HomeMy WebLinkAbout05-340 Resolution No. 05-340
RESOLUTION
APPROVING CHANGE ORDER NO. 1 AND FINAL
IN THE CONTRACT WITH FUERTE SYSTEMS, INC.
FOR MULBERRY GROVE PARK CONSTRUCTION CONTRACT
WHEREAS,the City of Elgin has heretofore entered into a contract with Fuerte Systems,Inc.
for construction of the Mulberry Grove Park; and
WHEREAS,it is necessary and desirable to modify the terms of the contract as is described
in Change Order No. 1 and Final, attached hereto.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF
ELGIN,ILLINOIS,that Olufemi Folarin,City Manager,be and is hereby authorized and directed to
execute Change Order No. 1 and Final,a copy of which is attached hereto and made a part hereof by
reference.
s/Ed Schock
Ed Schock, Mayor
Presented: December 21, 2005
Adopted: December 21, 2005
Omnibus Vote: Yeas: 5 Nays: 0
Attest:
s/Dolonna Mecum
Dolonna Mecum, City Clerk
ELGIN, ILLINOIS
PROJECT 509622
CHANGE ORDER No. 1 and Final
CONTRACT: Mulberry Grove Park
SCOPE: This Change Order No. 1 will provide additional items necessary to complete the
Mulberry Grove Park Project in an acceptable manner.
This change order affects a contract entered into between the City of Elgin and Fuerte Systems,
Inc. of Plainfield, IL an Illinois corporation, dated May 16th, 2005 for Mulberry Grove Park
Project.
REASONS FOR CHANGE: This Change Order No. 1 and Final is in the best interests of the
City and is authorized by law. The necessities for the changes were unforeseen at the time of the
original agreement, and the changes contemplated hereby are germane to the original agreement.
SUMMARY OF CHANGES IN CONTRACT AMOUNT: The amount the contract will be
revised is as follows:
Itemized List of Changes
1. August 11, 2005—Addition of$8,764.00 for installation of seat wall and
additional unit pavers.
2. October 3,2005—Addition of$7,900.00 for installation of Fibar Safety surfacing,
power raking, over seeding and fertilization of athletic field.
. i
The original contract with Fuerte Systems, Inc. is $358,308. By reason of Change Order No. 1
and Final, the contract for the Mulberry Grove Park Project will be increased in the amount of
sixteen thousand six hundred forty and 00/100 dollars ($16,640). The new and final contract
amount, inclusive of Change Order No. 1 and Final is three hundred seventy-four thousand nine
hundred seventy-two and 00/100 dollars($374,972.00). The total addition to the original contract
price is 4.6%.
CHANGE ORDER No.! and Final
November 16,2005
Page 2
OTHER CONTRACT PROVISIONS: All other contract provisions shall remain the same.
Agreed to this l,'Sday of Novts4c- —,2005.
Recommended:
PARKS AND RECREATION DEPARTMENT
By:Jeremy Helton
Title:Park Development Coordinator
Date:November 14,200
Accepted: .404404) 1411;
Fuerte Syste ��'�
Party of
p<<�.s . tor) •BY:
Title: if EkSIchM 4-
lir
Date: j I — IS-6_S
Approved:
CITY OF ELGIN
Party of the First Part(Owner)
By: ..C�ia a. ,(J eztve,..
6`
Title: %e "2./Plii,eJ
Date: /.2 .)--
N0V-42005 09:56A FROM:FUERTESYSTEMS 815 436 0566 TO:18479315983
P.2
FU E Ri Systems, INC.
Till 11111RONC, NA . Il IN 1111 •VIIIIS
BRICK PAVER-RETAINING WALL•N TURAL STONE SPECIALIST
•
DRIVEWAYS • PATIOS • !P ONT ENTRANCES
SIDEWALKS • PAR ING LOTS
COMMEROI•L
RESIDENTI•L
August 11, 2005
5
•
City of Elgin
150 Dexter Court
Elgin,IL. 60120
ATT: Jeremy Helton
RE: Mulberry Grove Park
Seat wall and pavers •
Involo-
FUERT.E SYSTEMS, INC. is to provide all lab• to:
Install 126 L.F of seat wall with coping paverlo•k retaining wall.
Install 182 S.F of Unilock hollanstone pavers •
Seatwall 126L.S x$58.00 $7,c 00.00
Brick pavers 182 S.F.x $8.00 - $1 56.00
Total change order: $8 64.00
Any alteration from the above specification invidying extra cost, will be executed only
upon written orders, and will become and extra harge over and above the estimate. All
agreements contin = • Don strike, accidents, 0 delays beyond our control. FUERTE
SYSTE INC/to all necessary insuf, ce upon above work.
AdOF
' = • urtado
/
P sident
•
2007 Cumberland Drive • Plainfield, IL 60$ • • 815-436-6186 • Cell: 847-312-9393
www.fuertea -tems.com
F V E R E Systems, INC.
THE STRONG NAME IN PAYERS
BRICK PAVER-RETAINING WALL-NATURAL STONE SPECIALIST
DRIVEWAYS • PATIOS • FRONT ENTRANCES fIf
SIDEWALKS • PARKING LOTS
COMMERCIAL
RESIDENTIAL
October 3,2005
City of Elgin
150 Dexter Court
Elgin,IL. 60120
ATT: Jeremy Helton
RE: Mulberry Grove Park
Install play surface,power rake, seed and fertilizer
Invoice
FUERTE SYSTEMS,INC. is to provide all labor and materials
_ I
Install play surface
Power rake, seed and fertilize.
Total Invoice: $ 7,900.00
Any alteration from the above specification involving extra cost,will be executed only
upon written orders, and will become and extra charge over and above the estimate. All
agreements contingent upon strike,accidents, or delays beyond our control. FUERTE
SYSTEMS,INC.is to carry all necessary insurance upon above work.
Raphael Hurtado
President
2007 Cumberland Drive • Plainfield, IL 60586 • 815-436-6196 • Cell:847-312-9393
www.fuertesystems.com
xttaa5fielat
•
PAGE ONE OF
APPLICATION AND CERTIFICATE FOR PAYMENT MA DOCUMENT G702
To0At 1 Oc ��c�1 PROJECT:Ftul` 1� ( ern' tcm) h APPLICATION ND:063 i ONM R to:
� 3MOOt ,� „�y �
k40 RCM\ A PERIOD TO: I)ARCHITECT
I i.y (0012-3
/�jJtJ GCC NO: I I CONTRACTOR
FROM(CONTRACTOR):f re, G1401'2 VIA ARCHITECT: II
�� r?d.b�tc"�:S�-4il . n
11
CONTRACT FOR A r I •i' • 0.C�'Or CONTRACT DATE:
CONTRACTOR'S APPLICATION FOR PAYMENT Application is made for Payment,as shown below,In connection with the Contract.
CHANGE ORDER SUMMARY Continuation Sheet,which is attached. V.
Change Orders approved In VALUES 1,ORIGINAL CONTRACT SUM s: •• o–
previous months by Owner 2.Net change by Change Orders , .. .
TOTAL 0 3.CONTRACT SUM TO DATE(Line 1 ±2) �E
Approved This Month 4.TOTAL COMPLETED&STORED TO DATEi>� �
Number Date Approved un
e, r�- (Column I on Continuation Sheet)
I 0-t I – Os- 4&–?(oy. 0 5.RETAINAGE: .
o-0 r— c7 �
Z /0 ..C3,-OS"...
O—c3_Q S— l+/r 900. a. %of Completed Work
0 J� (Column F+G on Continuation Sheet)
0 (J� b. %of Stored Material. ,• •�:,.')4 f all,0, ,
TOTALS a 0 i (Column H on Continuatic�k i I' '
Net change by Change Orders I (/rhs"' 0 %",,` Total Retainage(Line 5a+5b ? ("'�`A 3
t S Total In Column L of Conratfon Sheet) c'
The undersigned Contractor certifies that to the best of the Contractor's knowledge, 6.TOTAL EARNED LESS RETAINAGE tl�t #3'�l j C}f
rm
infoation and belief the Work covered by this Application for Payment has been (Line 4 less Line 5 Total) f'S7 £ \ I 1}
completed in accordance with the Contract Documents,that all amounts have been 7.LESS PREVIOUS CERTIFICATES•;FOR
paid by the Contractor for Work for which previous Certificates for Payment were PAYMENT(Line 6 from prior Certificate)) .,..r-,L.( S'�.. ...1) , 0.40•-7 cf
issued and payments received from the Owner,a that current payment shown B.CURRENT PAYMENT DUE...... i:[:�( Qv I- .,i et, ;ate
herein is now due. / 9.BALANCE TO FINISH,PLUS RETAINAGE �-ry — C,
'nos
(Line 3 less 6) ,- /fir
- CONTRACTOR: ,j l '��`�Ji��� ""—'1- State of: Illinois County of: iiisli
� Subscribed and sworn to before t• - O •
da.'f r v
By: �� � DATE:ia)3)ts- Notary Public-00w t,. /7/7 i OFFICIr..`ZEAL
����- �/ My Commission expires: ri, O . aOO , MARIA G.ht1;TAD+
`� ` `o. m 'PUBLIC-STATE OF ILLINOIS
ARCHITECT'S OR PAYMENT AMOUNT CERTIFIED MY.COMLOBSIONl'xPIRESBEBL-06,2ooq
a (An.ch as planation it amount cahbad dNbrs from IN,amount apprwd for.
In accordance with • ontract Documents,based on on-site observations
and the data comprising the above application,the Architect certifies to the ARCHIT Tr
Owner that the Work has progressed to the point indicated;that to the best •
of his knowledge,information and belief,the quality of the Work is In accordance By: - 'ri my Date: &
. with the Contract Documents;and that the Contractor is entitled to payment of the
AM• m+o=-'- • MATERIAL;SE F',.:;;27.,i This certificate is not negotiable. The AMOUNT CERTIFIED is payable only to Or Contractor
+� —1 r.� y�V`U Ir. named herein. Issuance,payment and acceptance of payment are without prejudice to any
I`{�`.{` rights of the Owner or Contractor under this Contrail.
1
,<.<OF k-,,, L
¢G` a '~• City of Elgin Agenda Item No.
�;;t aur
E
L
November 23, 2005
TO: Mayor and Members of the City Council (pm/ N
T, ,n
FROM: Olufemi Folarin, City Manager " �
EGR . QN^`,`U�' 10,
ANC>F Ft114 Al I CIPPo F.nis T1fa 5.
Randy Reopelle, Director of Parks and Recreation
SUBJECT: Mulberry Grove Park Project- Change Order Number 1 and Final Payment
PURPOSE
The purpose of this memorandum is to provide the Mayor and members of the City Council with
information to consider the authorization of Change Order Number 1 and Final Payment to
Fuerte Systems, Inc. for the Mulberry Grove Park construction.
RECOMMENDATION
Pk' It is recommended that the City Council authorize execution of Change Order Number 1 in the
amount of $16,664, and authorize final payment to Fuerte Systems, Inc. in the amount of
$43,671.21 for the Mulberry Grove Park construction contract.
BACKGROUND
In May, 2005, the City entered into a contract with Fuerte Systems Inc. of Plainfield, Illinois for
the construction of Mulberry Grove Park in the amount of $358,308.00. The contract amount
was based upon bid documents consisting of construction drawings and specifications prepared
by Park and Recreation Department staff. The original budget for this project was $446,410.
During the course of construction, it became apparent that several steel benches included in the
original construction drawings and specifications would not be available until several months
after the park construction was completed. The addition of a decorative block unit seating wall
was added to the project to replace the seating capacity near the playground. Additionally, soil
and turf conditions on the site required additional landscape work and over-seeding to remove
existing debris and assure the survival of the turf on the grass practice field.
COMMUNITY GROUPS/INTERESTED PERSONS CONTACTED
None
".,. FINANCIAL IMPACT
The original budget for Mulberry Grove Park was as follows:
CO #1 & Final Payment for Mulberry Grove Park Construction Contract
November 23, 2005
Page 2
Revenues
Riverboat Fund , account number 275-0000-791.92-37 $205,425
Park Development Fund, account number 340-0000-795.92-32 • 241,065
Total Revenues $446,490
Expenditures
Fuerte Systems $358,308
Change Order 1 16,664
Sub Total $374,972
Miscellaneous 4,771
Total Expenditures $379,743
Balance Remaining $66,747
A copy of the Change Order Summary and documentation are attached as Exhibit A.
el""k A copy of the final pay application is attached as Exhibit B. •
There are sufficient funds available ($27,007) in account number 275-0000-791.92-37, and
sufficient funds available, ($83,411) in account number 340-0000-795.92-32, project number
509622 for Change Order Number 1 and Final Payment to Fuerte Systems in the amount of
$43,671.
\INI//EGAL IMPACT
None
ALTERNATIVES
1. Approve Change Order Number 1 and Final Payment.
2. Do not approve Change Order Number 1 and Final Payment.
Respectfully submitted for Council consideration.
(mjh)
Attachments