HomeMy WebLinkAbout01-179 Resolution No. 01-179
RESOLUTION
APPROVING CHANGE ORDER NO. 1 IN THE CONTRACT WITH
ILLINOIS CONSTRUCTORS CORPORATION FOR THE REHABILITATION
OF THREE BRIDGES
WHEREAS, the City of Elgin has heretofore entered into a
contract with Illinois Constructors Corporation for the
rehabilitation of three bridges; and
WHEREAS, it is necessaryand desirable to modifythe terms of
the contract as is described in Change Order No. 1, attached
hereto.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY
OF ELGIN, ILLINOIS, that Joyce A. Parker, City Manager, be and is
hereby authorized and directed to execute Change Order No. 1, a
copy of which is attached hereto and made a part hereof by
reference .
s/ Ed Schock
Ed Schock, Mayor
Presented: June 27, 2001
Adopted: June 27, 2001
Omnibus Vote: Yeas : 7 Nays : 0
Recorded:
Attest :
s/ Dolonna Mecum
Dolonna Mecum, City Clerk
ELGIN, ILLINOIS
PROJECT 339563
CHANGE ORDER No. 1
SCOPE: This Change Order No. 1 will add one new pay item to the contract and
increase or decrease several existing pay items.
The general contractor for this project is Illinois Constructors Corporation of St. Charles,
Illinois.
REASON FOR CHANGE: This Change Order No. 1 is in the best interest of the City
and is authorized by law.
SUMMARY OF CHANGES IN CONTRACT AMOUNT:
SEE EXHIBIT A
The original contract with Illinois Constructors Corporation is $361,035.50. By reason of
Change Order No. 1, the contract for the Rehabilitation of Three Bridges Project will be
increased in the amount of twenty two thousand two hundred seventy and 00/100
dollars ($22,270.00). The new contract amount, inclusive of Change Order No. 1 is
three hundred eighty three thousand three hundred five and 50/100 ($383,305.50).
PROJECT 339563
CHANGE ORDER NO. 1
May 25,2001
PAGE 2 OF 3
OTHER CONTRACT PROVISIONS: All other contract provisions shall remain the
same.
Agreed to this day of , 2001.
Recommended:
ENGINEERING DIVISION
By: CL
Title: Fiv ci'v£FR 2
Date: /la 29, 2Oo/
Accepted:
IL N CONSTRUCTORS CORPORATION
Pa o Second Part (Contractor)
By:
Title: ?*QIiç
Date: -2 512
Approved:
CITY OF ELGIN
Party of the First Part (Owner)
By: 4.4r., t
Title: O24
r "
Date: 9.we 2�ji Lo o l
PROJECT 339563
CHANGE ORDER NO. 1
May 25,2001 .
PAGE 3 OF 3
EXHIBIT A
ITEM UNIT PRICE INCREASE DECREASE ADDITIONAL REDUCED
QUANTITY QUANTITY AMOUNT AMOUNT
Parking Area Repair $5,105/LS 1 $5,105.00
Bituminous Surface Removal $7.00/SY 87 $610.00
Binder Course $85.00/TON 19 $1,615.00
Surface Course $85.00/TON 19 $1,615.00
Prime Coat $2.50/GAL 20 $50.00
Formed Concrete Repair $75.00/SF 322 $24,150.00
Repair Keyway $50.00/LF 350 $17,500.00
Preformed Joint Seal $55.00/LF 10 $550.00
Concrete Removal $870.00/CY (2.5) ($2,175.00)
Class SI Concrete $700.00/CY (2.5) ($1,750.00)
Bridge Sidewalk Repair - Full Depth $27.00/SF (926) ($25,000.00)
TOTAL CHANGE $51,195.00 ($28,925.00)
NET CHANGE ORDER NO. 1 $22,270.00