HomeMy WebLinkAbout07-99 Resolution No. 07-99
RESOLUTION
APPROVING CHANGE ORDER NO. 1 IN THE CONTRACT WITH
NORTHWEST CONTRACTORS, INC.
FOR THE HIGHLANDS OF ELGIN CLUBHOUSE
WHEREAS, the City of Elgin has heretofore entered into a contract with Northwest
Contractors of Elgin, Inc. for The Highlands of Elgin Clubhouse; and
WHEREAS,it is necessary and desirable to modify the terms of the contract as is described
in Change Order No. 1, attached hereto.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF
ELGIN,ILLINOIS,that Olufemi Folarin,City Manager,be and is hereby authorized and directed to
execute Change Order No. 1,a copy of which is attached hereto and made a part hereof by reference.
s/Ed Schock
Ed Schock, Mayor
Presented: April 25, 2007
Adopted: April 25, 2007
Omnibus Vote: Yeas: 7 Nays: 0
Attest:
s/Dolonna Mecum
Dolonna Mecum, City Clerk
'CHANGE
' ORDER OWNER [ ]
ARCHITECT [ ]
CONTRACTOR [ ]
PROJECT: The Highlands of Elgin Golf CHANGE ORDER NUMBER: 001
Clubhouse Project
875 Sports Way
Elgin, Illinois 60120
DATE: March 20,2007
CONTRACTOR: ARCHITECT'S PROJECT NO 06720
Northwest Contractors Inc.
200 Industrial Drive
Hamphire,Illinois 60140 CONTRACT DATE: September 27, 2006
The Contract is changed as follows:
Additional Work for the Highlands of Elgin Golf Clubhouse Project. Please refer to the Larson Kramer
letter dated March 20, 2007 for more information regarding the NCI proposals below
NCI #001a -Foundation Adds and Deducts $ 5,724.13
NCI #001b -Civil Drawings Adds and Deducts $ 17,882.47
NCI #001c -Masonry Allowance/Mason Labor $ 20,384.96
NCI #001d - Structural Steel Adds and Deducts $ 3,955.35
NCI #001e -Plumbing Venting Adds and Deducts $ 8,132.25
Total Change Order#001 $ 56,079.16
Referenced as Henry Bro. CO#22-3/19/07.
Not valid until signed by the Owner,Architect and Contractor.
The original Contract Price was $ 4,430,000.00
Net Change by previously authorized Change Orders was. $ 0.00
The Contract Price prior to this Change Order was. $ 4,430,000.00
The Contract Price will be increased by this Change Order in the amount of $ 56,079.16
The new Contract Price including this Change Order will be. $ 4,486,079.16
Change in the Contract Time will be increased by 0 days
ARCHITECT CONTRACTOR OWNER
Larson . er&A.soc. Northwest Contractors Inc. City of Elgin
701 Yor •oad 200 Industrial Drive 150 Dexter Court
Hin IL .15 H.u•shire 11'x,;is 60140 1 Elfin`Illinois 60120
BY �� (" BY ___ _
BY �- v�`.
C �r�6E "'
S7/14/6 /5 U DA :Am' MINK°.*0
DA ' DATE
• Northwest Contractors, Inc.
200 Industrial Drive
Hampshire, IL 60140
(847)683.0550 Fax (847)683.0555
February 9, 2007
Larsen-Kramer&Associates
701 N. York Road
Hinsdale, IL 60521
Attn: Steve Kramer
RE: The Highlands of Elgin
Change Order Request Number 001a — Brick Ledge/Foundation Change
Gentlemen:
Northwest Contractors, Inc. requests a change order to perform the work associated with the
changes on drawing S1.1 (12.28.06) for supplying labor, material and equipment necessary to
increase the height the "end" walls to full height, while incorporating a brick ledge to
accommodate the masonry veneer and sloping terrain. There is an associated credit with this
work for not installing the CMU back up. Additionally there's a credit for not installing a 31'
section of wall at the front of the building, but there's added were footings and walls for exterior
storage in the back of the building. The following is a breakdown for this work;
1) Brick Ledge Adds:
NCI Labor:
(17) Superintendent Hours @ $81.08 per/hr$ 1,378.36
(96) Carpenter Hours @ $78.06 per/hr 7,493.76
(88) Laborer Hours @ $67.37 per/hr 5,923.28
Total Labor $ 14.795.40 $14,795.40
NCI Material:
Home Depot receipt dated 11.2.06 $ 348.54
Bracing Systems Invoice dated 11.20.06 84.00
Total Material $ 432.54 $ 432.54
Sub-Total Labor & Material $15,227.94
15% Mark up $ 2,284.19
Total Labor & Material $17,512.13
2) Storage Room Foundation Adds:
6cy of concrete (footings & walls) @ $ 3.300.00 $ 3,300.00
$550.00 per/cy (unit cost)
3) Brick Ledge 8" CMU deduct;
572sf of 8" CMU @ $14.00 per/sf (unit cost) ($8,008.00) ($8,008.00)
H:\CLIENTS\ELGINCTY\Highlands Golf Course...Club House\Change Order Request\Brick ledge 1.22.07 revised 3.15.07.doc
Page 2,
4) Foundation wall omitted:
17.70cy of concrete (wall) @ $400.00 per/cy ($ 7.080.00) ($ 7,080.00)
(This section was already excavated
during the building excavation)
Total cost for Change Order Request No. la Add $5,724.13
Please issue a change order so we can invoice.
Sincerely;
NORTH ST C TRACTORS, INC.
/ 2,_
tuart C. Beam
Project Manager
H:\CLIENTS\ELGINCTY\Highlands Golf Course...Club House\Change Order Request\Brick ledge 1.22.07 revised 3.15.07.doc
TIME & MATERIAL f.lG'rtE.l 12.7.06 JOB#: obta
. ❑PARTIAL DATE:
®FINAL
Northwest Contractors, Inc. CONTRACT/P.O.:
200 Industrial Drive,Hampshire,IL 60140
Ph: 847.683.0550 F: 847.683.0555/0777
OWNER/CLIENT: Ci Of EI 4_ n JOB LOCATION: 875 Sports Wa , Elgin,IL 60123
PROJECT NAME: The Highlands of EI in
DESCRIPTION OF WORK THIS DATE: Increasing Wall Height,Framing Wall Depression to Accommodate Brick Ledge
LABOR
STRAIGHT STRAIGHT TIME TIME DOUBLE DOUBLE COMMENTS TOTAL
'TIME &1/2 &1/2 TIME TIME COST
EMPLOYEE EQUIP TIME ESTIMATE
NAME I, EMPLOYEE or Description Furnished CLASSIFICATION HOURS RATE HOURS RATE HOURS RATE
WORKED WORKED
Material, Equipment or Service Furnished WORKED � _IIINIIIINII � __ 5624.48
12.6.06 8 78.06
Carpenter 5624.48
Carpenter 8 '78.06 __ _ 5524.48
Sam Solo ki , 8 67.31
Laborer � _
Sam Solomon
1111111111111111111111111111111.1111111 IIIIIIIIIINMNIIIIIIII 1111111111111111111111111111111111
11111111111111111111111111111111111111111 1111111111111111111.1......1...0
1111111111111111111.1111111111111111111 11111111111111111111111
' 1111111111111111111111111111111111111111 1111111111111111111111111111111
11111111111111111111111111111.1111111111111 IIIIMIIIIIIIIIINIIIIIIIIIIIIIIMINIII
IMIIIIIIMI111.1111111111111 MI MI 11111111111111111111111111111111111111
1111.111111 IIIIINIIIIIIII"Mll111
. 111111.11.111111111111111 MI' lNINIIIIIIIIIIIIIIIIIIIII
APPROVED BY: EST COST THIS TICKET
$1,7d7.44
SUBMITTED BY: tuart C. Beam, Project EST COST PREY.TICKETS $13.483.75
ct Manager
EST COST TO DATE 515.271'19
OWNER'S REPRESENTATIVE •-THWEST CONT••CT REPRESENTATIVE
H:\CLIENTS\ELGINCTYWighlands Golf Course...Club House\TSM issues\(Brickledge 11.20 lhru 11.28.06.xlS)12.6.06'
Rev 2 0.
TIME & MATERIAL Tit;K{✓'f
®PARTIAL DATE: 12.7.06 JOB#: 0629
Northwest Contractors, Inc. Ell FINAL
CONTRACT/P.O.:
200 Industrial Drive,Hampshire, 60140
Ph: 847.683.0550 F: 847.683.0555/0777
OWNER/CLIENT: Ci Of EI in 875 Sports Way,Elgin, IL 60123
JOB LOCATION:
PROJECT NAME: The Hi hlands of Elgin
DESCRIPTION OF WORK THIS DATE: Increasing Wall Height, Framing Wall Depression to Accommodate Brick Ledge
• LABOR
STRAIGHT STRAIGHT TIME TIME DOUBLE DOUBLE COMMENTS TOTAL
TIME &1/2 &1/2 TIME TIME COST
EMPLOYEE EQUIP TIME ESTIMATE OT
NAME I, EMPLOYEE or Description e CLASSIFICATION HOURS RATE HOURS RATE HOURS RATE
Material,Equipment or Service Furnished WORKED WORKED
WORKED
$324.32
11.28.06: Superintendent 4 81.08 IIIIIIIINIIIIIIIIIIIIIII
Jeff Berg � 8 78.06 $624.48
Carpenter 5624.48
67
• Carpenter 8 7$.06 $538.48
Jim Kosinski Laborer 8 .31
$538.48
Sam Solomon Laborer 8 6 .31
$269.24
Salvador Castro 4 677.31 _
Laborer -_ _ _leiffillil ,' MI Home De•ot(20)s e dated 11 "OS ____ _
40)2x6x10',(20)sheets of 7/16"OSB
____IIIIIIIIIIIIIIIIIIIIIIIIII
Bracing S stems Receipt dated 11.20.06 $84.00 IIIIIIIIIIIIIIIIIIIIII
Dovetaol Anchor Slot(3001f)
Subtotal IIIIIIIIIIIIIIIIIIIIIII
10% 475.79 IIIIINNIIIIIIIINIIII Innalli
Total _
EST COST THIS TICKET $3,395.27
SUBMITTED BY: Stuart C. Beam, Project Manager EST COST PREY.TICKETS $10,088.48
APPROVED BY:
EST COST TO DATE $13,483.75
O - 'RESENTATIVE
OWNER'S REPRESENTATIVE
N.Te1i'_�R" T CONTRA'
H:\CLIENTS\ELGINCTY\Highlands Golf Course...Club House\T&M issues\IBrickledge 11.20 thru 11.28.06.xIs]11.28.06
Rev 1:C:
c. DEPOT 1934
60123 RANDA(847 )62-9441
1934 00002 57238 i 1 11/20/06
61 SB452E 09:53 AM
SALE 1
, . ^
lF.: 4;‘, ,�, o6 z9
\ c4e444:r1 0' Z.C>In/
:;tqb_ g 4f:-.Xi"r71-.
j r 'a1 4b, �'r.4.�.
039404117632 18GCRWST11/2 <A�I L '4•-
2 @ 14.99
090214000118 2X6-10 HT WW <A> 170.00
40 @ 4.25
776391200007 7/16 OSB <A> 125.00
20 @ 6.25 SUBTOTAL 324.98
SALES TAX ' ! 23.56
TOTAL 11 $348.54
XXXXXXXXXXXX1783 HONE DEPOT' ' 348.54
RUTH CODE 020022/7021896
TA
I
1934 02 57238 11/206
RETURN POLICY DEFINITIONS
POLICY ID DAYS POLICY EXPIRES ON
A 1 90 02/18/2007
THE HOME DEPOT RESERVES ITIHE RIGHT TO
LIMIT / DENY RETURNS. PUEASE SEE THE
RETURN POLICY SIGNS INII19TORES FOR
D .CARPET CLEANING BY CHEI�1}DRY IS NOW
AVAILABLE THROUGH THE HOME DEPOT.
CALL 1000: 1-8U0-HOMEDEPUT
****W*******************.4W *W***W****iI.
I
• ENTER FOR
A HIC HANCE
TO WIN A $ , 000
HOME DEPOTi GIFT
CARD
Your Opinion Counts: Weruld like to
hear about your shopPin experience.
Gift
Enter tcn ,a0briefesuurvey about
Card d by completing a
your store visit at:
il
. - Ip111111 1/11111111 11111111 Page 1 of 1
�
3racing Systems-North Contract#: 74319 Status: Closed•
'0 Box 517 630-665.2732 phone Date Out: Mon 1112012006 11:17am
3loomingdale,IL 60108 630-665-0838 fax
,v Operator: Jeff Lange
•ww.bracingsystems.com
— Customer# 684 Terms: On Account
NORTHWEST CONTRACTORS INC. 847 683-0550 FAX 847 ob Name: THE HIGHLANDS CLUBHOUSE
200 INDUSTRIAL DRIVE. PO#: JEFF —
Hampshire,IL 60140
Price Each Price
Items Sold ' 0 22 4Price
1tv Key WB 49.90
2,000 WB-1 WEDGE BOLTS•STEELIPLY 49.90
WALER2X4 2 40 249.00
1 WALER2X4-1 2"x 4"WALER TIE-box ZTIEHOLD 84.00
100 ZTIEHOLD-1 Z-TIE HOLDER 2.48
DOVETAIL ANCHOR SLOT-(10') 1 DOVETAIL
39Q. DOyETAiL=1,•'`;
30 PCS.x 10-0 29.50 118.00
Yq FT12.1
12"FLAT TIES box F712
INVOICE
_ .
C:': •• .,
. =r r n rF 06 z,9 j•-.i;
Yeti 3
��, • ...
.,cam , z .
f•
.. ,,t. Parr 1
•
-=i=ts
Waiver: $Rental: $0.00
RENTAL CONTRACT 0.00
This is a contract. The back of this contract contains important terms and conditrOnS including lessor's disclaimer Damage WSales: $940.90
from all liability for injury or damage and details of customers obligations. These terms and conditions are a part of
this contract agrees THEM! Delivery Charge: $0.00
The customer agrees that all manufacturers'operating instructions are included with this equipment and agrees to $0.00
have only qualified personnel erect and operate this equipment. Ivor Charges: $
Fuel and routine maintenance are the responsibility of the customer,including daily SubTotal: $940.90
safety inspections.If there are any safety concerns,customer agrees to discontinue use of equipment and
immediately notify lessor.All tire damage is the responsibility of the customer.
Customer agrees to furnish insurance for all rented equipment. •
Rental is based on a IG0 hr/month,40 hr/week,8hr/day.Any overtime shall be charged pro rata.
If other than lessee.signer represents he is agent of and authorized to sign for lessee.I certify that I have read and
• $63.51
agree to all terms of this contract 1. TOTAL: $1,004.41
•
PAID: woo SIGNATURE: AMOUNT DUE: $1,004.41
NORTHWEST CONTRACTORS INC. . ,, •
L I I iv'il= c.:c MA I E K I H L I I1,r\L I
DATE: 12.7.06
.. , _ lx1 PARTIAL ,
Northwest Contractors, Inc. E FINAL
200 Industrial Drive,Hampshire,IL 60140 CONTRACT/P.O.:
Ph: 847.683.0550 F: 847.683.0555/0777
OWNER/CLIENT: City Of Elgin
PROJECT NAME: The Highlands of Elgin JOB LOCATION:
875 Sports Way, Elgin, IL 60123
DESCRIPTION OF WORK THIS DATE: Increasing Wall Height, Framing Wall Depression,to Accommodate Brick Ledge
LABOR
STRAIGHT STRAIGHT TIME TIME DOUBLE DOUBLE COMMENTS TOTAL
NAME OF EMPLOYEE or Description of EMPLOYEE EQUIP TIME TIME &1/2 & 1/2 TIME TIME COST
Material, Equipment or Service Furnished CLASSIFICATION HOURS RATE HOURS RATE HOURS RATE ESTIMATE
WORKED WORKED
11.22.06: S624.48
Mike VanBuren Carpenter 8 78.06
5624.48
Jim Kosinski ' ' Carpenter 8 78.06 •• 5538.48
Salvador Castro Laborer 8 67. E
11.27.06: 5324.32
Jeff Berg Superintendent 4 81.08
5624.48
Mike VanBuren Carpenter 8 78.06
5624.48
Jim Kosinski Carpenter 8 78.06
S538.48
Sam Solomon Laborer 8 67.31
5538.48
Salvador Castro Laborer 8 67!31
5269.24
Mike Clark Laborer 4 67.131•
II
EST COST THIS TICKET S4,706.92
APPROVED BY: SUBMITTED BY: Stuart C. Beam, Project Manager
EST COST PREY. TICKETS $5,381.56
OWNER'S REPRESENTATIVE NO WEST C NTRA T ' REPRESENTATIVE
EST COST TO DATE $10,088.48
H:\CLIENTS\ELGINCTY\Hlghlands Golf Course...Club House\T&M issues\[Brickledge 11.20 thru 11.28.06.xIs111.224 11.27.06
Rev 7202
TIME & MATERIAL TICKET
®PARTIAL DATE: 12 7.06
Northwest Contractors, Inc. FINAL
200 Industrial Drive,Hampshire,IL 60140 CONTRACT/P.O.:
Ph: 847.683.0550 F: 847.683.0555/0777 •
OWNER/CLIENT: City Of Elgin
,JOB LOCATION: 875 Sports Way, Elgin, IL 60123
PROJECT NAME: The Highlands of Elgin
DESCRIPTION OF WORK THIS DATE: Increasing Wall Height, Framing Wall Depression to Accommodate Brick Ledge
•
LABOR
COMMENTS TOTAL
STRAIGHT STRAIGHT TIME TIME DOUBLE DOUBLE nCOST
TIME &1/2 &112 TIME ESOT ATE
NAME OF EMPLOYEE or Description ce Furnished e EMPLOYEE EQUIP HOURS RATE HOURS RATE HOURS RATE _
WORKED WORKED_
Material, Equipment or Service Furnished CLASSIFICATION WORKED ___
-__ 5729.72
11.20.06: 9 81.08 ____ 5624.48
Jeff Berg Superintendent ____am
g 78.06 ____ 5624.48
Carpenter
g .78.06 1111111111111111111111111 $538.48
Carpenter MI
Jim Kosinski 8 67.31 __ 5538.48
Laborer __ _
Sam Solomou 8 67.31 __
Laborer __Salv ador Castro __ 5624.48
ij2iOillillIllrlrIIIIIIIIIII'
6: 8 78.06 __ 5624.48
Carpenter 1111111111111111111111111
g 78.06 _
Carpenter 8 67.31 ___
Sam Kosinski __ 5538.48
Laborer __ _
Sam Solomou 8 67.31 __
Laborer rim_ __
Salvador Castro _ MIIIIIIIIIIIIII
__
IIIIIIIIIIIIIIIIIIIIIINIIIIIMIIIIIIIIIIIIIII- ,3
APPROVED BY: SUBMITTED :Y: •tuart Beam, Project Manager EST COST THIS TICKET 581.56
EST COST PREV. TICKETS
g C Alb_
EST COST TO DATE
55,381.56
•THWEST ONT.' • ' •EPRESENTATIVE
OWNER'S REPRESENTATIVE ONT.'/f°iL
H:\CLIENTS\ELGINCTY\Highlands Golf Course...Club House\T&M issues\[Brickledge 11.20 thru 11.28.06.xls111.20&11.21.06
Re•.. 12 02
Northwest Contractors, Inc.
200 Industrial Drive
Hampshire, IL 60140
(847)683.0550 Fax (847)683.0555
February 9th, 2007
Larsen-Kramer &Associates
701 N. York Road
Hinsdale, IL 60521
Attn: Steve Kramer
RE: The Highlands of Elgin
Change Order Request Number 001 b —Civil Drawing Changes
Gentlemen:
Northwest Contractors, Inc. requests a change order to perform the work associated with the
changes on the civil drawings (revisions 3 thru 6) for supplying labor, material and equipment
necessary to complete the additional sanitary and water main work, per Dominic Fiordirosa
Construction Co., Inc. detailed proposal attached.
NCI Subcontractors:
Dominic Fiordirosa Construction Co., Inc. $17,293.85
Proposal dated 1.26.07
Sub-total $ 17,293.85
NCI 5%* $ 588.62
Total Subcontract $ 17.882.47
Total Cost for Item#001b $ 17,882.47
*The 5% mark up is on $11,772.35, not on any unit price items.
Please issue a change order so we can proceed with this work.
Thank you.
Sincerely;
NORTHW T NTRACTORS, INC.
tuart C. Beam
Project Manager
H:\CLIENTS\ELGINCTY\Highlands Golf Course...Club House\Change Order Request\Civil Changes 2.9.07 revised 3.20.07.doc
JANUARY 26,2007
PROPOSAL FOR
HIGHLAND GOLF COURSE NEW CLUB HOUSE
ELGIN,ILLINOIS
PAGE 1
UM ITEM UNT PRCE EXTENSION
SANITARY SEWER ADDITIONS
54,00 LF PVC 6"SDR-26(3034) $48.85 $2,637.90
TOTAL SANI SEWER $2,637.90
WATER MAIN ADDITIONS
12.00 LF WATER MAIN 6"DIP CL.52 $53.30 $639.60
185,00 LF WATER MAIN 4"DIP CL.52 $60.30 $11,155.50 tit
151.00 LF TRENCH BACKFILL CA-6 $39.80 $6,009.80
1.00 EA FIRE HYDRANT REM/REPL $1,703.00 $1,703.00 (C�
2.00 EA VALVE 4"IN VAULT 48" $2,101.00 $4,202.00 �� n''��f
2.00 EA - -CUT IN CONNECTION -$3,162.55 $6,325.10 `�
1.00 LS TEST AND CHLORINATE $5,264.50 $5,264.50 l9
IN it eV V
SUB TOTAL WATER MAIN ADDITIONS $35,299.50 1G� v y
WATER MAIN DELETIONS G�LT
($10,500.10) /1 GL
197.00 LF WATER MAIN 6"DIP CL.52 ($53.30) ($1010) A 'f ti
104.00 LF TRENCH BACKFILL CA-6 ($39.80) ($4,139.20) 'V \V" V.
1.00 EA FIRE HYDRANT REM/REPL ($2,141.00) ($2,141.00) 7 )1G
1.00 LS TEST AND CHLORINATE ($3,581.25) ($3,581.25)__- a
SUB TOTAL WATER MAIN ADDITIONS ($20,361.55)
TOTAL CHANGE ORDER ADDITION $17,575.85
NOTES
WE DO NOT INCLUDE THE FOLLOWING ITEMS: 1 ! 7,Z93,sc
#1 LAYOUT AND/OR ENGINEERING
#2 RESTORATION OF ANY KIND
#3 PERMITS BONDS OR FEES
#4 SALES AND USE TAXES
#5 TIGHT SHEETING NOR EXCESSIVE DEWATERING
#6 SAWCUTTING PAVEMENTS
#7 TRAFFIC CONTROL AND PROTECTION
WE DO INCLUDE THE FOLLOWING ITEMS:
#1 CONNECTIONS TO EXISTING PIPE AND STRUCTURES
#2 TRENCH FILL AS SHOWN
#3 ONE MOBILIZATIONS FOR DFCC,INC WORK
#4 PROPOSAL GOOD FOR 30 DAYS FROM PROP, DATE
#5 SPOIL REMOVAL FROM SITE(APPROX.365 C.Y.)
Northwest Contractors, Inc.
200 Industrial Drive
Hampshire, IL 60140
(847)683.0550 Fax (847)683.0555
February 15, 2007
Larsen-Kramer &Associates
701 N. York Road
Hinsdale, IL 60521
Attn: Steve Kramer
RE: The Highlands of Elgin
Change Order Request Number 001 c— Masonry Adds
Gentlemen:
Northwest Contractors, Inc. requests a change order to perform the work associated with the
changes on the Structural Steel Drawings (dated 10.19.06, 10.31.06 & 1.5.07)for supplying
labor, material and equipment necessary to; set bearing plates for the Veranda steel, addition
material cost to supply the Mission Pink Velour Norman size brick over the allowance specified.
The following is a breakdown for this work;
Masonry Adds:
Set (21) Bearing Plates 1,328.00
Addition Brick cost
($.265 x 65,000 = $17,225.00 18,086.25
plus Porter's mark-up $2,584.00)
Total Subcontractor Cost $ 19,414.25
NCI 5% $ 970.71
Total Cost $ 20.384.96
Total Cost for Masonry Changes $ 20,384.96
Please issue a change order so we can proceed with this work.
Sincerely;
NO HW T C NTRACTORS, INC.
Stuart C. Beam
Project Manager
H:\CLIENTS\ELGINCTY\Highlands Golf Course...Club House\Change Order Request\COR 003r Masonry Changes 2.15.07 revised
3.16.07.doc
cut)."
47 WED 15:13 FAX 630 377 7781
r MI
G. PORTER & CO.
MASON CONTRACTORS
1041 PORTER COURT ST. CHARLES 1 ILLINOIS 60174
(630)
FAX(6730) 377-7781
January 31, 2007
Northwest Contractors
Attn: Stuart Beam The Highlands of Elgin Clubhouse
Elgin, ILL.
Listed below is the cost for the brick over and above the $500.00 per
thousand allowance specified.
Mission Pink Velour Norman size brick from Sioux City Brick Co.
65,000 Mission Pink Velour brick @ $765/M $49,725.00
65, 400 brick @ the 5500.00/allowance
$32, 500.00
$17,225.00
15%ra cost for brick: �`v $ -
15 {0 P 1 .$34,�BQ9--66
Total Extra:
Sincerely
.,m`1•--�--
ike DeBenedictis
Northwest Contractors, Inc.
200 Industrial Drive
Hampshire, IL 60140
(847)683.0550 Fax(847)683.0555
February 19, 2007
Larsen-Kramer&Associates
701 N. York Road
Hinsdale, IL 60521
Attn: Steve Kramer
RE: The Highlands of Elgin
Change Order Request Number 001d —Structural Steel Changes
Gentlemen:
Northwest Contractors, Inc. requests a change order to perform the work associated with the
changes on the Structural Steel Drawings (dated 10.19.06, 10.31.06 & 1.5.07)for supplying
labor, material and equipment necessary to; supply the lower level lintels not previously shown
and change (6) steel beams sizes. The following is a breakdown for this work;
Structural Steel Adds:
Mona Fab proposal dated 2.17.07
Supply 1.36-tons of Lintels $ 2,582.00
Supply the increased steel beams 1,185.00
sizes (260Ibs) and additional
detailing/drafting time)
Total Subcontractor Cost $ 3,767.00
NCI 5% $ 188.35
Total Cost $ 3.955.35
Total Cost for Structural Steel Changes $3,955.35
Please issue a change order so we can proceed with this work.
Sincerely;
NORT�IWES� ITRAC7S, INC.
tuart C. Beam
Project Manager
H:\CLIENTS\ELGINCTY\Highlands Golf Course...Club House\Change Order Request\COR 004d Steel Changes 2.19.07 revised
3.15.07.doc
MAR-`i5 2007 09:41A FROM:MONA FABRICATION 8477426662 TO:18476830555 P.1
Change Order 11004 Structural Steel Changes 511,018.00
Background: Per RF1001,Northwest Contractors requested an RFI regarding if lintels were required for
windows and doors. Steve from LK responded that lintels were required. Structural drawings did not show
lower level lintels_ Approved shop drawings dated December 20th changed sizes of interior steel beams.
Change Order#004 Additional labor and materials to provide changes for January 5,2007
Evaluation $3,955
Original steel shop drawings from Mona Fabricators were received on 11/30/06 and subsequently were
revised by Mona on 12/13/06. We received reviewed shops from our Engineer on December 20 Revision
3,which revised some of the connections which Mona,had drawn incorrectly. Beam sizes increased in
order to provide additional support to handle increased snowdrifts along row E. Hinsdale Engineering
revised the drawings again for January 5,2007 Rev 4. which reduced additional beam sizes to offset beam
size increases along Row 13.
Per Structural Engineer's evaluation
Lintels
2,720 extra lbs of lintels @ S.50 lbs $ 1,360
Shop fabrication $ 480
— Studs $ 150
- - ----- --
Shipping $ 255
Subtotal $2,245
Markup 15% $ 336
Total $2,582
Steel Beams
Steel beams were increased by net of 2,620 lbs
Steel beams were decreased by a net of 2,360 lbs
total add 260 lbs
Detailing 10 hours @$60 $ 600
Additional Steel 260 lbs @$.50 5 130
Fabricating and Painting $ 50
Shipping $ 250
Math-up 15% $ 155
Total $ 1,185
Total Change Order plus 5% 53,955
-
3 IS (19
w
ev.,„„F2
! Northwest Contractors, Inc.
200 Industrial Drive
Hampshire, IL 60140
(847)683.0550 Fax(847)683.0555
February 16, 2007
Larsen-Kramer&Associates
701 N. York Road
Hinsdale, IL 60521
Attn: Steve Kramer
RE: The Highlands of Elgin
Change Order Request Number 001e—Building Plumbing Adds
Gentlemen:
Northwest Contractors, Inc. requests a change order to perform the work associated with adding
vent piping for the cart storage area floor drains. Drawing P2.0 shows the riser diagrams for the
various plumbing systems, including the vent piping. The cart storage floor drains and
associated piping for this system as drawn does not include vent piping. We inquired via an RFI
and were directed to install vents on this line. Below is a breakdown for this work along with an
attached proposal from MG Mechanical Plumbing Services, Inc.
Also, in a unrelated matter, please note that the Grease Trap GT-1 (Rockford RTO-16)will have
to be increased from a 16 gallon capacity to hold 100% of the triple-basin sink that it serves; this
was changed from FRWRD's review and recommendation for this project The size has yet to
be determined but if it were to be a 110 gallon capacity unit the cost associated with this would
be $2,976.00.The following is a breakdown for this work;
Plumbing Adds:
M G Mechanical Plumbing Services, Inc.
Proposal dated 3.16.07
Vent Piping For Cart Storage Area $ 7,745.00
NCI 5% $ 387.25
Total Cost $ 8.132.25
Total Cost For This Plumbing Change $ 8,132.25
Please issue a change order so we can proceed with this work.
Please note this cost is for Orion brownline acid pipe, if blueline is required
please add $4,420.08
Sincerely;
NORTHWEST CONTRACTORS, INC.
Stuart C. Beam \.
Project Manager
H:\CLIENTS\ELGINCTY\Highlands Golf Course...Club House\Change Order Request\COR 005r Building Plumbing Acid vent piping
2.19.07e revised 3.16.07.doc
Mar . 16 . 2007 4:44PM M G MECHANICAL No .7967 P. 1/2
M G Mechanical Plumbing Services, Inc.CHANGE ORDER REQUEST
1513 Lamb Road
Woodstock IL 60098 ORDER 4
ORDER DATE 03/16/2007
ORDERED DY 1 Frederick Learman, Jr.
CUSTOMER ORDER 0629
TO Northwest Contractors PROJECT 200
200 Industrial Dr. Highlands of Elgin
Hampshire IL 60140 875 Sports Way
r Elgin IL 60123
Fax#:847 683-0555
The contractor agrees to perform and the owner agrees to PLANS ATTACHED
pay for the following changes to this contract SPECIFICATIONS ATTACHED
Description of Work Amount
THE FOLLOWING IS A BREAKDOWN OF OUR PROPOSAL TO PROVIDE VENT PIPING FOR THE DRAINS IN THE
CART STORAGE AREA AS DISCUSSED. (FOR MATERIAL ONLY)
MATERIAL
300 LF of 2"Orion Brownline Acid @ $4.80/LF 1,440.00
(60)2"Orion Blueline Acid Fittings @$50.00/ea 3,000.00
(180)2"Orion Blueline Acid Couplings @ $14.00/e 2,520 00
- OOLF of 2"-P-VC_P_i - ------
-156;OU
- pe{��.52/LF- - --- -- -- - -
(-60)2"PVC Tees ig$1 14/LF -68.40
Overhead and Profit 1,010 00
Notes
MANUFACTURE DOES NOT RECOMMEND BROWNLINE ACID PIPING FOR ABOVE GROUND APPLICATIONS. ANY
CHANGES DUE TO CODE RESTRICTIONS WILL HAVE TO BE COMPLETED ON A TIME AND MATERIAL BASIS.
Negative changes will lower the overall contract
price requiring no additional payment by owner. Requested Amount of Change 7, 745. 60
Approved Date Date
Contractor Owner
"'°"' cMa r • 16 . 20075k 4;44PM15334M G MECHANICAL 3352910.1 03/16/200716:i3:4CN0 .7967,f2 P • 2/2
Q U O T A T I O N
From COLUMBIA PIPE & SUPPLY CO. Quote 352832
Lag #
Page 1
Ent By EB
Salesrep: ED BROOKING Sls #1 146
Phone (847)608-4131 -
To MG MECHANICAL PLBG SERVICE + 815-334-9450 Entered 3/16/07
1513 LAMB RD Printed 0/00/00
WOODSTOCK IL 60098 9677
Attn: CANDI
Ship to Via OUR TRUCK
Terms
Job Info CANDI CANDI
PLEASE NOTE:
Columbia Pipe & Supply Co. proposes to furnish the following described products:
Description Quantity U/M Net Each Ext Amt
ORDER CONTACT: CANDI
�PS Item# /050-3360729
ORION 2X10 ' BROWNLINE PIPE 300 FT 4.80 1440.00
TO BE USED-UNDERGROUND ONLY -
MATERIAL TOTAL - 1,440.00
Inbnd Ert and Hnding To Be Applied
o warranties other than those offered by the manufacturers are included.
'UE TO THE CURRENT MARKET CONDITIONS, PRICE AND AVAILABILITY ARE SUBJECT TO THE
ERMS AND CONDITIONS OF THE MANUFACTURER(S) AT THE TIME OF SHIPMENT.
hank you.
Mar . l6. 2007, 2 : 14PM M G MECHANICAL No .7935 P . 2/2
From C ..... .. ..rl. ,...;.153346 .,., rnbg+*,334970.0.1 03/16/2007 13:37:49 age 2 of 2
Q U O T A T I O N/41q
From COLUMBIA PIPE & SUPPLY CO. Quote 351895
Log ##
Page 1
Ent By EB
Salesrep: ED BROOKING _ S.Ls # 146
Phone (847)608-4131
To MG MECHANICAL PLBG SERVICE + 815-334-9450 Entered 3/14/07
1513 LAMB RD Printed 3/16/07
WOODSTOCK IL 60098 9677 Revised 3/16/07
Attn: CANDI
Ship to 1513 LAMB RD Via OUR TRUCK
Terms
WOODSTOCK IL 60098
Job Info CANDI CANDI
PLEASE NOTE:
7:olumbia Pipe & Supply Co. proposes to furnish the following described products:
Description Quantity U/M Net Each Ext Amt
ORDER CONTACT: CANDI
�PS Item# /050-3358428
ORION 2X10 ' BLUELINE PIPE 300 FT 17 .04 5112 .00
:PS Item# /050-3358429
ORION 2" MJ TEE 60 EA 50.54 3032.40
:'PS Item# /050-3358430
ORION 2" MJ COUP 180 EA 14. 04 2527.20
:PS item# 006339
2 X20 PVC-DWV SCH 40 PIPE 300 FT .52 156 .00
,PS Item# 006480
2 PVC-DWV IIHXH SAN TEE 400 60 EA 1 .14 68.40
MATERIAL TOTAL - 10,896.00
Inbnd Frt and Hndlng To Be Applied
to warranties other than those offered by the manufacturers are included.
_SUE TO THE CURRENT MARKET CONDITIONS, PRICE AND AVAILABILITY ARE SUBJECT TO THE
ERMS AND CONDITIONS OF THE MANUFACTURER(S) AT THE TIME OF SHIPMENT.
Mar . 16 . 2007 2 : 14PM M OMECHANICAL No .7935 P. 1/2
3Y7
•
M G Mechanical Plumbing Services, rnc.CHANGF, ORDER RFQTTST
1513 Lamb Road
Woodstock IL 60098 ORDER 3
ORDER DATE 03/16/2007
ORDERED 13 Y 1 Frederick Leannan, Jr.
CUSTOMER ORDER 0629
•
TO Northwest Contractors PROJECT 200
200 Industrial Dr. Highlands of Elgin
Hampshire IL 60140 875 Sports Way
S\per gam-' Elgin IL 60123
Fax#: 847 683-0555
The contractor agrees to perform and the owner agrees to PLANS ATTACHED
pay for the following changes to this contract SPECIFICATIONS ATTACHED
Description of Work Amount
THE FOLLOWING IS A BREAKDOWN OF OUR PROPOSAL TO PROVIDE VENT PIPING FOR THE DRAINS IN THE
CART STORAGE AREA AS DISCUSSED. (FOR MATERIAL ONLY)
MATERIAL
300 LF of 2"Orion Blueline Add Pipe @$17.00/LF 5,100.00
(60)2"Orion Blueline Acid Fittings @$50.00/ea 3,000.00
(180)2"Orion Blueline Acid Couplings @$14.00% 2,520.00
-300 LF of 2"PVC Pipe @$,52/LF 156.00
(-60)2" PVC Tees @$1 14/LF -68,40
Overhead and Profit 1,559.00
Notes
Negative changes will lower the overall contract
price requiring no additional payment by owner. Requested Amount of Change 11, 954 . 60
Approved Date Date
Contractor Owner
`0 OF Etc'
Agenda Item No.
¢ § City of Elgin
yii III.`
S' • u
April 6, 2007
TO: Mayor and Members of the City Council
/ i a::fti,z'�Irl,ifit'tt!�
FROM: Olufemi Folarin, City Manager (,'ti,."a ' 1' "'` 471(
Randy Reopelle, Parks and Rec eation Director
SUBJECT: Change Order No. 1 for the Construction of the Highlands of Elgin Clubhouse
PURPOSE
The purpose of this memorandum is to provide the Mayor and members of the City Council with
information to consider authorization of Change Order No. 1 with Northwest Contractors Inc. for
the construction of The Highlands of Elgin Clubhouse.
RECOMMENDATION
It is recommended that the City Council approve the execution of Change Order No. 1 with
elk' Northwest Contractors Inc. for the construction of The Highlands of Elgin Clubhouse in the
amount of$56,079.16.
BACKGROUND
On September 27, 2006, the City Council awarded a bid to Northwest Contractors, Inc. (NCI) in
the amount of $4,430,000 to construct the Highlands of Elgin Clubhouse at 875 Sports Way.
The construction of the Highlands Clubhouse began in fall of 2006. Construction is scheduled
to be completed by late summer.
Change Order No. 1 provides additional items necessary to add foundation, masonry, and
structural enhancements to the Highlands Clubhouse. Attachment A provides the details of the
five areas that comprise this change order. These changes were discussed in detail at the March
22 Golf Leadership Team meeting, at which time the Leadership Team unanimously
recommended approval of Change Order 1.
By reason of Change Order No. 1, the contract for the Highlands of Elgin Clubhouse project will
increase in the amount of $56,079.16 or approximately 1.27 percent of the original contract
amount. The new contract amount, inclusive of Change Order No. 1, is $4,486,079.16. A copy
of the Change Order,provided by project architect Larson/Kramer & Associates, is attached.
r
Change Order No. 1 for the Construction of the Highlands of Elgin Clubhouse
rApril 6,2007
Page 2
COMMUNITY GROUPS/INTERESTED PERSONS CONTACTED
Highlands of Elgin Golf Leadership Team
INANCIAL IMPACT
The cost of Change Order No. 1 with Northwest Contractors, Inc. is $56,079.16. There are
sufficient funds budgeted ($1,160,050) and available ($733,571) in the Riverboat Lease Fund,
account number 276-0000-791.92-36, "Capital Additions-Buildings and Structures," project
number 509737, "Highlands Clubhouse Design & Construction,"to fund Change Order No. 1.
LEGAL IMPACT
VIVWNone
ALTERNATIVES
1. The Council may choose to approve Change Order No. 1 in the amount of$56,079.16 as
recommended.
r2. The Council may choose not to approve Change Order No. 1 in the amount of$56,079.16
as recommended.
Respectfully submitted for Council consideration.
rr/ml
attachment(s)
r
Change Order No. 1 for the Construction of the Highlands of Elgin Clubhouse
r April 6, 2007
Page 3
ELGIN, ILLINOIS
PROJECT 509737
CHANGE ORDER No. 1
CONTRACT: Highlands Clubhouse Construction
SCOPE: Change Order No. 1 will provide additional items necessary to add foundation,
masonry, and structural enhancements to the Highlands of Elgin Clubhouse project at 875 Sports
Way.
This change order affects a contract entered into between the City of Elgin and Northwest
Contractors, Inc., Hampshire, IL, an Illinois corporation, dated September 27, 2006 for the
Highlands of Elgin Clubhouse Project.
REASONS FOR CHANGE:,This Change Order No. 1 is in the best interests of the City and is
authorized by law. The necessity for the changes was unforeseen at the time of the original
agreement, and the changes contemplated hereby are germane to the original agreement.
SUMMA,:' OF CHANGES IN CONTRACT AMOUNT: The original contract will be
amended as to scope and costs as provided by Attachment A hereto:
See Attachment A
The original contract with Northwest Contractors Inc. is $4,430,000.00. By reason of Change
Order No. 1, the contract for the Highlands of Elgin Clubhouse Project will be increased in the
amount of fifty-six thousand seventy nine and 16/100 dollars ($56,079.16) or approximately
1.27% of the original contract amount. The new contract amount, inclusive of Change Order No.
1 is four n.i'.lion four hundred eighty six thousand seventy nine and 16/100 dollars
($4,486,079.16).
•
Change Order No. 1 for the Construction of the Highlands of Elgin Clubhouse
April 6,2007
Page 4
ATTACHMENT A
March 20,2007
Highlands of Elgin Golf Clubhouse Project
875 Sports\V v Drive
Elgin,Illinois
Synopsis of Change Order#001 a-e
Change Order Breakdown
Change Order#OOIa Concrete/Masonry Adds and Deducts $ 5,724.13
Change Order#001b Civil Drawing Adds and Deducts $17,882.47
Change Orccr=(O01c Brick Allowance $20,384.96
Change Orde: ;fOOld Structural Steel Adds and Deducts $ 3,955.35
Change Order#001e Plumbing Acid Venting Adds and Deducts $ 8,132.25
Change Order#O01a-e $56,079.16
Change Order Number Title
Change Order 110Ola Concrete/Cmu Adds and Deducts
Background:
Northwest Cc ntractors bid the foundation walls on the east and west sides as full concrete steps and not as a brick
ledge wall designs as shown on the structural drawings. Sheet A-3 denotes part of the east and west sides as having
brick and concrete block. Converting the designed structural system from a brick ledge foundation system to a full
step foundation wall was not possible because footing was already poured. A full step foundation wall would have
required lure er concrete footings with more steel. Due to the height of wall above the sloping grade it was
determined 2roceed with a 4"brick ledge foundation was required. Northwest Contractors extended the concrete
foundation ;s with concrete to create the brick ledges. There was added labor and materials to form foundation
walls. The! ,,ere credits provided for labor and materials of not having to install the emu walls. Per revised
structural d :. ' ings there were added concrete foundation walls and footings to support masonry walls at an outdoor
storage root,: :'ut there was an associated credit for a foundation wall that was eliminated. The change order was
verified wit'! .;-proved Unit Cost pricing.
Total Cham'.2 ThIer#001 a $5,724.13
Change 01 11(101b Civil Drawing Adds and Deducts
Backgroun_.:
Resulting ti ., , the Permit review process the City of Elgin Engineering Department and Fox River Water
Reclamatio :strict required changes to civil utilities resulting in extra labor and materials. The Bid documents
were awarded to the contractor before the Permit process was completed so addendums were not provided to
bidders.TI.:' 'I Engineering plans showed water and sewer lines that were connected to existing stub connections
that were F' ,:ded after Phase I that were to be used for the expansion of the main clubhouse. There was a single 6"
water line t' '.,'::s hrougl,t to the building that branched off inside the building. There was also an 8"sanitary line
that was exl d to the building.
Per the Ene 1-.ring Review, The City required 2)water lines to enter into the building instead of one.One for
domestic u ' .',d the other for the Fire sprinkler system. The water lines were redirected not from the stub point but
to water m, was c'. ser to the building to the north. This reduced the cost of the 6"water line but required
additional; '. in,and r,aterial for the 2)4"lines. The sewer line was reduced from an 8"to a 6"pipe. There
rihk
Change No. 1 for the Construction of the Highlands of Elgin Clubhouse
April 6, 2.:'; 7
Page 5
were credits far the reduction from an 8"to a 6" sewer line. But in the FRWRD Review the sanitary line was
extended to an inspection manhole downstream from the outdoor grease trap,which required additional trenching
and materials. The change order was verified with the Civil Engineer with respect to approved Unit Cost pricing.
Total $17,882.47
Change Or,:,t#OOlc Masonry Allowance
Backgroun-!:
Per the Prof cc; P.°:aural an allowance was provided for a Brick Allowance set at$500 per thousand. The selected
brick-Mis a !'ink V I. ur had a price of$765 per thousand. We investigated other bricks within the same shade
from other aiicrs, which ranged between$790-$830. The cost of the brick is selection driven and the selected
brick is a N •. . an size br:ck that we feel is the perfect shade and material.
Total $20,384.96
Change Or r#t)01d Steel Adds and Deducts
Backgroua
Per the app. . structural shop drawings,the structural engineer was directed by the architect to provide additional
strength ak steel beams to provide additional support on the mechanical roof well for increased snow
loading. TI; w melt system would cost$2,000-$3,000 with approximately$1,000 per year in operating costs not
to mention c: . •:,nt maintenance.The entire system would need to be replaced every 5 years. The payback for the
cost of the s'..::m would occur in 3 years. We felt that the increase in steel for this area was a benefit to the project.
In order to r, :ce the cost impacts some other structural items were either eliminated or reduced without changing
the structu, :i • 2rity of the building structure. The change order was verified by our structural engineer with
respect to s' . I stet' arising.
Total $ 3,955.35
Change Ot ' O1 e Vent Piping Adds
During the ' cat?i plia ice review,vent piping for the cart storage floor drains was required to be acid resistant
per Illinois c_t C, .:e 2004. However,this was required after the contract was awarded so this item was not
provided in d.r The contractor had provided only Schedule 40 PVC vent piping. The amount of the
Change O• _. ;ides 'credit for Schedule 40 PVC vent material,the PVC fittings, and an add for the acid
resistant pi T•ai; The change order was verified by our plumbing engineer with respect to approved Unit
Cost pricir :icing :om plumbing suppliers.
Total $ 8,132.25