Loading...
HomeMy WebLinkAbout02-72 • Resolution No. 02-72 RESOLUTION APPROVING CHANGE ORDER NO. 1 IN THE CONTRACT WITH RYAN INCORPORATED CENTRAL FOR THE HIGHLANDS OF ELGIN GOLF COURSE WHEREAS, the City of Elgin has heretofore entered into a contract with Ryan Incorporated Central for construction associated with The Highlands of Elgin Golf Course; and WHEREAS, it is necessary and desirable to modify the terms of the contract as is described in Change Order No. 1 , attached hereto. NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF ELGIN, ILLINOIS, that Olufemi Folarin, Interim City Manager, be and is hereby authorized and directed to execute Change Order No. 1, a copy of which is attached hereto and made a part hereof by reference . s/ Ed Schock Ed Schock, Mayor Presented: February 27, 2002 Adopted: February 27, 2002 Omnibus Vote : Yeas : 7 Nays : 0 Attest : s/ Dolonna Mecum Dolonna Mecum, City Clerk CHANGE ORDER REQUEST DISTRIBUTION: x I PROJECT MANAGER RYAN INCORPORATED CENTRAL I x I GOLF COURSE ARCHITECT P.O. BOX 206 I FIELD OFFICE JANESVILLE,WI 53547 11 I, 608/754-2291 PROJECT: CHANGE ORDER NUMBER: 11 1;i Elgin Municipal Golf Course DATE: 12/31/01 Elgin, Illinois TO PROJECT MANAGER: CONTRACT FOR: Randy W. Trull Golf Course Construction 3311 Sandstone Ct Lake in the Hills, IL 60102 847/658-3512 THE CONTRACT IS HEREBY CHANGED AS FOLLOWS: 1. Clubhouse/Maintenance Site Remediation 1 LS @ $136,556.00 = $136,556.00 Clubhouse Site Remediation 1 LS @ $7,990.00 = $7,990.00 Maintenance Site Remediation Subtotal $144,546.00 2. Water Supply Line&Float Pump&Generator 1 LS @ $53,404.00 = $53,404.00 Water Supply Line&Float Pump, incl. Generator Subtotal $53,404.00 3. Treatment Facility Discharge 1 LS @ $182,842.21 = $182,842.21 Treatment Facility Discharge Subtotal $182,842.21 4. Vandalism/Erosion Damage Repair 1 LS @ $37,774.94 = $37,774.94 Vandalism/Erosion Damage Repair Subtotal $37,774.94 5. Fertigation System 1 LS @ $32,525.00 = $32,525.00 Fertigation System Subtotal $32,525.00 6. Utility Costs 1 LS @ $1,551.00 = $1,551.00 Install Electrical Conduit at Maintenance 1 LS @ $12,134.55 = $12,134.55 Utility Cleanup 1 LS @ $22,614.76 = $22,614.76 Primary Electrical Service Subtotal $36,300.31 Amount: $487,392.46 Reasons for the Change Order: 1. The circumstances said to necessitate the change in performance were not reasonably foreseeable at the time the contract was signed; and 2. the change is germane to the original contract as signed; and 3. the change order is in the best interest of the city and authorized by law. Original Contract Sum: $3,198,470.70 Net Change By Previous Change Orders: $0.00 Contract Sum Prior To This Change Order: $3,198,470.70 Amount Of This Change Order: $487,392.46 New Contract Sum Including This Change Order: $3,685,863.16 Contract Time Will Be Changed By: 0 Days All other terms of the original contract are unchanged and remian in full force and effect. PROJECT MANAGER: CONTRACTOR: CITY OF ELGIN: Randy W , GPM Ryan Incorporated Central City Manager / C z•N r 767'7- ` By: ( By: +�j✓'��•� By Date: ,2 O8/ova Date: F f`% Agenda Item No. — City of Elgin E L January 18 , 2002 ° ' • N TO: Mayor and Members of the City Council f<.Jtt A lit)NAI.I,1-.■1141: ANI>< ILI IIIt AI <)O•f t1It f LINO f 14':: • iOfi Al.l..t..l f,ll N5 FROM: Joyce A. Parker, City Manager SUBJECT: Amendment No. 1 with Ryan Central Construction for additional construction costs associated with The Highlands of Elgin Golf Course PURPOSE The purpose of this memorandum is to provide the Mayor and members of the City Council with information to consider Amendment No. 1 to an agreement with Ryan Central Construction for additional construction costs associated with The Highlands of Elgin Golf Course . BACKGROUND On April 11, 2001 the City entered into a $3 . 2 million contract with Ryan Central, Inc. for the Construction of the initial nine holes of The Highlands of Elgin Golf Course . During the course of the golf course development several issues were encountered that required additional work by Ryan. Item 1 : Clubhouse/Maintenance Site Re-mediation. Both sites were previously used as a dump site . In order to clean up both areas as well as bring in suitable material $144, 546 of additional work was required. Item 2 : Water Supply Due to the severely dry summer conditions, an alternative water source needed to be installed to ensure there was sufficient reserves available to irrigate the golf course . Rather then drill a well at a cost of $400, 000 plus, a floating pump and the drainage system was utilized at a cost of $53 , 404 . Item 3 : To assist the Water Dept . in addressing their ph discharge issue, a stream channel was constructed. The treatment system cost $182 , 842 . 21, it was the least costly alternative and will be paid for by Water Fund monies . rm. Amendment No. 1-Ryan Central Construction January 18, 2002 Page 2 Item 4 : Damage caused by vandals as well as erosion from severe rain events resulted in repair costs totaling $37 , 774 . 94 . Item 5 : In order to significantly reduce long term maintenance costs, the addition of a fertigation system was approved by The Highlands of Elgin Golf Course Leadership Team. The $32 , 525 . 00 cost of the system will pay for itself within the first two years of operation. Item 6 : Utility work consisting of electrical service for the irrigation system, repair work for sewer / water construction and additional conduit beneath the maintenance building parking lot was installed. Total cost of these improvements equal $36, 300 . 31 . The first four items were previously communicated to the City Council with preliminary cost figures . The final two items were either not contemplated in Phase I or brought long term savings to the golf course operation. rm. COMMUNITY GROUPS/INTERESTED PERSONS CONTACTED The Highlands of Elgin Golf Course Leadership Team were apprised of the items included within the change order. r‘-- FINANCIAL IMPACT The cost of Change Order No. 1 totals $487 , 392 .46 . The Water Fund portion of the 2001 Bond Sale, account number 381-4000-795 . 92-36, project number 409557 , South McLean Decant Pond has $200, 000 budgeted to pay for Item #3 in the change order totaling $182 , 842 . 21 . The remaining items within the change order total $304 , 550 . 25 and were not contemplated nor budgeted. The Change Order could be funded by greater than anticipated Riverboat proceeds in that a total of $24 . 3 million was received in 2001 with $23 . 5 million actually used/budgeted. LEGAL IMPACT \q//// The change order will need to be reviewed by the Legal Department . rim. Amendment No. 1-Ryan Central Construction January 18, 2002 Page 3 ALTERNATIVES Do not approve Change Order No. 1 with Ryan Central Construction. RECOMMENDATION It is recommended that the City Council approve Change Order No. 1 in the amount of $487, 392 . 46 with Ryan Central Construction, Inc. for additional construction associated with The Highlands of Elgin Golf Course . Respectfully submitted, Joyce \A. Parker City Manager JN/nh Attachment ** � • * n.. * -� RANDY W. TRULL Golf Project Management PROJECT MEMORANDUM DATE: December 17,2001 TO: Mr. James R.Nowicki, CPA Fiscal Services Manager-City of Elgin • 150 Dexter Court Elgin, IL. 60120-5625 RE: Highlands of Elgin Golf Club Final Cost of Golf Course Construction—Ryan,Inc. Contract Dear Jim, As you requested, the following is a summary of Ryan, Incorporated's cost for construction of the Highlands Golf Course. The original value of the contract, $3,198,470.70, has been adjusted to include Change Orders totaling $487,392.46. The adjusted cost of all work completed is $3,685,863.16. The following provides a description of the additional work performed by Ryan,to be reflected in the form of a change order attached to the final invoice submitted by the contractor: Change Order Item 1: Clubhouse/Maintenance Site Remediation At the time of execution of the original contract, geotechnical information related to the clubhouse site & maintenance sites was not available. Upon investigation, these sites were found to contain a large amount of what appeared to be construction debris,previously deposited and buried at the site by parties unknown. It was determined by the Project Engineer that, in order to support the parking and building areas, this material had to be removed and replaced with suitable material in a controlled (compacted) manner. The cost for additional work required at the two sites totaled$144,546.00. Rough grading of the clubhouse & maintenance sites is complete. Clubhouse Site Remediation Add: $136,556.00 Maintenance Site Remediation Add: $ 7,990.00 Change Order Item 2: Water Supply It was originally intended to drill a new well to provide irrigation water to the golf course. The Golf Project Leadership Team was informed that a supply line connection from the irrigation pond to the existing well could be installed at less cost than that to drill a new well. Although this pipe is not currently in use, the Project Leadership Team acknowledged that it was necessary to install it during this phase of construction. In order to obtain water required for irrigation of the first nine golf holes,a floating pump was installed to pump water through the golf course drainage system from the existing mine settling pond to the irrigation reservoir. Future Water Supply Line&Float Pump Add: $53,404.00 3311 Sandstone Court• Lake in the Hills,IL 60102• 847-658-3512 • Fax 847-658-3513 Highlands of Elgin Golf Club Project Cost Summary: Ryan,Inc.Contract 12/17/01 Page Two Change Order Item 3: Water Lime-Treatment Facility Discharge During construction,the City authorized the contractor to construct a channel to discharge water from the lime treatment facility to the existing stream at the southeast boundary of the golf course property. The contractor also manufactured and installed an overflow release control structure.The Project Manager,City Water Dept. staff and Black&Veatch Engineers monitored this work. The entire system is complete and has been approved by the design engineers,Black&Veatch Engineering. Treatment Facility Discharge Add: $182,842.21 Change Order Item 4: Vandalism Damage/Erosion Repair On at least four occasions,after completion and acceptance by the City,vandals entered onto the property in motor vehicles,resulting in significant damage to several greens,tees and fairway areas.The golf course also incurred moderate erosion damage in some areas as a result of severe rain events immediately after planting. The contractor was authorized by the City to repair vandalism and/or erosion damage resulting from severe rain events following completion of work. Vandalism/Erosion Damage Repair after acceptance Add: $37,774.94 Change Order Item 5: Fertigation System A fertigation injection system was added to the irrigation pumpstation. This system, which will inject various chemicals, herbicides and fertilizers directly into the water supply as it is pumped to the golf course, has been proven to significantly reduce long-term maintenance costs by eliminating the need to apply these agents by equipment operated maintenance personnel. It is estimated that this system will reduce initial equipment purchase costs and annual maintenance personnel costs to the degree that it will pay for itself within the first two years of operation and will continue to reduce maintenance costs thereafter.The Golf Project Leadership Team approved this very cost-effective option. Fertigation System Add: $32,525.00 Change Order Item 6: Utility Costs Plans and specifications for utilities were not developed at the time of execution of the original contract. This is a cost the City had scheduled as part of Phase H. However, because this would have required disturbance of the golf holes constructed during Phase I,it was necessary to perform this work at this time. In order to ensure coordination and timely installation of electric service for irrigation and watering of the golf course,the Golf Project Leadership Team authorized this work to be completed at this time. Water and sewer services to the clubhouse, maintenance and on-course restroom facilities were largely installed in golf course areas. This required the contractor to restore those areas disturbed by the sewer/water contractor. Ryan was authorized to repair these areas for additional cost. The cost of restoration/sodding ($14,700.00) was deducted from the sewer/water contractor's (Getdown Underground's)contract amount.This resulted in a net project cost reduction of$2,565.45. r 3311 Sandstone Court•Lake in the Hills,IL 60102• 847-658-3512• Fax 847-658-3513 ribk Highlands of Elgin Golf Club Project Cost Summary:Ryan,Inc.Contract 12/17/01 Page Three The contractor was requested to install additional electric conduit beneath the maintenance site parking area to prevent damage to electrical cables during construction of the maintenance facility. Installation of electric conduit at maintenance Add: $ 1,551.00 Utility cleanup Add: $ 12,134.55 Primary Electric Service Add: $22,614.76 1. Clubhouse/Maintenance Site Remediation Add: $144,546.00 2. Future Water Supply Line/Float Pump Add: $ 53,404.00 3. Treatment Facility Discharge Add: $182,842.21 4. ,Vandalism/Erosion Damage Repair Add: $ 37,774.94 5. Fertigation System Add: $ 32,525.00 Electric Service Add: $ 22,614.76 6. Primary Utility cleanup Add: $ 12,134.55 Installation of electric conduit at maintenance Add: $ 1,551.00 Total Value-Change Order 1 Add: $487,392.46 Original Value of Contract $3,198,470.70 Amount of Change Orders Add: $ 487,392.46 Total Contract Price Adjusted for Change Orders $3,685,863.16 Please contact me at my office#847-658-3512,or my mobile#847-624-1418 at any time. Sin Randy Z.Trulv l Golf Project Manager 3311 Sandstone Court• Lake in the Hills,IL 60102• 847-658-3512•Fax 847-658-3513