HomeMy WebLinkAbout17-49 Resolution No. 17-49
RESOLUTION
AUTHORIZING EXECUTION OF AMENDMENT AGREEMENT NO. 2
WITH SMITHGROUP JJR FOR DESIGN AND ENGINEERING SERVICES
IN CONNECTION WITH THE JACK E. COOK PARK
PARKING EXPANSION PROJECT
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF ELGIN, ILLINOIS,
that Richard G. Kozal, City Manager, and Kimberly A. Dewis, City Clerk, be and are hereby
authorized and directed to execute Amendment Agreement No. 2 on behalf of the City of Elgin
with SmithGroup JJR for design and engineering services in connection with the Jack E. Cook
Park Parking Expansion Project, a copy of which is attached hereto and made a part hereof by
reference.
s/David J. Kaptain
David J. Kaptain, Mayor
Presented: April 12, 2017
Adopted: April 12, 2017
Omnibus Vote: Yeas: 8 Nays: 0
Attest:
s/Kimberly Dewis
Kimberly Dewis, City Clerk
AMENDMENT AGREEMENT NO. 2
THIS AMENDMENT AGREEMENT NO. 2 is hereby made and entered into this 12th
day of April , 2017, by and between the City of Elgin, Illinois, a municipal corporation
(hereinafter referred to as the "City"), and SmithGroup JJR, an Illinois professional service
corporation (hereinafter referred to as "Engineer").
WHEREAS, the City and Engineer have previously entered into an agreement dated
August 22, 2012, where in the City engaged the Engineer to furnish certain professional services
in connection with the Regional Park Phase I development (hereinafter referred to as the "Subject
Agreement" and the "Project"); and
WHEREAS, the City and Engineer have previously entered into Amendment Agreement
No. 1 dated May 8, 2013, wherein the parties agreed to add additional services to the scope of
work for proposed Project to include the bidding and award phase and the construction
administration and engineering phase; and
WHEREAS, the City has determined to proceed with Phase 11 improvements to the Subject
Jack E. Cook Regional Park for the Engineer to provide additional services relating to the final
design,permit coordination,bidding documents and construction administration of the parking lot
expansion.
NOW, THEREFORE, for and in consideration of the mutual undertakings as set forth in
the Subject Agreement, and the mutual undertakings as set forth in this Amendment Agreement
No. 2, and other good and valuable consideration, the receipt and sufficiency of which is hereby
acknowledge, the parties hereto agree as follows:
1. Section IB of the Subject Agreement is hereby further amended by adding the
following to the end thereof:
"The CONSULTANT shall also provide the construction documentation;
permitting, bidding and award; and construction phase services for the parking lot
expansion portion of the PROJECT. A Scope of Services for the additional services
to be provided pursuant to this Amendment Agreement No. 2 is provided in
CONSULTANT'S proposal therefore dated _March 14 , 2017, attached
hereto as Attachment A-2. The schedule for such additional services is included
within Attachment A-2."
2. Section 4 of the Subject Agreement is hereby amended by adding a new
subparagraph F thereto to read as follows:
"F. For services provided by the CONSULTANT pursuant to Amendment
Agreement No. 2 as set forth in Attachment A-2,the CONSULTANT shall be paid
a lump sum of$12,000 for the construction phase, $9,500 for the bidding, award
and permitting phase and $6,000 for the construction administration and periodic
observation phase, for a total of$27,500 inclusive of all costs and expenses of the
CONSULTANT,regardless of actual costs incurred by the CONSULTANT unless
substantial modifications to the Scope of Work are authorized in writing by the
DIRECTOR and approved by way of written amendment to this Agreement. No
additional services shall be provided nor additional fees or expenses paid unless
approved by way of written amendment to this Agreement."
3. The changes provided to the Subject Agreement as provided in this Amendment
Agreement No. 2 are germane to the original contract as signed and this Amendment Agreement
is in the best interests of the City and is authorized by law.
4. That except as amended in this Amendment Agreement No. 2, and as previously
amended by Amendment Agreement No. 1, the Subject Agreement shall remain in full force and
effect.
5. That in the event of any conflict between the terms of this Amendment Agreement
No. 2, and the terms of the Subject Agreement or Amendment Agreement No. 1, the provisions of
this Amendment Agreement No. 2 shall control.
IN WITNESS WHEREOF, the undersigned have entered into and executed this
Amendment Agreement as of the date and year first written above.
CITY OF ELGIN CONTRACTOR
By- By:
City Manager Its
Attest: Attest:
City Clerk Its
FALegal Dept\Agreement\SmithGroup JJR-Amend Agr#2-3-10-17.docx
- 2 -
SMITHOROUP0Attachment A-2
March 14, 2017
Maria Cumpata
City of Elgin
100 Symphony Way
Elgin, Illinois 60120
RE: Scope of Services
Jack Cook Park Parking Expansion
Dear Maria:
On behalf of SmithGroupJJR, Inc.,("SmithGroupJJR")we are pleased to submit this proposal for design and
engineering services for the Jack E Cook Park Parking Expansion in Elgin, IL. We have recently completed the
Schematic Design and preliminary stormwater management design for this project and are prepared to continue into
the next phases. The following is our understanding of the services which are to be provided.
UNDERSTANDING OF THE PROJECT
The City of Elgin would like SGJJR provide the following services:develop drawings and specifications for Bid and
Construction of the Jack E. Cook Park parking lot expansion, based on the attached Exhibit A Schematic Design and
stormwater management design, issued on August 2, 2016; Preparation and issuance of stormwater permit
documents; provide construction observation services. Proposed designs shall be in compliance with local codes
and ordinances.
This proposal is based upon a construction budget of$304,000.
Exclusions include survey,geotechnical,electrical, and site structural.
SCOPE OF SERVICES
The following represents our recommended Scope of Work to completing this project within the timeframe and
budget available. For purposes of this proposal,"Client'shall mean City of Elgin.
A. PHASE 1:CONSTRUCTION DOCUMENTATION
Task 1.1 Construction Documents
SGJJR will prepare Construction Drawings and Specifications for one bid package setting forth in
detail the requirements for the construction of the project.
• SGJJR will prepare fully coordinated documents conforming to applicable district,
municipal,county, state and federal laws, regulations,ordinances and interpretations of
same.
• SGJJR will develop,coordinate and complete the technical specifications,which
designate all construction materials,systems,qualities,workmanship and equipment,
City of Elgin Jack E.Cook Park SmithGroupJJR
Elgin, IL
LETTER FORM PROPOSAL -1 - 02/06/2017
SMITHOROUPRAttachment A-2
using the CSI format. Front End Documents(General and Supplementary Conditions)will
be provided by the Client but will be incorporated by SGJJR into the Project Manual.
Task 1.2 Coordination Meetings and Reviews
SGJJR will participate in two(2) meetings with the Client during the Construction Documentation
Phase for purposes of reviewing the Documents.
B. PHASE 2: PERMITTING, BIDDING AND AWARD
Task 2.1 Permit Coordination
SGJJR will prepare and submit permit applications to assist the Client in obtaining the necessary
regulatory permits and approvals. SGJJR services include original submittal to the regulatory
agency plus up to one re-submittal based upon agency comments. Additional submittals could be
cause for additional compensation, For this project, approval from the following agency is
anticipated:
• City of Elgin—Stormwater management permit
• IEPA—National Pollution Discharge Elimination System Permit Coverage
Task 2.2 Bidding: Clarifications
SGJJR will answer questions and supply additional detail to the Bid Documents to clarify
contradictions or ambiguities and will participate in one Pre-Bid meeting.
Task 2.3 Award:Scope Review
SGJJR will attend up to one(1)subcontractor scope review meetings related to site development.
Bid advertisement,distribution, opening and tabulation by Client.
C. PHASE 3: CONSTRUCTION PHASE SERVICES
Task 3.1 Construction Administration
SGJJR will commence Construction Administration services and responsibilities upon the award to
a Contractor of one contract for construction of the project and terminate such services at the end
of the Contractor's one-year warranty and guaranty period.
• SGJJR will participate in one pre-construction meeting.
• SGJJR will promptly monitor and coordinate with the Contractor the timing of submittals;
check, note and review Shop Drawings, material samples,and other submissions and
proposals of the Contractor(s)for compliance with the working drawings,specifications
and design intent.
City of Elgin Jack E.Cook Park SmithGroupJJR
Elgin, IL
LETTER FORM PROPOSAL -2- 02/06/2017
SMITHHOUPMAttachment A-2
• SGJJR will review and check the inspection reports and periodic field test reports and
data provided by the Owner's testing and inspection entity.
• SGJJR will respond to RFI's submitted by the Contractor and assist in the preparation of
bulletins,change orders,and supplemental instructions including clarifications and
progress reports when directed by the Client.
• SGJJR will review as-builts(prepared by the Contractors)and will deliver them to the
Client within thirty days after completion of construction and before final payment is
approved for the Contractor.
Task 3.2 Periodic Site Observations
• SGJJR will make weekly visits to the site during construction when requested by the
Client. During the site visits, SGJJR will become generally familiar with the progress and
quality of the work and will determine, in general, if the work is proceeding in accordance
with the Contract Documents. (Maximum 4 site visits.)
• SGJJR will not have control or charge of and will not be responsible for construction
means, methods,techniques,sequences or procedures,or for safety precautions and
programs in connection with the work,or for the acts or omissions of the Contractor,
Subcontractors or any other persons performing any of the work,or for the failure of any
of them to carry out the work in accordance with the Contract Documents, unless SGJJR
has observed a defect in the work and fails to report the same in writing to the Client,or
should have observed the defect in the exercise of the standard of professional care set
forth in this agreement.
• SGJJR will conduct inspections to determine the date of Substantial Completion of the
work by the Contractor,and shall compile a"Punch List"of items that are not in
compliance with the Contract Documents. (Maximum 1 site visits)
• SGJJR will conduct subsequent inspections to determine that the Contractor has
satisfactorily completed all Punch List items,and has otherwise complied with the
Contract Documents including, but not limited to,the completion and delivery to SGJJR of
all record drawings and all appropriate manuals and written warranties as required by the
Contract. (Maximum 1 site visits).
• Additional site visits could be cause for additional compensation.
ASSUMPTIONS
Construction documents for the parking lot expansion will be based on the Schematic Design documents, issued on
August 2,2016,approved by the City of Elgin.
The City of Elgin will coordinate and acquire a topographic survey of the Phase 1 development area to serve as base
information for the proposed Construction Documents.
SCHEDULE
SGJJR is prepared to proceed with the services outlined in this proposal upon receipt of a signed copy. SGJJR will
endeavor to complete the Contract Documents for an Issued for Bid date of Spring 2017,with construction beginning
mid-May of 2017 and completion of items by early-August 2017.
City of Elgin Jack E.Cook Park SmithGroupJJR
Elgin, IL
LETTER FORM PROPOSAL -3- 02/06/2017
SMITHOROUNJRAttachment A-2
COMPENSATION or PROFESSIONAL SERVICES FEE
The following lump sum fees are based on the Scope of Services, schedule and personnel assigned to the project.
SGJJR Labor Fee—Lump Sum
Contract Documents: $ 12,000
Bid,Award and Permitting: $ 9,500
Construction Administration and Periodic Observation: 6,000
Total: $ 27,500
ADDITIONAL SERVICES
Requests for additional services or staff will be documented by SmithGroupJJR(if given verbally),and the work will
commence upon The City of Elgin approval of an estimated fee for that effort or, if not agreed otherwise,The City of
Elgin shall reimburse SmithGroupJJR on an hourly basis of SmithGroupJJR's project staff actively engaged for all
man hours worked on the project. See attached exhibit A-hourly wage sheet,
Attachment: Exhibit'A'—Hourly Wage Sheet
Exhibit'B'—SD Exhibit
City of Elgin Jack E.Cook Park SmithGroupJJR
Elgin, IL
LETTER FORM PROPOSAL -4- 02/06/2017
SMITHGROUNA Exhibit
WAGE RATES BY CLASSIFICATION FOR 2017*
Class Description Billing Rate
Principal In Charge $ 290
Senior Project Manager $ 260
Design Principal $ 240
Landscape Architect V $ 210
Landscape Architect IV $ 155
Landscape Architect III $ 125
Landscape Architect II $ 95
Landscape Architect 1 $ 85
Civil Engineer V $ 245
Civil Engineer IV $ 175
Civil Engineer III $ 150
Civil Engineer II $ 120
Civil Engineer 1 $ 95
Specification Writer $ 170
Urban Designer $ 190
Mixed-Use Design Specialist $ 190
Technical/Administration $ 85
Intern $ 80
Adminstrative Assistant $ 85
Construction Specialist $ 190
Building Tech Specialist $ 190
BIM CAD Specialist $ 150
Sr Lighting Designer $ 210
Lighting Designer $ 120
Visualization Specialist $ 135
Business Development $ 200
Marketing $ 120
Note: Project managers will be billed at their classification rate.
*Rates are subject to annual review and increase