HomeMy WebLinkAbout17-54 Resolution No. 17-54
RESOLUTION
AUTHORIZING EXECUTION OF AMENDMENT AGREEMENT NO. 2
WITH ENGINEERING ENTERPRISES, INC. FOR
SUPPLEMENTAL PROFESSIONAL DESIGN SERVICES REGARDING
FURTHER EXTENSION OF THE SANITARY SEWER TRUNK LINE
IN CONNECTION WITH THE SOUTH STREET EXTENSION PROJECT
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF ELGIN, ILLINOIS,
that Richard G. Kozal, City Manager, and Kimberly A. Dewis, City Clerk, be and are hereby
authorized and directed to execute Amendment Agreement No. 2 on behalf of the City of Elgin
with Engineering Enterprises, Inc. for supplemental professional design services regarding
further extension of the sanitary sewer trunk line in connection with the South Street Extension
Project, a copy of which is attached hereto and made a part hereof by reference.
s/David J. Kaptain
David J. Kaptain, Mayor
Presented: April 26, 2017
Adopted: April 26, 2017
Omnibus Vote: Yeas: 7 Nays: 2
Attest:
s/Kimberly Dewis
Kimberly Dewis, City Clerk
AMENDMENT AGREEMENT No. 2
THIS AMENDMENT AGREEMENT No. 2 is hereby made and entered into this 26 day of
April , 2017, by and between the City of Elgin, Illinois, a municipal corporation
(hereinafter referred to as the "City"), and Engineering Enterprises, Inc., an Illinois corporation
(hereinafter referred to as "Engineer").
WHEREAS, the City and Engineer hereto have previously entered into an agreement dated April
8, 2015 (hereinafter referred to as "ORIGINAL AGREEMENT"), wherein the City engaged the
Engineer to furnish certain professional design services in connection with the South Street
Extension improvements(hereinafter referred to as the "Project"); and
WHEREAS, the City and Engineer hereto have previously entered into an amendment agreement
No. 1 dated September 9, 2015 (hereinafter referred to as "AMENDMENT AGREEMENT
NO.1"), wherein the City engaged the Engineer to furnish certain professional construction
administration and observation services in connection with the"Project"; and
WHEREAS, the ORIGINAL AGREEMENT and AMENDMENT AGREEMENT NO. 1
included the design and the construction administration of an extension of a sanitary sewer trunk
line, also known as BRIS TR 20, as part of the South Street Extension improvements; and
WHEREAS, the parties hereto have determined it to be in their best interest to amend Original
Agreement and Amendment Agreement No. 1; and
WHEREAS, the City has determined that the proposed scope of the Project should be modified
to include Supplemental Professional Design Services for further extension of the sanitary sewer
trunk line, extension to be known as BRIS TR 20 — Phase 2 Gravity Extension, from the
previously completed South Street Extension sanitary sewer trunk line — Attachment C-1 and
Additional Construction Phase Professional Engineering Services for the South Street Extension
—Attachment C-2 (hereinafter referred to as"Supplemental Services"); and
WHEREAS, the Original Agreement provides for a maximum payment of$305,051.00; and the
Amendment Agreement No. 1 provides for a maximum payment of$741,329.00; and
WHEREAS, the parties hereto have determined and agree that the total maximum payment for
the Supplemental Services described in this Amendment Agreement No. 2 shall be in the amount
of$ 96,671.00; and
WHEREAS, the changes contemplated by this Amendment Agreement No. 2 are germane to the
Original Agreement and the Amendment Agreement No.l as signed; and this Amendment
Agreement No. 2 is in the best interests of City and is authorized by law.
NOW, THEREFORE, for and in consideration of the mutual promises and covenants provided
for herein, and other good and valuable consideration, the sufficiency of which is hereby
acknowledged, the parties hereto agree as follows:
1. The above recitals are incorporated into and made a part of this agreement as if fully
recited hereby.
2. That Section 1 of the Original Agreement is hereby amended by adding the following
subparagraph D thereto to read as follows:
"D. The Engineer shall also provide Supplemental Services for the Project which
includes the Supplemental Professional Design Services for the further extension of the
sanitary sewer trunk line (BRIS TR 20 — Phase 2 Gravity Extension) in accordance with
Attachment C-1 and Additional Construction Phase Professional Engineering Services
for the South Street Extension in accordance with Attachment C-2. Engineer shall furnish
such Supplemental Services for the Project as outlined and detailed in Attachments C-1
and C-2,"
3. That Section 2 of the Original Agreement is hereby amended by adding the following to
the end of Subparagraph B:
"Engineer shall provide the Supplemental Services provided for in Amendment
Agreement No. 2 in accordance with the schedule outlined herein and detailed in
Attachment B-3."
4. That Section 4 of the Original Agreement is hereby amended by adding the following
paragraph D and Payment Schedule to read as follows:
"D. For services described in Attachments B-3, C-1, and C-2, Engineer shall be paid at
an hourly rate for the classifications of personnel who perform work on this Project;
provided, however, that Engineer shall be paid a total maximum fee of S 96,671.00 for
the services to be provided pursuant to this Amendment Agreement No. 2, regardless of
the actual time or actual costs incurred by the Engineer unless substantial modifications
and scope of work are authorized in writing by the City and approved pursuant to a
further written amendment to this Agreement. The total fees to be paid to the Engineer
pursuant to the Original Agreement, Amendment Agreement No. 1, and Amendment
Agreement No. 2 now total $1,143,051.00. The detailed basis of the additional fee
associated with Amendment Agreement No. 2 is included in Attachments C-1 and C-2
and is based on hourly rates of personnel utilized. The attached Standard Schedule of
Charges dated January 2017 will be utilized for this Project."
Payment Schedule for Supplemental Services
ESTIMATED ESTIMATED VALUE ESTIMATED INVOICE
DATE %COMPLETE OF WORK COMPLETE VALUE
4/30/2017 20% $ 19,334.20 $ 19,334.20
5/31/2017 25% $ 43,501.95 $ 24,167.75
6/30/2017 25% $ 67,669.70 $ 24,167.75
7/31/2017 5% $ 72,503.25 $ 4,833.55
8/31/2017 5% $ 77,336.80 $ 4,833.55
9/30/2017 5% $ 82,170.35 $ 4,833.55
10/31/2017 5% $ 87,003.90 $ 4,833.55
11/31/17 5% $ 91,837.45 $ 4,833.55
12/31/2017 5% $ 96,671.00 $ 4,833.55
Total 100% $ 96,671.00
6. That except as amended in this Amendment Agreement No. 2, and as previously
amended in Amendment Agreement No. 1, the Original Agreement shall remain in full
force and effect.
7. That in the event of any conflict between the terms of this Amendment Agreement No. 2
and the terms of the Original Agreement as previously amended by Amendment
Agreement No. 1, the provisions of this Amendment Agreement No. 2 shall control.
IN WITNESS WHEREOF, the undersigned have entered into and executed this Amendment
Agreement as of the date and year first written above.
CITY OF IN CONSULTANT
By: By: dfoj±gk�
City Manager Its Vice President
Att Attest:
ity Clerk I Its x rve Assistant
ATTACHMENT B-PROPOSED SCHEDULE -
BRIS TR20-PHASE 2 GRAVITY EXTENSION ELGIN
Cq d Elfin
VON
am Oaiaao I wwmbw I Dwwar
ow 1 t t 3 1 4 1 1 1 111 1 s 1 ♦1 t 1 8111114111912 ♦ 1 1 21 91 ♦ t 1 It a ♦ t 1 1 a I a I t a I s I it I f a a ♦ 1 a 3141 1 i a
1 cmolw
7 C 1 SuV and F1 6Nes IV)In – _
a teclxcMKM Mp WMUw kN Lm
G Cow tort
ti nal plans am
7 a
coa
19 om
Losmad
qM:l AMWwYMon/M.rugMMnl ffW ErgravVy
PMrineatp
1NSry•u�pnflrnrpWQMr9ns �p.Ild COfal.Clatq
K.1 D.1—
A#- E—..d BY VIrlw7
wolwo OMrrolaoo 6=2017 {catwrvNrva slaty halo oawu ort 9ttAwrg wain CuuW OLrI as oalM al.I l li
6(iR Yi.nYdIMIW 53312011
FIJI for WMIMM OW-- 61IFU17 (MrY9sl Oal.l
F*W WWWa RO l 6VIS12017 (assunedl
90%P4n.ltd Sew:Sub nal In2017
P_15uDn"ilEPAI 90%PIMN In 2017
P,m S't".](ACOE)-W%Plain 71?72017
)EPA Paint RM1.NM1 WM017 I.SaJnw 90 o.w
ACOE PMmt Rawvw 12QW2017 (Now uw h.RP;
Ca Ww w Son 3172010 (lglnWQd 90 t Lana drys a 4Irlo"W
Ca uctw Ertl W3&2014
ATTACHMENT C-1•ESTIMATE OF LEVEL OF EFFORT AND ASSOCIATED COST
PROFESSIONAL ENGINEERING SERVICES
page 1 of 2
Egon to lurthar extend a sanitary sewer trunk hm recently complatstl with Mw South Streit Extenswn prelect-ooni ary sewer trunk
Nn.is known as Braves Road Int.rcegor Sewer Trunk 20. TNs exNnwon will bo c WI•KRIS TR 20-Phase 2 Gravity Extension' ELGIN
Soon exlen4ons are d".ted on Paps 2 012 of this ATTACHMENT C-1.
CITY OF ELGIN.ILLINOIS na s>n w na suraane
&am. ■QR
FINNaAL 80011 1101 OOiT
s1011a I11164060hs IN rlloma I Maio NlpxCr -MKW /IOI,sIOY CAD Imm"cT M011R P01
ffm oaat111N1 rilNioip GURVg # 1ECNMKWn Am IW
sum II
M0. Now RIN glaiM.Y Mtt. 111196 llin NM an slit Nita NMi
n PQ WA 7
1 9 709
' C t f F N x1- tl �1 17 11257
4 - t l and w#1141.)Ir I n 1 '1 7 1 1, t2 S♦
c Utility r
♦ a 592
h Foho Mans WW 19 ,20 32 y vu ♦ ?5' 3
7 14_QLWA&un W( MW,#r4l F%wnaM 1 3 d 1', :U S 1'lb7
d
pqmts 21 15 4 S b 89?
4 CI wklnr C.orxdunat 3 / '1
ID end C rsc -
.p, a•-. v-. .. 1 8 13 tl t9
32 4915
e
1 A00 E 9Eu»rw. 1 59.467
Slooae}i Iarx- S 500 5wveriltl E spenep. 10ITJ9
lieelecNlrri IR�dw a k00 Oraerna f aperuee. 10
W.OSb DeMWm. (HuMi1MJ11. t SAW AdmnMaWeF $ b0
E-voor+nanse,mccW 11fu11 i H,e). S 7.500
ATTACHMENT C-1 PAGE 2 OF 2 N
LOCATION MAP - RECENTLY COMPLETED
SANITARY SEWER TRUNK LINE WITH SOUTH STREET EXTENSION
AND PROPOSED FURTHER EXTENSION OF SAME
Proposed Engineering Design of Sanitary Sewer o _
Trunk Line to be extended from the sanitary sewer %V— Non liven
trunk line built with the South Street Extension: /d Cb
1. Portion of the Phase of BRIS Trunk 20 (green) �e Ke�'ehoo
constructed with South Street in 2016 ti
2. Portion of the Phase of BRIS Trunk 20 (blue) US?O a0��
currently under consideration 2017 Od
Bo
h �
Sutton C, ORIGINAL FINAL PHASE .S
0 OF BRIS Trunk 20 °Ss,
Hughsdale
Marion
Mosedale Phase of BRIS Trunk 20
Bridgeham � o 00 Qa currently under
c c cON 0 ,,Ohnar consideration
,te ` Sbaaold
` 0G0
a
` insert `ejdS
'2
m
Burgess
Jaguar r
O
r0
South Street cc
Phase of BRIS Trunk 20
built with South Street
Linsmore
Midleton Lismore
Arye Cape trod m
Wexford 'g
� e �
0
1480oft
ya�4 r�F
Waterford �� V GOOK
tetf°rd GrYsta
*� Vra N?ck/q
1%,l Pn° Phase of BRIS Trunk 20
built by Kimball Hill in 2004
ATTACHMENT C-::ESTIMATE OF LEVEL OF EFFORT AND ASSOCIATED COST E LG 1 N
ADDITIONAL CONSTRUCTION PHASE FROFESSIONAL ENGINEERING SERVICES
ne rnr«..a sr..s
SW M STREET EXTENSION
Caty of Ugim tL
42Doz 1M011= a /IIOIECT Fh*= MOwCI NIImm NIOIKT PNWKf CAC NIo= ROIRI NRI
um pN sm SNt 11Ei qM i/i]
i 11 S t9 S 27A5
is lowsw 9Andns $
• 11111111 IMR
En -- 4 S 370
S 4.750
pWyflyf.Vl1� S 665
Standard Schedule I Charges
January I
EMPLOYEE DESIGNATION CLASSIFICATION HOURLY RATE
Senior Principal E-4 $196.00
Principal E-3 $191.00
Senior Project Manager E-2 $185.00
Project Manager E-1 $168.00
Senior Project Engineer/Planner/Surveyor II P-6 $155.00
Senior Project Engineer/Planner/Surveyor I P-5 $145.00
Project Engineer/Planner/Surveyor P-4 $133.00
Senior Engineer/Planner/Surveyor P-3 $121.00
Engineer/Planner/Surveyor P-2 $111.00
Associate Engineer/Planner/Surveyor P-1 $100.00
Senior Project Technician 11 T-6 $145.00
Senior Project Technician I T-5 $133.00
Project Technician T-4 $121.00
Senior Technician T-3 $111.00
Technician T-2 $100.00
Associate Technician T-1 $ 87.00
Engineering/Land Surveying Intern 1-1 $ 82.00
GISTechnician G-1 $ 67.00
Administrative Assistant A-3 $ 80.00
CREW RATES,VEHICLES AND REPROGRAPHICS
1 Man Field Crew with Standard Survey Equipment $158.00
2 Man Field Crew with Standard Survey Equipment $247.00
1 Man Field Crew with RTS or GPS* $196.00
2 Man Field Crew with RTS or GPS* 5284.00
Vehicle for Construction Observation $15.00
In-House Scanning and Reproduction $0.25/Sq.Ft.(Black&White)
$1.00/Sq.Ft.(Color)
Reimbursable Direct Costs&Services by Others Cost+ 10%
*RTS=Robotic Total Station/GPS=Global Positioning System