HomeMy WebLinkAbout06-200 Resolution No. 06-200 RESOLUTION APPROVING CHANGE ORDER NO. 1 IN THE CONTRACT WITH TRIGGI CONSTRUCTION, INC. FOR 2006 NEIGHBORHOOD RESURFACING JACKSON/CRYSTAL PROJECT WHEREAS,the City of Elgin has heretofore entered into a contract with Triggi Construction, Inc. for the 2006 Neighborhood Resurfacing Jackson/Crystal Project; and WHEREAS,it is necessary and desirable to modify the terms of the contract as is described in Change Order No. 1, attached hereto. NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF ELGIN,ILLINOIS,that Olufemi Folarin,City Manager,be and is hereby authorized and directed to execute Change Order No. 1,a copy of which is attached hereto and made a part hereof by reference. s/Ed Schock Ed Schock, Mayor Presented: August 9, 2006 Adopted: August 9, 2006 Omnibus Vote: Yeas: 7 Nays: 0 Attest: s/Dolonna Mecum Dolonna Mecum, City Clerk • ELGIN,ILLINOIS PROJECT 39908B CHANGE ORDER No. 1 CONTRACT: 2006 Neighborhood Resurfacing—Jackson/Crystal Project SCOPE: This Change Order No. 1 will provide additional items necessary to complete the 2006 Neighborhood Resurfacing—Country Jackson/Crystal Project in an acceptable manner. This change order affects a contract entered into between the City of Elgin and Triggi Construction, Inc. of West Chicago, IL, an Illinois corporation, dated May 12, 2006 for the 2006 Neighborhood Resurfacing—Jackson/Crystal Project. REASONS FOR CHANGE: This Change Order No. 1 is in the best interests of the City and is authorized by law. The necessity for the changes was unforeseen at the time of the original agreement, and the changes contemplated hereby are germane to the original agreement. SUMMARY OF CHANGES IN CONTRACT AMOUNT: The amount the contract will be revised is as follows: Attachment A is incorporated herein and describes the additional work to be performed by the Contractor and additional contract amounts to be paid by the City in this Change Order No. 1. The original contract with Triggi Construction, Inc. is $2,810,092.50. By reason of Change Order No. 1,the contract for the 2006 Neighborhood Resurfacing—Country Jackson/Crystal Project will be increased in the amount of two hundred twenty thousand nine hundred ninety five and 00/100 dollars ($220,995.00). The new contract amount, inclusive of Change Order No. l is three million thirty one thousand eighty seven and 50/100 dollars ($3,031,087.50). CHANGE ORDER No.! July 10, 2006 Page 2 OTHER CONTRACT PROVISIONS: All other contract provisions shall remain the same. Agreed to this day of , 2006. Recommended: ENGINEERING DIVISION By: 6a— Title: Date: '7- (327-- 06 Accepted: TRIGGI CONSTRUCTION, INC. Party of the S e .nd . ■ l actor) By: if'. P►:fartw,t. Title: Kolar m Date: M/1/6 Approved: CITY OF ELGIN Party of the First Part (Owner) By: Title: Date: Attachment A 2006 Neighborhood Resurfacing - Jackson/Crystal Project Item Unit Quantity Unit Price Total RCCP Storm Sewer, 60" Dia. L.F. 132 $1,005.00 $132,660.00 RCCP Storm Sewer, 54" Dia. L.F. 20 $995.00 $19,900.00 RCCP Storm Sewer, 12" Dia. L.F. 50 $145.00 $7,250.00 Plug, 60" Dia. Ea. 1 $2,100.00 $2,100.00 Plug, 50" Dia. Ea. 1 $2,050.00 $2,050.00 Inlets Ea. 2 $1,105.00 $2,210.00 Manhole, 96" Dia. Ea. 3 $16,275.00 $48,825.00 Traffic Control and Protection L.S. 1 $6,000.00 $6,000.00 Total = $220,995.00 OF Agenda Item No. — City of Elgin A July 21, 2006 ' , TO Mayor and Members of the City Council FROM: Olufemi Folarin, City Manager s,,,+t John Loete, Public Works Dire tor c-ir Government SUBJECT: Change Order No. 1 for the 2006 Neighborhood Resurfacing — Jackson/Crystal Project. PURPOSE The purpose of this memorandum is to provide the Mayor and members of the City Council with information to consider authorization of Change Order No. 1 for the subject project. RECOMMENDATION It is recommended that the City Council authorize the City Manager to execute Change Order No. 1 in the amount of$220,995.00 to the contract with Triggi Construction, Inc. for the 2006 Neighborhood Resurfacing—Jackson/Crystal Project. BACKGROUND On April 26, 2006,the City Council awarded the subject project to Triggi Construction, Inc. The project includes, where necessary, the removal and replacement of curb & gutter, sidewalk, drive approaches and pavement base repair. The existing pavement will be ground and overlayed with 3 inches of new, bituminous concrete. The project also includes the replacement of approximately 5,500 L.F. of 8 inch water main and replacement of 54 brick catch basins. Change Order No.1 ($220,995.00) will add 8 new contract pay items. These items are for installation of approximately 150 L.F. of large diameter storm sewer and appurtenances. The storm sewer is part of the 2006 Combined Sewer Separation (CSS)-Highland Ave. Project. A copy of Change Order No. 1 is attached as Exhibit A. The 2006 CSS-Highland Ave. Project will provide a new storm sewer on Highland Ave. and W. Chicago St. to separate the current combined (storm and sanitary) sewer. The subject portion of the sewer falls under portions of Jackson Street and Highland Avenue that are to be resurfaced as part of the Jackson/Crystal project. By constructing the new sewer now, the newly resurfaced street will not need to be disrupted when the rest of the sewer project is constructed next year. This work was not included in the original bid because the Sewer Separation Project design was Change Order# 1 for Jackson-Crystal Resurfacing Project *00^ July 21, 2006 Page 2 not complete and the sewer size and location had not been determined when the resurfacing project was bid. COMMUNITY GROUPS/INTERESTED PERSONS CONTACTED None gitiA., FINANCIAL IMPACT The cost of Change Order No. 1 totals $220,995.00. Funds for construction of the sewer are available in sewer portion of the 2005 General Obligation Bond Fund, account number 365- 4200-795.92-41, "Distribution Systems", project number 339691, "Combined Sewer Separation Project"with $385,000 budgeted and $373,726 available. LEGAL IMPACT None ALTERNATIVES 1. Approve Change Order No. 1. 2. Do not approve Change Order No.1. Respectfully submitted for Council consideration. do Attachment