HomeMy WebLinkAbout00-42 Resolution No. 00-42
RESOLUTION
AUTHORIZING EXECUTION OF AMENDMENT NO. 2 TO AN AGREEMENT WITH
BAXTER & WOODMAN, INC. FOR THE OTTER CREEK LIFT STATION
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY . OF ELGIN,
ILLINOIS, that Joyce A. Parker, City Manager, and Dolonna
Mecum, City Clerk, be and are hereby authorized and directed
to execute Amendment No. 2 to a Agreement on behalf of the
City of Elgin with Baxter & Woodman, Inc . for design services
for the Otter Creek Lift Station/Force Main Project, a copy of
which is attached hereto and made a part hereof by reference .
s/ Ed Schock
Ed Schock, Mayor
Presented: February 23 , 2000
Adopted: February 23 , 2000
Omnibus Vote : Yeas 6 Nays 0
Attest :
s/ Dolonna Mecum
Dolonna Mecum, City Clerk
CITY OF ELGIN, ILLINOIS
OTTER CREEK PUMPING STATION, FORCE MAIN
INFLUENT SEWER AND BOWES ROAD INTERCEPTOR SEWER-UPSTREAM
ENGINEERING SERVICES AGREEMENT
AMENDMENT NO. 2
THIS AGREEMENT AMENDMENT NO. 2 entered into this_ day of
2000,by and between the CITY OF ELGIN, an Illinois Municipal Corporation(hereinafter
referred to as "CITY"), and Baxter & Woodman, Inc., an Illinois Business Corporation
(hereinafter referred to as "ENGINEER"), shall modify that Agreement dated 14 September
1995, as amended by Amendment No. 1 dated 31 August 1998, whereby the ENGINEER
was engaged by CITY to perform certain professional services in connection with the
preparation of plans, specifications, estimates of cost, bidding and preconstruction award
services, and construction related engineering services for the Otter Creek Pumping Station,
Force Main, Influent Sewer and Bowes Road Interceptor Sewer-Upstream (hereinafter
referred to as "PROJECT").
WHEREAS, the services did not include additional design services to re-design the
pumping station site access road to locate the road within the Commonwealth Edison right-
of-way at Hopps Road,
AND
WHEREAS, the CITY desires the ENGINEER to provide final design services for
said access road revisions,
AND
WHEREAS, the services did not include bid assistance services to re-package the
Final Design Documents for the pumping station and re-bid the project,
AND
WHEREAS, the CITY desires the ENGINEER to provide bid assistance services
for said re-packaging and re-bidding of the pumping station project,
- 1 -
BAXTER
WOODMAN
Consulting Enginrrra
AND
WHEREAS, the services did not include evaluation of an alternative route for the
force main from the pumping station to the existing Bowes Road Interceptor Sewer,
AND
WHEREAS,the CITY desires the ENGINEER to provide alternative route evaluation
services for the force main,
AND
WHEREAS, the CITY desires to include the payments to the ENGINEER under the
Agreement in connection with the design of the access road revisions, the re-packaging and
re-bidding of the pumping station project, and the evaluation of the alternative route for the
force main.
In response to these additional services, certain revisions must be made to the
Agreement. In compliance, therefore, the terms and conditions of the Agreement are
modified as specifically set out below. All other parts of the Agreement remain unchanged.
SECTION I of the AGREEMENT, as amended by AMENDMENT NO. 1,is hereby
amended to replace Paragraphs A, B, C, D, E and F with the following Paragraphs A, B, C,
D, E, and F:
I. SCOPE OF SERVICES
A. All work hereunder shall be performed under the direction of the
Director of Public Works of the CITY, hereinafter referred to as the
"DIRECTOR".
B. The professional services to be provided by the ENGINEER under
this Agreement have been divided into two phases as follows:
1. Paragraphs C.1 through C.9 are funded under the lump sum
fee identified in Paragraph IV.A.
2. Paragraph D is funded under the not to exceed fee identified
in Paragraph IV.E.
C. In general, the initial professional services to be performed under this
Agreement will consist of the following.
B A X T E R
_•
WOODMAN
(wistdlin Eno w e)
1. Preparation of the Final Design Documents of the Otter Creek
Pumping Station. The pumping station shall be as described
in the Otter Creek Pumping Station - Preliminary Design
Report, prepared by the ENGINEER for the CITY and dated
October 1993, ENGINEER's Project No. 930630.
2. Preparation of revisions to the Final Design Documents of the
Otter Creek Pumping Station to accommodate an increase in
the 100-year flood elevation, ENGINEER's Project No.
930630.
3. Preparation of revisions to the Final Design Documents of the
Otter Creek Pumping Station to provide the architectural
treatment required by the Kane County Forest Preserve
District, ENGINEER's Project No. 930630.
4. Preparation of the Final Design Documents of the Otter Creek
Force Main. The force main shall extend from the Otter
Creek Pumping Station to the Bowes Road Interceptor Sewer
terminus manhole located at Randall Road approximately
1,250 feet south of Bowes Road, ENGINEER's Project No.
930849.
5. Preparation of the Final Design Documents of the Otter Creek
Pumping Station Influent Sewer. The influent sewer extends
approximately 1,400 feet from the Pumping Station site to the
confluence of Otter Creek and Fitchie Creek, ENGINEER's
Project No. 950510.
6. Preparation of the preliminary line and grade of the Bowes
Road Interceptor Sewer - Upstream. The interceptor sewer
extends from the Otter Creek Pumping Station Influent Sewer
approximately 17,500 feet along Otter Creek and Randall
Road to Sandy Creek located about 2,500 feet north of U.S.
Route 20, ENGINEER's Project No. 930850.
7. Performance of bidding and preconstruction award services
for the Otter Creek Pumping Station,Force Main and Influent
Sewer, consisting of the following:
- 3 - 6 A X T E R•
WOODMAN
Cons/thing/-4,44,,rims
a. Bid Document Printing
b. Bid Document Distribution
c. Pre-Bid Meetings
d. Bid Evaluations
e. Recommendation for Award
8. Preparation of revisions to the Final Design Documents of the
Otter Creek Pumping Station to locate the access road within
the Commonwealth Edison right-of-way at Hopps Road,
ENGINEER'S Project No. 980917.
9. Performance of bid assistance services to re-package and re-
bid the Otter Creek Pumping Station, ENGINEER's Project
No. 990155.
10. Performance of evaluation services to identify the costs,
advantages and disadvantages of an alternative route for the
force main from the pumping station to the existing Bowes
Road Interceptor Sewer. The route will extend from the
pumping station southerly along the entrance road to Hopps
Road, easterly along Hopps Road to Randall Road, and
northerly along Randall Road to the existing Bowes Road
Interceptor Sewer, ENGINEER's Project No. 991027.
D. All field construction phase services, including General Construction
Administration and Resident Project Representative, for the Otter
Creek Pumping Station, Force Main, Influent Sewer, and selected
start-up and operational services will be performed after an
amendment is authorized to this Agreement.
E. A detailed Scope of Services for the design, bidding and
preconstruction award services described in Paragraphs C.1, C.4, C.5,
C.7, C.8, C.9 and C.10 above is attached hereto as Attachment A.
F. A detailed Scope of Services for the additional design services
described in Paragraphs C.2 and C.3 above is attached hereto as
Attachment A-1.
- 4 - B A X T E 10;
4
WOODMAN
ConsultingLnginrrrs
SECTION IV of the AGREEMENT, as amended by AMENDMENT NO. 1, is
hereby amended to replace Paragraphs A,B, C,D, E, F and G with the following Paragraphs
A, B, C, D, E, F, G, H, I, J and K:
IV. PAYMENTS TO THE ENGINEER
A. The CITY shall reimburse the ENGINEER for professional services
described in Paragraphs I.C.1 through I.C.10, a lump sum of two
hundred and thirty-five thousand eight hundred and thirty dollars
($235,830), regardless of actual costs incurred by the ENGINEER
unless substantial modifications to the PROJECT are authorized in
writing by the CITY.
B. The CITY shall make periodic payments to the ENGINEER based
upon actual progress within thirty(30) days after receipt and approval
of invoice. The total value of said periodic payments to the
ENGINEER shall not exceed the amounts shown in the following
schedule, and the final payments for each task shall not be made until
the task is completed and accepted by the DIRECTOR.
Final Design Documents
Otter Creek Pumping Station $100,000
Force Main 20,000
Influent Sewer 25,000
Bowes Road Interceptor—Upstream 15,000
Subtotal $160,000
Additional Final Design Services
Re-design Pumping Station Site $ 10,392
Re-design Pumping Station Building 26,100
Re-design Pumping Station Access Road 12.678
Subtotal $ 49,170
Assistance During Bidding
Otter Creek Pumping Station $ 6,500
Re-package and Re-bid 8,660
Force Main 3,000
Influent Sewer 2,500
Subtotal $ 20,660
Evaluation of Alternative Force Main Route 6,000
Total $235,830
B A X T E R
- 5 - �.
WOODMAN
Consulting En�inrrrs
C. The ENGINEER shall make necessary arrangements and employ
qualified subconsultants for all geotechnical services, subject to
approval of the DIRECTOR, for the following work:
1. Geotechnical and soils investigations.
2. Wetlands delineation.
3. Plats of property and easement acquisition.
4. MFT project implementation.
The CITY shall reimburse the ENGINEER for the direct cost of the
above professional subconsultant services, an amount not to exceed
Forty-Five Thousand Dollars($45,000)without a modification to this
agreement by a change order or amendment.
D. The total payments by the CITY under this agreement under
paragraphs IV.A and IV.0 shall not exceed Two Hundred Eighty
Thousand Eight Hundred and Thirty Dollars ($280,830) unless this
agreement is modified by a change order or amendment.
E. For those services identified under the Scope of Services as Field
Construction Phase Services (Section I.D), the fee shall be negotiated
between the ENGINEER and the CITY, and this Agreement modified
by a change order or amendment, at such time prior to the
commencement of the work after a funding appropriation for the
project construction has been enacted by the CITY.
F. A detailed fee breakdown for the design,bidding and preconstruction
award services described in Paragraphs I.C.1, I.C.4, I.C.5, I.C.6 and
I.C.7 is attached hereto as Attachment C.
G. A detailed fee breakdown for the additional design services described
in Paragraphs I.C.2 and I.C.3 is attached hereto as Attachment C-1.
H. A detailed fee breakdown for the additional services described in
Paragraphs I.C.8, I.C.9 and I.C.10 is attached hereto as Attachment
C-2.
B A X T E R
WOODMAN
Cansulliv f_rip neliv
All other provisions of the AGREEMENT shall remain in full force and effect.
IN WITNESS WHEREOF, the undersigned have placed their hands and seals upon and
executed this Agreement in triplicate as though each copy hereof was an original and that
there are no other oral agreements that have not been reduced to writing in this statement.
For the CITY:
ATTEST: THE CITY OF ELGIN, ILLINOIS
By 64-14-1,42 B
City Clerk / City Manager
(SEAL)
For the ENGINEER:
fe‘ iP9y
Dated this:2E -day of • ea t. .- , A.D., 29@0.
ATTEST: BAXTER& WOODMAN, INC.
,2
/ �
By j(Gt� 17h 1 1--- By GZr� 7 - c
y, ,, y
Secretary President/CEO
(SEAL)
H:\PROJ\ELGNC\990156\AMENDMENT NO.2.doc
RWB:mk 12/22/99
B A X T E R
WOODMAN
Coesulii i g higin rn
CITY OF ELGIN
OTTER CREEK PUMPING STATION,INFLUENT SEWER,FORCE MAIN
BOWES ROAD INTERCEPTOR SEWER-UPSTREAM
ENGINEERING SERVICES AGREEMENT
AMENDMENT NO.2
ATTACHMENT C-2
RE-DESIGN PUMPING STATION ACCESS ROAD
HOURS PER EMPLOYEE CLASSIFICATION
PRINC. PROJECT PROJECT ELECT. TRAFFIC SURVEY TECH CADD SECR. TOTAL
MAN. ENGG. ENGG ENGG COST
MEETINGS AND PROJECT MANAGEMENT 14.25 10.5 $ 2,307.00
TOPOGRAPHICAL SURVEY 12.5 6 $ 942.00
CIVIL ENGINEERING 21.25 23.75 22.25 $ 4,995.50
ELECTRICAL ENGINEERING 2.5 $ 230.00
CADD GENERAL 64 $ 3,900.00
SECRETARIAL AND PRINTING 4 $ 170.50
SUBTOTAL $ 12,545
MILEAGE AND SUPPLIES $ 132.80
TOTAL AMOUNT $12,677.80
RE-PACKAGE AND RE-BID THE CONSTRUCTION CONTRACT
HOURS PER EMPLOYEE CLASSIFICATION
PRINC. PROJECT PROJECT ELECT. CONSTR. SURVEY TECH CADD SECR. TOTAL
MAN. ENGG. ENGG ENGG COST
MEETINGS AND PROJECT MANAGEMENT 8 4.25 $ 1,157.00
ASSISTANCE DURING BIDDING 33.75 0.25 0.5 2 $ 3,062.50
CIVIL ENGINEERING 17.75 $ 1,491.00
ELECTRICAL ENGINEERING 5 $ 390.00
CADD GENERAL 13.5 $ 873.00
SECRETARIAL AND PRINTING 29.25 $ 1,255.00
ADDENDUM PREPARATION 4.5 $ 378.00
SUBTOTAL
$ 8,606.50
MILEAGE AND SUPPLIES $ 53.55
TOTAL AMOUNT $ 8,660.05
EVALUATE ALTERNATIVE FORCE MAIN ROUTE
HOURS PER EMPLOYEE CLASSIFICATION
PRINC. PROJECT PROJECT ELECT. CONSTR. SURVEY TECH CADD SECR. TOTAL
MAN. ENGG. ENGG ENGG COST
MEETINGS AND PROJECT MANAGEMENT 4 4 $ 772.00
TOPOGRAPHICAL SURVEY 4 8 8 $ 1,400.00
CIVIL ENGINEERING 16 8 4 $ 2,256.00
ELECTRICAL ENGINEERING 4 $ 360.00
GADD GENERAL 16 $ 1,056.00
SECRETARIAL AND PRINTING 4 $ 176.00
SUBTOTAL
$ 6,020.00
MILEAGE AND SUPPLIES $ 70.00
TOTAL AMOUNT $ 6,090.00
105 88 62 90 88 63 68 66 44
•`,��OF-r(ci
� Agenda Item No.
At,,1 — City of Elgin
(0+14.4/LEW
January 28 , 2000
TO: Mayor and Members of the City Council
FROM: Joyce A. Parker, City Manager
SUBJECT: Amendment No. 2 to an Agreement with
Baxter & Woodman for the Otter Creek Lift
Station/Force Main Design Engineering
PURPOSE
The purpose of this memorandum is to provide the Mayor and Members
of the City Council with information to consider Amendment No. 2 to
an Agreement with Baxter & Woodman (B&W) for additional design
services for the Otter Creek Lift Station/Force Main Project .
BACKGROUND
"'' The original agreement with B&W ($207, 000) for the preparation of
final plans, specifications, cost estimates and bidding assistance
for the subject project was authorized by City Council August 23 ,
1995 . Amendment No. 1 added additional design services ($36, 492) to
accommodate changes in the flood plain elevations and the exterior
appearance of the building.
Amendment No. 2 in the amount of $27, 338 is for additional design
services to relocate the pumping station access road within
Commonwealth Edison right-of-way at Hopps Rd. , additional bidding
assistance provided to re-bid the project, and additional design
services to evaluate an alternative route for the force main.
The original access road design called for the City to obtain an
easement from a private property owner for access to Hopps Rd.
When it became apparent that the property owner was not willing to
grant an easement to the City, the location of the access road had
to be changed. Commonwealth Edison has agreed to grant access to
Hopps Rd. across their right-of-way. Although a formal agreement
with them has not yet been adopted, the Legal Department and
Engineering Division are very close to having it finalized and
ready for approval . This change in turn necessitated a redesign of
the access road.
In addition, an alternative route for the force main from the
pumping station to the existing Bowes Road Interceptor Sewer needs
to be evaluated. The City has been unable to obtain easements from
t . .I
Amndmnt No. 2 (B&W) /Otter Creek Lift Station
February 4, 2000
Page 2
potential developers have not proposed an alternate routing. This
evaluation will attempt to place the force main within public
property wherever possible . This amendment also includes
additional services provided by B&W to rebid the project . However,
because the contract was not awarded following the second bidding,
the project will have to be bid a third time . The actual costs
associated with this rebid will be included in the future amendment
for construction services .
A copy of Amendment No. 2 is attached as Exhibit A.
COMMUNITY GROUPS/INTERESTED PERSONS CONTACTED
None .
FINANCIAL IMPACT
Funds for engineering and construction are budgeted in account no.
395-4200-795 . 92-32 ($362 , 000) and account no. 396-4200-795 . 92-32
($2 , 950, 000) project no. 339505 . The original agreement with B&W
is in the amount of $207, 000 . Amendment No. 1 is in the amount of
$36, 492 . Amendment No. 2 will add $27, 338 to the agreement with B&W
rft. for a total not-to-exceed amount of $270, 830 .
IOW EGAL IMPACT
Agreement is being reviewed by the Legal Department.
ALTERNATIVES
None .
RECOMMENDATION
It is recommended that City Council approve Amendment No. 2 with
Baxter & Woodman in the amount of $27, 338, leaving a total not-to-
exceed fee with B&W of $270, 830, and authorize staff to execute the
amendment .
•ectfully sub ' ted,
41( a . -
Jd ce Parker
City Manager
SP:do
Attachment