HomeMy WebLinkAbout01-204 Resolution No. 01-204
RESOLUTION
AUTHORIZING EXECUTION OF AMENDMENT NO. 4 TO AN
ENGINEERING SERVICES AGREEMENT WITH BAXTER & WOODMAN, INC.
FOR THE OTTER CREEK LIFT STATION
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF ELGIN,
ILLINOIS, that Joyce A. Parker, City Manager, and Dolonna Mecum,
City Clerk, be and are hereby authorized and directed to execute
Amendment No. 4 to an Engineering Services Agreement on behalf of
the City of Elgin with Baxter & Woodman, Inc . for engineering
inspection services for the Otter Creek Lift Station Project, a
copy of which is attached hereto and made a part hereof by
reference .
s/ Ed Schock
Ed Schock, Mayor
Presented: July 25, 2001
Adopted: July 25, 2001
Omnibus Vote : Yeas : 7 Nays : 0
Attest :
s/ Dolonna Mecum
Dolonna Mecum, City Clerk
CITY OF ELGIN, ILLINOIS
OTTER CREEK PUMPING STATION,FORCE MAIN
INFLUENT SEWER AND BOWES ROAD INTERCEPTOR SEWER - UPSTREAM
ENGINEERING SERVICES AGREEMENT
AMENDMENT NO. 4
THIS AGREEMENT AMENDMENT NO. 4 entered into this 2Mt1day of J4 _Gi
2001,by and between the CITY OF ELGIN, an Illinois Municipal Corporation (hereinafter
referred to as "CITY"), and Baxter & Woodman, Inc., an Illinois Business Corporation
(hereinafter referred to as "ENGINEER"), shall modify that Agreement dated 14 September
1995, as amended by Amendment No. 1 dated 31 August 1998, Amendment No. 2 dated 8
March 2000, and Amendment No. 3 dated 25 August 2000, whereby the ENGINEER was
engaged by CITY to perform certain professional services in connection with the preparation
of plans, specifications, estimates of cost, bidding and preconstruction award services, and
construction related engineering services for the Otter Creek Pumping Station, Force Main,
Influent Sewer and Bowes Road Interceptor Sewer-Upstream (hereinafter referred to as
"PROJECT").
WHEREAS, the services did not include construction-related services for the new
sewage pumping station,
AND
WHEREAS, the CITY desires the ENGINEER to provide construction-related
services for the new sewage pumping station,
AND
WHEREAS,the CITY desires to include the payments to the ENGINEER under the
Agreement in connection with the construction of the pumping station project.
In response to these additional services, certain revisions must be made to the
Agreement. In compliance, therefore, the terms and conditions of the Agreement are
modified as specifically set out below. All other parts of the Agreement remain unchanged.
A X T R
- 1 -
orB
_t
•
WOODMAN
Gonsulli ng Engineers
SECTION I.D. of the AGREEMENT, as amended by AMENDMENT NO. 1 and
AMENDMENT NO. 2, is hereby deleted and replaced with the following:
D. The construction-related services to be performed under this
Agreement will consist of the following:
1. General Construction Administration and Resident Project
Representative services, including selected start-up and
operational services, for the Otter Creek Pumping Station
project, ENGINEER's Project No. 990156.
2. Additional services for the Otter Creek Pumping Station
project,provided after the original construction contract final
completion date, or in regards to warranty work by the
Contractor.
3. General Construction Administration and Resident Project
Representative services for the Otter Creek Influent
Sewer/Force Main project will be performed after an
amendment is authorized to this Agreement.
A detailed Scope of Services for the services described in the
foregoing PARAGRAPHS D.1 and D.2 is attached hereto as
Attachment A-1.
SECTION IV.E. of the AGREEMENT, as amended by AMENDMENT NO. 1 and
AMENDMENT NO. 2, is hereby deleted and replaced with the following:
E. The CITY shall reimburse the ENGINEER for professional
construction-related services described in Paragraphs I.D.1 through
I.D.3, for all actual direct employee compensation, overhead, and
expenses, plus a fixed fee for readiness to serve and profit.
1. The ENGINEER's fee for the construction-related services
described in Paragraph I.D.1 for the Otter Creek Pumping
Station project shall be reimbursement for all actual direct
employee compensation, overhead, and expenses, plus ten
(10)percent of the sum of the direct costs, overhead, and non-
payroll expenses for readiness to serve and profit. For the
period from the bid opening to the original construction
contract final completion date, the total amount will not
`B A X T E R
- 2 -
_•
WOODMAN
Consulting Engineers
exceed Two Hundred Eighty-Five Thousand Sixty-Four
Dollars ($285,064) unless this agreement is modified by a
change order or amendment.
2. The ENGINEER's fee for the additional services described in
Paragraph I.D.2 for the Otter Creek Pumping Station project
shall be reimbursement for all actual direct employee
compensation, overhead, and expenses plus a profit of ten
(10) percent of the reimbursement amounts.
3. The ENGINEER's fee for the construction-related services
described in Paragraph I.D.3 for the Otter Creek Influent
Sewer/Force Main project shall be negotiated between the
ENGINEER and the CITY, and this Agreement modified by
a change order or amendment, at such time prior to the
commencement of the work.
SECTION IV. of the AGREEMENT, as amended by AMENDMENT NO. 1,
AMENDMENT NO. 2, and AMENDMENT NO. 3 is hereby further amended to include the
following paragraph IV.J.:
J. A detailed fee breakdown for the additional services described in
Paragraph I.D.1 is attached hereto as Attachment C-4.
All other provisions of the AGREEMENT shall remain in full force and effect.
A X T E
- 3 -
ire
�
WOODMAN
Con.stating E•nginens
IN WITNESS WHEREOF, the undersigned have placed their hands and seals upon
and executed this Agreement in triplicate as though each copy hereof was an original and that
there are no other oral agreements that have not been reduced to writing in this statement.
For the CITY:
ATTEST: THE CITY OF ELGIN, ILLINOIS
By RBy
1"
City Clerk 7 City Man er
(SEAL)
For the ENGINEER:
Dated this 28th day of June, A.D., 2001.
ATTEST: BAXTER & WOODMAN, INC.
By By 722 C,
Secretary President/CEO
(SEAL)
RWB:py 06/29/01
H:\PROJ\ELONC\990156\Amend 4.doc
B A X T E R
-4 -
` E
1111.
WOODMAN
Consulting Engineers
CITY OF ELGIN, ILLINOIS
OTTER CREEK PUMPING STATION,FORCE MAIN
INFLUENT SEWER AND BOWES ROAD INTERCEPTOR SEWER—UPSTREAM
ENGINEERING SERVICES AGREEMENT
ATTACHMENT A-1
SCOPE OF SERVICES
CONSTRUCTION-RELATED SERVICES
1. Represent City
Act as the CITY's representative with duties, responsibilities and limitations of
authority as assigned in the Construction Contract Documents, and advise and
confer with CITY officials during construction and issue the CITY's authorized
instructions to the Contractor.
2. Provide Resident Project Representative
Provide Resident Project Representatives at the construction site on either a full-
time basis of forty (40) hours per week from Monday through Friday, not
including legal holidays, or on a periodic part-time basis from the ENGINEER's
office of not more than eight (8) hours per regular weekday, as deemed necessary
by the ENGINEERS, to stake-out construction lines and grades, to assist the
Contractor with interpretation of the Drawings and Specifications, to observe in
general if the Contractor's work is in conformity with the Final Design
Documents, and to monitor the Contractor's progress as related to the
Construction Contract date of completion. However, the ENGINEERS are not
responsible for the Contractor's construction means, methods, techniques,
sequences or procedures, time of performance, compliance with Laws and
Regulations, or safety precautions and programs in connection with the
PROJECT, and the ENGINEERS do not guarantee the performance of the
Contractor and are not responsible for the Contractor's failure to execute the work
in accordance with the Construction Contract Documents.
3. Review Submittals
Review and approve Shop Drawings, Manufacturer's Literature, Samples, and
other submittals by the Contractor, but only for compliance with the Drawings
and Specifications as to quality of materials and performance of equipment. Such
review shall not be construed as relieving the Contractor of the responsibility to
meet requirements of the Construction Contract Documents.
iirB A X T E R
4
WOODMAN
Consulting Engineers
Attachment A-1 2.
4. Review Test Reports
Review laboratory, shop and mill test reports of materials and equipment
furnished and installed by the Contractor.
5. Review Requests for Payment
Review the Contractor's requests for payments as construction work progresses,
and advise the CITY of the amounts due and payable to the Contractor in
accordance with the terms of the Construction Contract Documents.
6. Prepare Change Orders
Prepare Construction Contract Change Orders when authorized by the CITY.
7. Conduct Final Inspection
Conduct a final inspection of construction work, review the Contractor's written
guarantees, and issue an opinion of satisfactory completion for acceptance of the
PROJECT by the CITY.
8. Prepare Record Drawings
Prepare construction record drawings which show field measured dimensions of
the completed work which the ENGINEERS consider significant and provide the
CITY with one set of reproducible record drawings and all equipment operation
and maintenance manuals within ninety (90) days of the PROJECT completion.
9. Prepare 0 &M Manual
Prepare an operation and maintenance manual.
ADDITIONAL SERVICES
10. Extended Contract Time
Provide construction-related engineering services including, but not limited to,
General Construction Administration and Resident Project Representative
Services after the original construction contract final completion date for the
PROJECT.
BAXTER
1
WOODMAN
Consulting E•nginerrs
Attachment A-1 3.
11. Warranty Work
Provide construction-related engineering services regarding warranty work by the
Contractor after the PROJECT, or parts thereof, have been accepted for
operational use by the CITY. Such services will include, but not be limited to
assistance to the CITY in enforcing the Contractor's guaranty to repair or replace
defective work within the warranty time stated in the Construction Contract
Documents for the PROJECT.
H:\PROJ\ELGNC\990156\Attachment A-1 for ESA Amendment No.4.doc
B A X T E R
4111
WOODMAN
Constdling Engineers
CITY OF ELGIN,ILLINOIS
OTTER CREEK PUMPING STATION,INFLUENT SEWER,FORCE MAIN
AND BOWES ROAD INTERCEPTOR SEWER-UPSTREAM
ENGINEERING SERVICES AGREEMENT
AMENDMENT NO.4
ATTACHMENT C-3
MANPOWER REQUIREMENTS AND COSTS SUMMARY FOR CONSTRUCTION-RELATED SERVICES
OTTER CREEK PUMPING STATION PROJECT
ESTIMATED MANHOURS
Resident
Senior Project
Engineer Representative Technician Direct
DESCRIPTION @$40/hr @$32/hr @$25/hr Labor Cost
1. OTTER CREEK PUMPING STATION
A. Project Management 50 $2,000
B. Drafting,Record Drawings 60 $1,500
C. Normal Shop Drawing Review 400 $10,000
D. General Construction Administration
Construction Contract Documents 25 $1,000
Preconstruction Meeting 12 $480
Insurance 10 $400
Field Orders 40 $1,600
Pay Requests 96 $3,840
Review Test Results 6 $240
Periodic Progress Meetings 72 $2,304
Monitor Construction Schedule 4 $160
Notice of Acceptablility of Work 1 $40
E. Work Change Directives and Change Orders 40 $1,600
F. Construction Issues Investigations 40 $1,600
G. Construction Staking 10 $320
H. Field Observation,Full Time 1600 $51,200
I. Field Observation,Part Tiime 384 $12,288
J. Start-Up 40 $1,280
K. Operation and Maintenance Manual 40 $1,600
L. Milage $4,340
TOTAL DIRECT LABOR COSTS 364 2,106 460 $97,792
OVERHEAD @ 165% $161,357
PROFIT @ 10% $25,915
TOTAL ENGINEERING FEES $285,064
BAXTER
Attachment C-4 for ESA Amendment No.4 WOODMAN
Consulting Fri un errs
• C>
_;
City of Elgin Agenda Item No.
E
L , �« b, 0111
July 6, 2001 G �i
.
row Amendment No. 4-B&W -Otter Creek Lift Station
July 6, 2001
Page 2
A summary of the original contract and amendments with B&W are
shown below:
• Original Agreement (OCLS Design) $ 207, 000
• Amendment No. 1 (Design Scope Addition) $ 36, 492
• Amendment No. 2 (Design Scope Addition) $ 27, 338
• Amendment No. 3 (Design Scope Addition) $ 101, 380
• Proposed Amendment No.4 (Constr. Serv. ) : $ 285, 064 ,
Total $ 657, 274
EGAL IMPACT
\)\)10/
None.
ALTERNATIVES
None .
RECOMMENDATION
rik It is recommended that the City Council approve Amendment No. 4
with Baxter & Woodman in the amount of $285, 064 and authorize staff
to execute the necessary documents .
Respectfully submitted,
_t . \._, ,,,s 4L
Joyce'. Parker
City Manager
SP:do
Attachments
r
. f
r
LOCATION MAP
Otter Creek Sewage Pumping Station
A
N
4
Y-4/
BOWES ROAD
�V
Project 11, ,,j±m1=r(-,,z___
Location i___
,, , -g-iii \' rEi T
`-i' : pr-1 r---31 HgCLI
"PPS _ • 1 ROAD ^l
_ ,.sem' ���
J o • 00
- f&
• ct'ilc _ li r\217/
'- - \ CGSf (^ �
C�
dd D
I4��R
ay