HomeMy WebLinkAbout02-209 Resolution No. 02-209
RESOLUTION
APPROVING CHANGE ORDER NO. 1 IN THE CONTRACT WITH
SEAGREN CONSTRUCTION, INC. FOR THE
AIRLITE WATER TREATMENT PLANT IMPROVEMENTS-SECTION II
WHEREAS, the City of Elgin has heretofore entered into a
contract with Seagren Construction, Inc . for the Airlite Water
Treatment Plant Improvements-Section II ; and
WHEREAS, it is necessary and desirable to modify the terms of
the contract as is described in Change Order No. 1, attached
hereto.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY
OF ELGIN, ILLINOIS, that Olufemi Folarin, Interim City Manager, be
and is hereby authorized and directed to execute Change Order
No. 1, a copy of which is attached hereto and made a part hereof by
reference.
s/ Ed Schock
Ed Schock, Mayor
Presented: June 12 , 2002
Adopted: June 12 , 2002
Omnibus Vote : Yeas : 5 Nays : 0
Attest :
s/ Dolonna Mecum
Dolonna Mecum, City Clerk
,
ELGIN, ILLINOIS
WATER WORKS IMPROVEMENTS
AIRLITE WTP IMPROVEMENTS
CHANGE ORDER NO. 1
SCOPE
This Change Order No. 1 adjusts the Contract Price to account for additions and
modifications as indicated below.
NATURE OF CHANGES
1. Relocation of Power and Signal Conduits to Bulk Water Station. Re-route
electrical conduits from Odor Control Building to Bulk Water Station. Refer to
Contractor's letter dated September 25, 2001.
2. Change Door 700 to Flush Aluminum. Door 700 will be changed to flush
aluminum instead of the glass door. The City requested that Door 700 be flush
aluminum with insulation. Refer to Contractor's letter dated October 15, 2001.
3. Metal Wall Panels in Airlite Filter Gallery. Change installation detail of metal
wall panels in Airlite Filter Gallery as shown in Field Order No. 5. Refer to
Contractor's letter dated January 21, 2002.
4. Remove 12-inch steel pipe in Boiler Room. Remove steel pipe and perform other
work as described in Field Order No. 4. Refer to Contractor's letter dated January
21, 2002.
5. Delete Curbs and Lining in the Odor Control Building Curbs and protective lining
were deleted from Contract in Field Order No. 2. Refer to Contractor's letter
dated January 28, 2002.
6. Delete HVAC work in Odor Control Building_HVAC work deleted from
Contract in Field Order No. 3. Refer to Contractor's letter dated January 21, 2002.
7. "Bisque" color for NaOH tank at Riverside. Specialty color for the NaOH storage
tank at the Riverside WTP. Refer to Contractor's letter dated December 3, 2001.
8. Air Line at Riverside Plant. Re-route 2-inch air line to NaOH containment area to
avoid excavating in parking lot. Refer to Contractor letter dated January 21, 2002.
CO1-1
9. Curbs, Lining, and Terrazzo for Chemical Feed Room. Modify containment,
flooring, and piping in Chemical Feed Room at Airlite WTP. Refer to Contractor
letter dated January 29, 2002.
10. Paint Lab/Storage Room, Control Room, Storage Room Cabinets. Perform extra
painting on Operating Floor of Airlite WTP. Refer to Contractor letter dated
September 20, 2001.
STATUTORY BASIS FOR CHANGES
Change Order No. 1 is necessary and proper due to the following:
• The above changes were not anticipated for the reasons listed, at the time the
contract with Seagren Construction, Inc. was authorized.
• It is in the best interest of the Owner to approve the above changes.
• These changes are germane to the intent and scope of the original contract.
SUMMARY OF CHANGES IN CONTRACT AMOUNT
Adjustments to the Contract Price resulting from the aforementioned items shall be the
negotiated lump sum prices covering all compensation due for the work as shown in
Table 1 in the amount of$30,225.
OTHER CONTRACT PROVISIONS
All other Contract provisions shall remain unchanged.
C01-2
•
CHANGE ORDER NO. 1
Table 1
Summary of Contract Price Changes
ITEM ADD DEDUCT
1. Relocation of Power and Signal Conduits to B.W.S. $2,694.00
2. Change Door 700 to Flush Alumnium $1,346.00
3. Metal Wall Panels in Airlite Filter Gallery $26,489.00
4. Remove 12-inch steel pipe in Boiler Room $4,197.00
5. Delete Curbs and Lining in the Odor Control Building $7,142.00
6. Delete HVAC work in Odor Control Building $2,834.00
7. "Bisque"color for NaOH tank at Riverside $410.00
8. Air Line at Riverside Plant $4,389.00
9. Curbs, Lining, and Terrazo for Chemical Feed Room $7,669.00
10. Paint Lab/Storage Room,Control Room, Stor. Room $1,785.00
Cabinets
TOTAL ADD $44,590.00
TOTAL DEDUCT $14,365.00
NET CONTRACT PRICE CHANGE $30,225.00
ORIGINAL CONTRACT AMOUNT $2,372,200.00
NET CONTRACT PRICE CHANGE $ 30,225.00
NEW CONTRACT AMOUNT $2,402,425.00
C01-3
1
ACCEPTANCE
The changes and conditions set forth in this Change Order No. 1 are hereby accepted. All
other provisions of the Contract remain unchanged.
SEAGREN CONSTRUCTION INC. CITY OF ELGIN, ILLINOIS
(ContrItor) (Owner)
By: - By: 't' -� - .t►�....
Date: 4 40 b ! Date: ? o 2
CO 1-4
,(OF E�Ci
�� City of Elgin Agenda Item No.
E
L • . pI$.
May 3 , 2002 G iiW �
FINANCIALLY STABLE CITY GOVERNMENT
EFFICIENT SERVICES,
AND DUALITY INFRASTRUCTURE
TO: Mayor and Members of the City Council
FROM: Olufemi Folarin, Interim City Manager
SUBJECT: Authorization for Change Order No. 1 for the
Airlite Water Treatment Plant Improvements
Section II, with Seagren Construction Inc.
PURPOSE
The purpose of this memorandum is to provide the Mayor and members
of the City Council with information to consider authorization of
Change Order No. 1 for the Airlite Water Treatment Plant
Improvements - Section II , with Seagren Construction Inc .
BACKGROUND
On July 25, 2001, the City Council awarded a contract to Seagren
Construction Inc, Elgin, Illinois, for the Airlite Water Treatment
Plant Improvements - Section II .
Change Order No. 1 items are further explained in the attached
letter from Black & Veatch dated 4/11/02 and include the following:
1 . Relocation of Power and Signal Conduits to Bulk Water Station
at Riverside Water Treatment Plant to accommodate the new
Caustic Soda Storage and Feed System.
2 . Change Door 700 to Flush Aluminum.
3 . Metal Wall Panels in Airlite Filter Gallery.
4 . Remove 12-inch steel pipe in Boiler Room.
5 . Delete Curbs and Lining in the Odor Control Building.
6 . Delete HVAC work in the Odor Control Building.
7 . "Bisque" color for Sodium Hydroxide tank at Riverside.
8 . Re-route Air Line at Riverside Plant .
9 . Curbs, Lining, and Terrazo for Chemical Feed Room.
10 . Paint Lab/Storage Room, Control Room, Storage Room Cabinets.
€ Airlite Plant Improvements - Section II, Change Order No. 1
May 3, 2002
Page 2
These 10 items were not anticipated at the time the contract with
Seagren Construction was authorized, and it is in the best interest
of the City to approve the above changes . A copy of Change Order
No. 1 is attached.
COMMUNITY GROUPS/INTERESTED PERSONS CONTACTED
None
OV IMPACT
The total budget for this project is $2 , 923 , 000 . The total cost
for Change Order No. 1 is $30, 225 which can be funded from Account
Number 420-0000-771 . 92-36, Water Development Fund, Buildings &
Structures, project number 409543 , where sufficient monies are
available . The original contract with Seagren Construction was
$2, 372, 200 . This change order will bring the total contract to
$2, 402 , 425 . Remaining funds available are $79, 534 .
LEGAL IMPACT
\WWThe proposed change order is being reviewed by the Legal
department .
ALTERNATIVES
1 . Do not approve the Change Order at this time .
RECOMMENDATION
It is recommended that the City Council authorize the execution of
Change Order No. 1 in the amount of $30, 225 with Seagren
Construction Inc.
Respectfully submitted,
Ai—
Olufemi F. arin
Inte . im Cit• ger
LED:PLB;mb
rft. Attachments
•
BLACK & VEATCH
101 N.Wacker Dr. Black&Veatch Corporation
Suite 1100
Chicago IL,60606
Tel:(312)346-3775
Elgin, Illinois B&V Project No. 31264.438
Airlite WTP Improvements B&V File No. B-1.1
April 11,2002
Mr. Peter Bityou
Water Operations Engineer
City of Elgin
150 Dexter Court
Elgin, Illinois 60120-5555
Subject: Change Order No. 1
Dear Peter:
Enclosed is Change Order No. 1 for the Airlite WTP Improvements project. The change
order includes 9 work items. Change Order No. 1 results in a net increase of$30,225 to
the Contract Price.
All of the work items in the change order have been previously discussed and
recommended for acceptance in previous correspondence. The pricing for each item was
determined to be fair and reasonable for the work to be performed. However, for your
use and convenience,this letter briefly summarizes the background and reasons for, and
advantages of each change order task below.
1. Relocation of Power and Signal Conduits to Bulk Water Station. During
excavation for the NaOH storage tank containment area at the Riverside plant,
electrical conduits to the bulk water station were encountered. These conduits had
to relocated in order to construct the storage tank containment area. This item
includes the costs to Seagren Construction and its electrical subcontractor.
2. Change Door 700 to Flush Aluminum. At the request of the City, Door 700 at the
Airlite WTP was changed from glass with an aluminum frame to flush aluminum.
The City preferred to have a solid metal door with insulation. This item includes
the increased cost for the flush aluminum door.
3. Metal Wall Panels in Airlite Filter Gallery. The details in the contract drawings
showing the installation of new metal wall panels for the Airlite Filter Gallery
were revised after it was determined that the metal tee supporting the coping on
the outside of the Filter Gallery is in poor condition and needs to be replaced.
New details for the installation of the metal wall panels were issued in Field Order
Page 2
Mr. Peter Bityou B&V Project 31264.438
March 26,2002
No. 5. This item includes the costs to Seagren Construction for the extra work
required by Field Order No. 5.
4. Remove 12-inch steel pipe in Boiler Room. At the request of the City,the 12-inch
steel pipe running from the Boiler Room to the 24-inch filter effluent line will be
removed. Field Order No. 4 addresses this work. This line is no longer used and
removing the pipe will increase the available floor space in the Boiler Room. This
item covers the costs to Seagren Construction and its subcontractor for the
removal of the pipe and related repair work.
5. Delete Curbs and Lining in the Odor Control Building. Because the City no
longer uses the Odor Control Building at the Airlite WTP,the City requested that
the planned curbs and protective lining for the NaOH feed area be deleted from
the Work. Field Order No. 2 addresses this work. This item is a credit to the City
reflecting the cost savings for Seagren and its subcontractors.
6. Delete HVAC work in Odor Control Building. Because the City no longer uses
the Odor Control Building at the Airlite WTP, the City requested that the planned
HVAC work for the Odor Control Building at the Airlite WTP be deleted from
the Work. Field Order No. 3 addresses this work. This item is a credit to the City
reflecting the cost savings for Seagren and its subcontractors.
7. "Bisque" color for NaOH tank at Riverside. The City selected the"Bisque"color
from the manufacturer of the NaOH tank at the Riverside WTP. Because Bisque
is a specialty color it is more expensive than the standard colors. This item
includes the cost increase to Seagren for providing the tank in bisque.
8. Air Line at Riverside Plant. Seagren proposed and the City accepted re-routing
the 2-inch air line going to the NaOH tank containment area. This re-route
reduced the amount of work done by Seagren and is a credit to the City in the
amount of the savings to Seagren.
9. Curbs,Lining, and Terrazo for Chemical Feed Room. The City requested
modifications to the layout of the chemical feed pumps, containment curbs, and
flooring in the Chemical Feed Room at the Airlite WTP to provide a separate
containment area for the chemical feed equipment. This item reflects the
increased costs to Seagren and its subcontractor based on the revised layout.
10. Paint Lab/Storage Room, Control Room, Storage Room Cabinets. The City asked
Seagren to have its painting subcontractor perform extra painting in the above
areas of the Airlite WTP. This item reflects the cost of the painting.
Page 3
Mr. Peter Bityou B&V Project 31264.438
March 26,2002
It is B&V's understanding that the City wishes to present this proposed Change Order to
the City Council. B&V will provide Change Order No. 1 to Seagren for signature, upon
your approval.
This proposed Change Order covers Work items for which the City has received price
quotations from Seagren Construction.
Please contact us if you have any questions regarding this change order.
Very truly yours,
BLACK & VEATCH
Paul R. Rom, P.E.
Enclosures
cc: R. Renfrow, w/enclosures
t:\projects\elgin\airlite\change orders\change order 1 letter.doc