HomeMy WebLinkAbout08-259 Resolution No. 08-259
RESOLUTION
APPROVING CHANGE ORDER NO. 2 IN THE CONTRACT WITH
RYAN CENTRAL, INC. FOR CONSTRUCTION OF
THE HIGHLANDS PHASE II GOLF COURSE
WHEREAS,the City of Elgin has heretofore entered into a contract with Ryan Central,Inc.
for construction of The Highlands Phase II Golf Course; and
WHEREAS, it is necessary and desirable to modify the terms of the contract as is described
in Change Order No. 2, attached hereto.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF
ELGIN,ILLINOIS,that Olufemi Folarin,City Manager,be and is hereby authorized and directed to
execute Change Order No.2,a copy of which is attached hereto and made a part hereof by reference.
s/Ed Schock
Ed Schock, Mayor
Presented: November 5, 2008
Adopted: November 5, 2008
Omnibus Vote: Yeas: 6 Nays: 0
Attest:
s/Diane Robertson
Diane Robertson, City Clerk
�.i of 6,C
City of Elgin Change Order
ELGIN,ILLINOIS
PROJECT 509637
CHANGE ORDER NO.2
CONTRACT: Construction of the Highlands of Elgin Golf Course—Phase II
SCOPE:
This change order affects a contract between the City and Ryan Incorporated Central dated April 23,2006 for the construc-
tion of the Highlands of Elgin Golf Course—Phase II.
REASONS FOR CHANGE: Change Order No.2 is in the best interest of the City and is authorized by law. The necessity
for the change was unforeseen at the time the contract was originally executed. The changes contemplated in Change Order
No.2 are germane to the original contract.
SUMMARY OF CHANGES IN CONTRACT AMOUNT:
ORIGINAL CONTRACT AMOUNT $ 3,505,640.10
CHANGE ORDER NO.2:
Unit Extended
Description Quantity Unit Price Price
Erosion Control: Silt Fence-Add 200 LF $ 2.90 $ 580.00
Erosion Control:Rip Rap Apron @ Pipe Outlet-Add 2 EA $ 550.00 $ 1,100.00
Clearing: Wetland Clearing-Add 0.5 AC $ 9,500.00 $ 4,750.00
Erosion Control&Clearing Subtotal: $ 6,430.00
Drainage:Primary Interceptor Line-Deduct (248) LF $ 83.85 $ (20,794.80)
Drainage: Interceptor Line Cleanouts-Add 2 EA $ 800.00 $ 1,600.00
Drainage:French Drain-Add 290 LF $ 15.00 $ 4,350.00
Drainage Subtotal: $ (14,844.80)
Grassing: Seed Upland Prairie(Fescue)-Deduct (5.6) AC $ 710.00 $ (3,976.00)
Grassing: Seed Upland Prairie(Native)-Add 5.6 AC $ 1,520.00 $ 8,512.00
Grassing: Seed Upland Prairie&Blanket(Fescue)-Deduct (5.4) AC $ 9,920.00 $ (53,568.00)
Grassing: Seed Upland Prairie&Blanket(Native)-Add 5.4 AC $ 10,730.00 $ 57,942.00
Grassing: SC 150 in lieu of C125 Blanket-Deduct (5.4) AC $ 500.00 $ (2,700.00)
Grassing: Sod Allowance-Deduct (100,000) SF $ 0.43 $ (43,000.00)
Grassing:Rough Seed&Futerra Allowance-Add 186,957 SF $ 0.23 $ 43,000.00
Grassing: Straw Mulch-Deduct (64.8) AC $ 675.00 $ (43,740.00)
Grassing: Straw Mulch Crimped-Add 37.8 AC $ 790.00 $ 29,862.00
Grassing Subtotal: $ (7,668.00)
Addition:Hole No. 14 Grading-Add 1 LS 980.00 $ 980.00
Addition: Hole No. 3 Well Capping-Add 1 LS 1,150.00 $ 1,150.00
Addition: Cart Path Sleeves for Utilities-Add 60 LF 27.00 $ 1,620.00
Addition: Creek Crossings on Hole No.4-Add 2 EA 6,000.00 $ 12,000.00
Addition:Comfort Station Foundation-Add 1 LS 33,475.00 $ 33,475.00
Additions Subtotal: $ 49,225.00
TOTAL FOR CHANGE ORDER NO.2 $ 33,142.20
PREVIOUS CHANGE ORDER(S):
CHANGE ORDER NO. 1 $ 34,162.00
TOTAL OF PREVIOUS CHANGE ORDERS: Add: $ 34,162.00
TOTAL REVISED CONTRACT AMOUNT: $ 3,572,944.30
The original amount of the contract with Ryan Incorporated Central is$3,505,640.10. Change Order No.2 will increase the
original contract amount by a total of$33,142.20;that sum representing less than one percent(0.94%)of the original contract
amount.The new contract amount,inclusive of all change orders is$3,572,944.30.
OTHER CONTRACT PROVISIONS: All other contract provisions remain the same.
CHANGE ORDER No.2
Agreed to this 18th day of September ,2008.
Recommended by:
PARKS AND RECREATION DEPARTMENT
By:Mike Lehman
Title:Golf Services Manager
Date: l 0•to OZ
Signature: _).........--------------
Accepted by: 7-1(7 P Y /
RYAN INCORPORATED CENTRAL
Party of the Second Part(Contractor) q/108
By:Adam Ryan
Title:President
Date: September 18,2008
Signature: - . )\____l
Approved by:
CITY OF ELGIN
Party of the First Part(Owner)
By: Olufemi Folarin
Title:City Manager
Date: 0 .. '■ ' ' .?O d
Signature: t___ _
`r►
F:\Legal Dept\forms\Change 0 ,er orm.doc
E_
F J
,.,,,,4,-,.. „,,,,i-,,,,,
..4v.
� 4
October 16, 2008 ' +"
i
TO: Mayor and Members of the City Council --=
FROM: Olufemi Folarin, City Manager
Randy Reopelle, Parks and Recreation Director
SUBJECT: Change Order No. 2 with Ryan Central, Inc. for the Construction of the Highlands
Phase II Golf Course
PURPOSE
The purpose of this memorandum is to provide the Mayor and members of the City Council with
information to consider authorization of Change Order No. 2 with Ryan Central, Inc. for the
construction of the Highlands Phase II golf course.
RECOMMENDATION
It is recommended that the City Council approve the execution of Change Order No. 2 with Ryan
Central, Inc. for the Highlands Phase II Golf Course in the amount of$33,142.
BACKGROUND
On April 18, 2008, the City Council awarded a bid to Ryan Central, Inc. in the amount of
$3,505,640.10 to construct the Highlands of Elgin Phase II golf holes around the quarry to the
east of the new holes, which were opened in 2002. Change Order No. 1 provided for a number
of different changes related to drainage and the irrigation system and was approved on August
13, 2008 in the amount of$34,162.
Change Order No. 2 entails adjustments to the actual quantities of erosion control materials and
drainage materials used, as well as minor grading and grassing adjustments. These items
essentially balanced themselves, with the increased cost of Change Order No. 2 relating entirely
to installing the foundation and underground structures to support the construction of the comfort
station to be bid at a later date.
Change Order No. 2 will increase the contract by $33,142. The new contract amount, inclusive
of Change Order No. 1 and Change Order No. 2, is $3,572,944.10. A copy of Change Order No.
2 is attached and outlined by our contracted project manager, Randy Trull. Mr. Trull's outline is
identified as Attachment A.
Change Order No. 2 for the Construction of the Highlands Phase II Golf Course
October 16, 2008
Page 2
COMMUNITY GROUPS/INTERESTED PERSONS CONTACTED
Highlands of Elgin Golf Course Leadership Team
FINANCIAL IMPACT
The cost of Change Order No. 2 with Ryan Central, Inc. is $33,142. The total budget for this
project is $6.315 million and $5,896,830 has been spent/encumbered to date. There are
sufficient funds budgeted ($5.0 million) and available ($161,353) in the 2008 G.O. Bond Fund,
account number 368-0000-795.92-32, "Buildings and Structures," project number 509637,
Highlands Phase 2 Construction, to fund Change Order No. 2.
LEGAL IMPACT
None
ALTERNATIVES
1. The City Council may choose to approve Change Order No. 2 with Ryan Central, Inc. in
the amount of$33,142, as recommended.
2. The City Council may choose not to approve Change Order No. 2 with Ryan Central, Inc.
in the amount of$33,142, as recommended.
Respectfully submitted for Council consideration.
ml
Attachments