HomeMy WebLinkAbout04-267 Resolution No. 04-267
RESOLUTION
AUTHORIZING TERMINATION OF THE LINCOLN/DOUGLAS
SEWER SEPARATION PROJECT CONTRACT WITH MOLA CONSTRUCTION CO., INC.
AND AUTHORIZING THE AWARD OF A CONTRACT FOR THE REMAINING PORTION
OF THE PROJECT TO GETDOWN UNDERGROUND, INC.
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF ELGIN, ILLINOIS,that
David M.Dorgan,City Manager,be and is hereby authorized and directed to terminate for cause the
Lincoln/Douglas Sewer Separation Project Contract with Mola Construction Co.,Inc.and is further
authorized to execute all documents in connection with such termination.
BE IT FURTHER RESOLVED BY THE CITY COUNCIL OF THE CITY OF ELGIN,
ILLINOIS, that David M. Dorgan, City Manager, or his designee, be and is hereby authorized and
directed to complete negotiations for a contract for the remaining portion of the Lincoln/Douglas
Sewer Separation Project with the second low bidder for the subject project Getdown Underground,
Inc. and is further authorized and directed to enter into a contract with Getdown Underground, Inc.
for the remaining portion of such project and to execute all documents in connection with such
contract.
s/Ed Schock
Ed Schock, Mayor
Presented: September 22, 2004
Adopted: September 22, 2004
Vote: Yeas: 6 Nays: 0
Attest:
s/ Dolonna Mecum
Dolonna Mecum, City Clerk
SEPTEMBER 22, 2004 VOLUME LXIX
Resolution No. 04-266
RESOLUTION
AUTHORIZING EXECUTION OF A PURCHASE AND SALE AGREEMENT
WITH MONROE ACQUISITION PARTNERS LLC FOR PROPERTY LOCATED AT THE
NORTHEAST CORNER OF RANDALL ROAD AND COLLEGE GREEN DRIVE
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF ELGIN, ILLINOIS,
that Ed Schock, Mayor, and Dolonna Mecum, City Clerk, be and are hereby authorized and
directed to execute a Purchase and Sale Agreement on behalf of the City of Elgin with Monroe
Acquisition Partners LLC for property consisting of approximately 26.45 acres located at the
northeast corner of Randall Road and College Green Drive, a copy of which is attached hereto
and made a part hereof by reference.
s/Ed Schock
Ed Schock, Mayor
Presented: September 22, 2004
Adopted: September 22, 2004
Vote: Yeas: 6 Nays: 0
Attest:
s/Dolonna Mecum
Dolonna Mecum, City Clerk
RESOLUTION 04-267 ADOPTED AUTHORIZING TERMINATION OF THE
LINCOLN/DOUGLAS SEWER SEPARATION PROJECT CONTRACT WITH MOLA
CONSTRUCTION CO., INC. AND AUTHORIZING THE AWARD OF A CONTRACT
FOR THE REMAINING PORTION OF THE PROJECT TO GETDOWN
UNDERGROUND,INC.
Councilmember Rodgers made a motion, seconded by Councilmember Figueroa, to adopt the
following resolution. Upon a roll call vote: Yeas: Councilmembers Figueroa, Gilliam, Rodgers,
Sandor, Walters and Mayor Schock. Nays:None.
Resolution No. 04-267
RESOLUTION
AUTHORIZING TERMINATION OF THE LINCOLN/DOUGLAS
SEWER SEPARATION PROJECT CONTRACT WITH MOLA CONSTRUCTION CO., INC.
AND AUTHORIZING THE AWARD OF A CONTRACT FOR THE REMAINING PORTION
OF THE PROJECT TO GETDOWN UNDERGROUND, INC.
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF ELGIN, ILLINOIS,
that David M. Dorgan, City Manager, be and is hereby authorized and directed to terminate for
780
AGREEMENT
THIS AGREEMENT is dated this 25th day of October, 2004, by and between the CITY OF ELGIN, an
Illinois Municipal Corporation(herein called"City")and GETDOWN UNDERGROUND, INC. (herein
called "Contractor"), a Corporation with a principal place of business at 1311 North Raddant Road,
Batavia, Illinois 60510.
WHEREAS, on February 20, 2004 the City released an Invitation for Bids entitled CITY OF ELGIN,
ILLINOIS—LINCOLN/DOUGLAS SEWER SEPARATION PROJECT and
WHEREAS, Contractor submitted a timely bid on March 16, 2004 and
WHEREAS, the City Council has deemed Contractor to be the lowest price responsive and
responsible bidder to complete the balance of the CITY OF ELGIN,ILLINOIS—LINCOLN/DOUGLAS
SEWER SEPARATION PROJECT, hereinafter referred to as"Work;"
NOW THEREFORE, in consideration of the mutual covenants herein set forth, the sufficiency of
which is hereby acknowledges, the parties hereto hereby agree as follows:
Article 1. WORK.
Contractor shall complete the Work as specified in the Contract Documents.
The Work is generally described as follows:
The completion of the improvements for the subject Project as of October 4, 2004. The
proposed construction consists of the replacement of 18-inch and 8-inch sanitary sewer;replacement of
"break-in" branch tee connections; and replacement of brick sanitary manholes in order to upgrade
existing combined sewer to sanitary sewage use only.
The installation of 42-inch,36-inch,24-inch, 18-inch,and 12-inch storm sewer;storm manholes;
catch basins;and inlets as part of a new storm system to transport the water currently being handled by
the combined sewer system.
Also included in the work is patching of the sewer trenches; removal and replacement of all
water services crossed by the new storm sewer; tunneling of historic curbs in lieu of removing and
replacing the curbs; curb and gutter replacement; erosion control; parkway restoration; and other
miscellaneous items of work.
Article 2. ENGINEER.
The Work has been designed by Baxter&Woodman, Inc. ("Engineer"). Engineer shall act as City's
representative and shall assume and provide such duties and obligations to the extent provided in the
Contract Documents.
Article 3. WORK COMPLETION, LIQUIDATED DAMAGES, DELAYS AND DAMAGES.
3.1. Work Completion.The Work shall be completed as provided in the Contract Documents. The
Work will be substantially completed on or before December 3, 2004, and completed and ready for
final payment in accordance with the Supplementary Conditions on or before December 30,2004. In
the event of any conflict between these dates and dates elsewhere in the Contract Documents,these
dates shall prevail. Time is of the essence in this Agreement.
AGREEMENT
00500-1 (Eng. Job No. 021193/Const. Job No. 041296)
3.2. Liquidated Damages. City and Contractor agree that as reasonable liquidated damages for
delay(but not as a penalty)Contractor shall pay City$640 for each day beyond the time specified for
Substantial Completion in the Contract Documents. After Substantial Completion, if Contractor shall
neglect, refuse, or fail to complete the remaining Work within the times specified in the Contract
Documents(hereinafter referred to as"Contract Times")or any proper extension thereof granted by
City, Contractor shall pay City$320 for each day beyond the time for Final Completion.
3.3. Delays and Damages. In the event Contractor is delayed in the prosecution and completion of
the Work or achievement of any Contract Times because of any delays caused by City or Engineer,
Contractor shall have no claim against City or Engineer for damages or contract adjustment other
than an extension of the Contract Times as provided herein and the waiving of liquidated damages
during the period occasioned by the delay.
Article 4. CONTRACT PRICE.
City shall pay Contractor$1,259,313.06. This value is based on the Contractor's Bid Price submitted
($1,833,562.50) minus the value of completed work.
Article 5. PAYMENTS.
5.1. Payments. City shall make payments on the basis of Contractor's Applications for Payment as
recommended by Engineer, in conformance with the City of Elgin's accounts payable schedule. All
payments shall be based on the progress of the Work measured by the schedules provided in the
Contract Documents.
5.2. Retainaqe. City may withhold, from all payments prior to Substantial Completion, an amount
equal to up to ten percent(10%)of work completed, at City's sole discretion.
Upon Substantial Completion, City may release a portion of the retainage to Contractor,retaining at all
times an amount sufficient to cover the cost of the Work remaining to be completed, at City's sole
discretion.
The time for payment of any retainage from City to Contractor shall be at City's sole discretion. Such
payment shall not be unreasonably withheld.
5.3. Final Payment. The City shall not be required to make final payment prior to completion and
acceptance of the Work by the City.
Article 6. CONTRACT DOCUMENTS.
There are no Contract Documents other than those listed below. The Contract Documents which
comprise the entire agreement between City and Contractor concerning the Work consist of the
following:
a. This Agreement.
b. Certificates of Insurance.
c. Bonds.
d. Notice of Award.
e. Notice to Proceed.
f. General Conditions.
AGREEMENT
00500-2 (Eng. Job No. 021193/Const. Job No. 041296)
g. Supplementary Conditions.
h. Specifications.
i. Drawings consisting of 21 sheets, with each sheet bearing one of the following general
titles: CITY OF ELGIN, ILLINOIS — LINCOLN/DOUGLAS SEWER SEPARATION
PROJECT
Sheet titles are listed on the cover sheet of each drawing set.
j. Any Addenda.
k. Contractor's Bid.
I. City Forms.
m. Any subsequent Written Amendments to any documents listed above and other documents
amending, modifying,or supplementing the Contract Documents,which may be delivered
or issued after the Effective Date of the Agreement and are not attached hereto.
This Agreement and the Contract Documents listed above comprise the sole and exclusive
Agreement between the parties hereto. There are no other agreements between the parties hereto
either oral or written, and neither this Agreement nor any Contract Documents shall be modified or
amended without the written consent of the authorized representatives of the parties hereto.
Article 7. MISCELLANEOUS.
a. Terms used in this Agreement shall have the meanings indicated in the General
Conditions.
b. No assignment or delegation by a party hereto of any rights under,obligations or interests
in the Contract Documents shall be binding on another party hereto without the written
consent of the party sought to be bound;and specifically but without limitation moneys that
may become due and moneys that are due may not be assigned without such consent
(except to the extent that the effect of this restriction may be limited by law); and unless
specifically stated to the contrary in any written consent to an assignment, no assignment
shall release or discharge the assignor from any duty or responsibility under the Contract
Documents.
c. City and Contractor each binds itself, its partners, successors, employees, assigns, and
agents to the other party hereto,its partners, successors,employees,assigns,and agents
in respect of all covenants, agreements, and obligations contained in the Contract
Documents.
d. The business address of Contractor is hereby designated as the place to which all notices,
letters, and other communication to Contractor shall be mailed or delivered. The address
of City is hereby designated as the place to which all notices, letters, and other
communication to City shall be mailed or delivered. Such notices, letters and other
communications shall be directed to the City's General Services Manager. Either party
may change its address at any time by an instrument in writing delivered to Engineer and to
the other party.
e. The terms and provisions of this Agreement shall be severable. In the event any of the
terms or provisions of this Agreement shall be deemed to be void or otherwise
AGREEMENT
00500-3 (Eng. Job No. 021193/Const. Job No. 041296)
y�
unenforceable for any reason, the remainder of this Agreement shall remain in full force
and effect.
f. This Agreement shall be subject to and governed by the laws of the State of Illinois. Venue
for the resolution of any disputes and the enforcement of any rights arising out of or in
connection with the Agreement shall be in the Circuit Court of Kane County, Illinois.
g. This Agreement shall not be construed so as to create a partnership, joint venture,
employment or agency relationship between the parties hereto except as may be
specifically provided for herein.
h. In the event of any conflict between any of the terms or provisions of this Agreement and
any other Contract Documents, the terms and provisions of this Agreement shall control.
i. Indemnification. To the fullest extent permitted by law, Contractor agrees to and shall
indemnify, defend and hold harmless the City, its officers, employees, boards and
commissions from and against any and all claims,suits,judgments,costs, attorneys fees,
damages or any and all other relief or liability arising out of or resulting from or through or
alleged to arise out of any acts or negligent acts or omissions of Contractor or Contractor's
officers,employees,agents or subcontractors in the performance of this agreement. In the
event of any action against the City, its officers,employees,agents, boards or commissions
covered by the foregoing duty to indemnify,defend and hold harmless,such action shall be
defended by legal counsel of the City's choosing.
IN WITNESS WHEREOF, City and Contractor have signed this Agreement. One counterpart each
has been delivered to City, Contractor, Surety, and Engineer.
This Agreement shall be effective on May 28, 2004.
CITY OF ELGIN, ILLINOIS GETDOWN UNDERGROUND, INC.
City: David M. Dorgan Contactor: Mark K. Kennedy
By h-4. - " :.��!,
Title: City Manager Title: P -sident
Address for giving notices Address for giving notices
150 Dexter Court 1311 North Raddant Road
Elgin, Illinois 60120 Batavia, Illinois 60510
FEIN# 36-4286018