HomeMy WebLinkAbout04-157 Resolution No. 04-157
RESOLUTION
APPROVING CHANGE ORDER NO. 1 IN THE CONTRACT
WITH VIRGIL COOK AND SON, INC. FOR THE
2003 MID-BLOCK STREET LIGHTING PROJECT
WHEREAS, the City of Elgin has heretofore entered into a contract with Virgil Cook and
Son, Inc. for the 2003 Mid-Block Street Lighting Project; and
WHEREAS,it is necessary and desirable to modify the terms of the contract as is described
in Change Order No. 1, attached hereto.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF
ELGIN,ILLINOIS,that David M.Dorgan,City Manager,be and is hereby authorized and directed to
execute Change Order No. 1,a copy of which is attached hereto and made a part hereofby reference.
s/Ed Schock
Ed Schock, Mayor
Presented: June 23, 2004
Adopted: June 23, 2004
Omnibus Vote: Yeas: 6 Nays: 0
Attest:
s/Dolonna Mecum
Dolonna Mecum, City Clerk
II
ELGIN, ILLINOIS
PROJECT 339782, 2003 Mid-Block Lighting Project
CHANGE ORDER No. 1
CONTRACT: 2003 Mid-Block Lighting Project
SCOPE: This Change Order No. 1 will increase the quantities of items as set
forth in Attachment A hereto.
The general contractor for this project is Virgil Cook and Son, Inc. of DeKalb, Illinois.
REASON FOR CHANGE: This Change Order No. 1 is in the best interest of the City
and is authorized by law.
SUMMARY OF CHANGES IN CONTRACT AMOUNT:
SEE ATTACHMENT A
The original contract with Virgil Cook and Son, Inc. is $27,706.90. By reason of Change
Order No. 1, the contract for the 2003 Mid-Block Lighting Project will be increased in the
amount of twenty seven thousand seven hundred fifty six and 10/100 dollars
($27,756.10). The new contract amount, inclusive of Change Order No. 1 is fifty five
thousand four hundred sixty three and 00/100 ($55,463.00).
•
CHANGE ORDER No. 1
May 26,2004
PAGE 2 OF 2
OTHER CONTRACT PROVISIONS: All other contract provisions shall remain the same.
Agreed to this day of , 2004.
Recommended:
Public Works Department
By: a44g. /� uT a
Title: apE(La T‘00143 a PT.
Date: 6�/d�oi
Accepted: 1��
Virgil Cook and Son, Inc.
Party of the Second Part (Contractor)/
By: ��✓ 1 LZ./ I
Susan A.Carlson
Title: President
Date: 6/09/04
Approved: �/
Gary A. arlson, Proj. Coordinator
CITY OF ELGIN
Party of the First Part (Owner)
By: 9P-4-.,42_frfa,..,--
Title:
Date: ‘7d: `j/e/"?e/"?
Change
Original Order No. 1 Total
Item No. Item Description Unit Quantity Quantity Quantity Unit Price Total Cost
1 Traffic Control and Protection L.Sum 1 0 1 $ 1,600.00 $ 1,600.00
2 Electric Service Installation Each 1 0 1 $ 485.00 $ 485.00
3 Electric Utility Service Connection Each 1 0 1 $ 1,000.00 $ 1,000.00
4 Grounding Electrod in Foundation Each 5 9 14 $ 46.00 $ 644.00
5 Condut Pushed,4"Dia.,Galvanized Steel Foot 165 0 165 $ 22.40 $ 3,696.00
6 Trench and Backfill for Electrical Work Foot 1060 0 1060 $ 1.60 $ 1,696.00
7 Unit Duct,2#10XLP. 1#10XLP Ground 3/4"Dia.Polyethylene Foot 50 0 50 $ 2.20 $ 110.00
Unit Duct,with 3-1/C No.4 and 1/C No.6 Ground,600V(XLP-Type use),
8 1-1/4"Dia Polyethylene Foot 1225 0 1225 $ 2.65 $ 3,246.25
9 Unit Duct,2#2 XLP, 1#2 XLP Ground 1-1/4"Dia.Polyethylene Foot 150 0 150 $ 5.30 $ 795.00
10 Electric Cable in Conduit,600V(XLP-Type Use) 1/C No. 10 Foot 408 918 1326 $ 0.30 $ 397.80
11 Lighting Controller, Special Each 1 0 1 $ 4,225.00 $ 4,225.00
12 Light Pole Foundation,24"Dia. Foot 24 54 78 $ 95.00 $ 7,410.00
13 Break Away Device,Coupling,with aluminum skirt Each 4 9 13 $ 280.00 $ 3,640.00
14 Removal of Lighting Unit,Salvage Each 1 1 2 $ 210.00 $ 420.00
15 Lighting Foundation Removal Each 1 2 3 $ 135.00 $ 405.00
16 Light Pole,Aluminum,25 FT M.H.,6 FT Davit Arm Each 4 9 13 $ 885.00 $ 11,505.00
17 Luminaire,Metal Halide, Horizontal Mount, 175 Watt Each 4 9 13 $ 280.00 $ 3,640.00
18 Sodding and Supplemental Watering SY 215 188 403 $ 9.75 $ 3,929.25
Polyethylene Duct,Bored and Pulled 1-1/4"Dia.,with 3-1/C No.4 and 1/C
19 No.6 Ground,600V(XLP-Type Use) Foot 0 1094 1094 $ 6.05 $ 6,618.70
Total Value of Contract $ 55,463.00