No. 2, is
$585,140.
The increased cost amount attributable to the net addition of 1,950 linear feet of directional bore
fiber installation. An alternative route for crossing US Route 20 is required by the Illinois
Department of Transportation.
OTHER CONTRACT PROVISIONS:
All other contract provisions shall remain the same.
Agreed to this 7day of February,2008.
TURN-KEY NETWORK SOLUTIONS,INC. CITY OF ELGIN(Owner)
(Contractor)
By: By:
Olufe '•Folarin
Title: I C s Title: City
Date: 47/2 Dog
Item Unit Rate
Engineering ft. $ 0.75
Place inner duct ft. $ 1.25
Place fiber ft. $ 0.75
Directional Bore - City ft. $ 9.00
Directional Bore - Rural ft. $ 7.00
Place Hand Hole ea. $500.00
Fusion Splice ea. $ 50.00
Revised 12-17-2007 Original
Section 1 Section 1 Difference Change in SOW
Materials $ 24,491.48 Materials $ 24,491.48 $ -
Equipment $ 15,561.70 Equipment $ 15,561.70 $ -
Labor $ 62,246.82 Labor $ 62,246.82 $ -
Total Project Section 1 $ 102,300.00 Total Project Section 1 $ 102,300.00 $ - No Change
Section 2 Section 2
Materials $ 10,070.49 Materials $ 12,187.45 $ (2,116.96) Add 2100' of
Equipment $ 8,057.59 Equipment $ 10,173.51 $ (2,115.92) Engineering,
Labor $ 32,230.36 Labor $ 40,694.04 $ (8,463.68) Deduct 1400'
Total Project Section 2 $ 50,358.44 Total Project Section 2 $ 63,055.00 $ (12,696.56) Directional Drill
Section 3 Section 3
Materials $ 60,288.28 Materials $ 54,965.61 $ 5,322.67 Add 9000' of
Equipment $ 44,173.80 Equipment $ 35,776.88 $ 8,396.92 Engieering, Add
Labor $ 176,695.20 Labor $ 143,107.52 $ 33,587.68 3650' Directional
Total Project Section 3 $ 281,157.28 Total Project Section 3 $ 233,850.00 $ 47,307.28 Drill
Section 4 Section 4
Materials $ 21 ,711.31 Materials $ 22,135.10 $ (423.79) Deduct 300' of
Equipment $ 17,862.53 Equipment $ 18,432.98 $ (570.45) Engineering,
Labor $ 71 ,450.12 Labor $ 73,731.92 $ (2,281.80) Deduct 300'
Total Project Section 4 $ 111,023.96 Total Project Section 4 $ 114,300.00 $ (3,276.04) Directional Drill
Total Route Change Order $ 31,334.68
E
February 8, 2008 GEr� i
glE4if
TO: Mayor and Members of the City Council
N �rl I11
FROM: Olufemi Folarin, City Manager FINANCIALLY STABLE CITY GOVERNMENT
Jeffery D. Massey, MIS Director AND O EFFKIENTSERES"
LW UTV INFRA EFFICIENT
SUBJECT: Change Order No. 2 to Turnkey Network Solutions Agreement for Installation of
Fiber Optic Cable
PURPOSE
The purpose of this memorandum is to provide the Mayor and members of the City Council with
information to consider Change Order No. 2 to Turnkey Network Solutions Agreement for
Installation of Fiber Optic Cable.
RECOMMENDATION
It is recommended that the City Council approve Change Order No. 2 to the agreement with
Turnkey Network Solutions for fiber optic cable installation in the amount of$31,335.
BACKGROUND
In June 2007, the City Council approved an agreement with Turnkey Network Solutions for the
installation of more than 10 miles of new fiber optic cable. Fiber optic cable is being installed
from Riverside Water Treatment Plant to Airlite Water Plant in conduit that was installed as part
of the 2005 water main project. New conduit is being installed by directional boring from the
Airlite Water Plant to Hawthorn Hill Nature Center, to Fire Station 7, to the Bowes Road water
pump station, finally to Bowes Creek Country Club. This change order is to engineer an
alternate route for crossing US Route 20. The original route, chosen because it was the shortest,
most economical route to install the fiber, following existing underground gas, electric and telco
utilities, was to go west from Hawthorn Hill, across Randall Road, parallel to US Route 20 on
the north side, to Weld Road, then cross US Route 20 to Longcommon Parkway. A utility
permit is required by the Illinois Department of Transportation to work in the highway right-of-
way. The City's contractor on this project, Turnkey Network Solutions, created drawings of the
route (see attached) and prepared an application requesting a permit to install underground fiber
optic cable for IDOT. The permit request was denied. The reason stated by IDOT for the denial
is that the free-way portion of US 20 (from Weld Road east) is an access controlled right-of-way
and the longitudinal installation of new facilities within the access controlled right of way is
prohibited. This prohibition was unknown and unexpected. IDOT is requiring a perpendicular
crossing of US RT 20 with the east-west portion of the route out of the highway right-of-way.
Change Order No. 2 to Turnkey Agreement for Installation of Fiber Optic Cable
February 8, 2008
Page 2
The alternative route being considered is to go from the Airlite Water Plant south on Hawthorn
Street, cross US RT 20 at Hawthorn Street, to the south side of Weld Road south of US RT 20
(out of the highway right-of-way), then turn west to Longcommon Parkway. The new route adds
a net increase of 1,950 linear feet to the installation of conduit and fiber. The additional cost is
$31,335 or $16.07 per linear foot. This includes all labor, material and equipment to complete
the installation of conduit and fiber.
COMMUNITY GROUPS/INTERESTED PERSONS CONTACTED
None
FINANCIAL IMPACT
Sufficient funds are located in the Riverboat Fund, account number 275-0000-791.92-47,
"Communications Equipment, project 219511, MIS Strategic Plan Initiatives, ($2,407,470
budgeted and $550,075 available) to enter into change order no. 2 with Turn-Key Network
Solutions in the amount of$31,335.
LEGAL IMPACT
None
ALTERNATIVES
1. The City Council may choose to approve Change Order 2 to the Agreement with Turnkey
Network Solutions.
2. The City Council may choose not to approve Change Order 2 to the Agreement with
Turnkey Network Solutions.
Respectfully submitted for Council consideration.
JM
Attachment