RESOLUTION
AUTHORIZING EXECUTION OF ENGINEERING SERVICES AGREEMENT
AMENDMENT NO. 5 WITH BAXTER & WOODMAN, INC. FOR THE
TYLER CREEK INTERCEPTOR SEWER PHASE V AND PHASE VI
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF ELGIN,
ILLINOIS, that Joyce A. Parker, City Manager, and Dolonna
Mecum, City Clerk, be and are hereby authorized and directed
to execute an Engineering Services Agreement Amendment No . 5
on behalf of the City of Elgin with Baxter & Woodman, Inc . for
the Tyler Creek Interceptor Sewer Phase V and Phase VI , a copy
of which is attached hereto and made a part hereof by
reference .
s/ Ed Schock
Ed Schock, Mayor
Presented: January 12 , 2000
Adopted: January 12 , 2000
Omnibus Vote : Yeas 7 Nays 0
Attest :
s/ Dolonna Mecum
Dolonna Mecum, City Clerk
•
CITY OF ELGIN, ILLINOIS
TYLER CREEK INTERCEPTOR SEWER
PHASE V
ENGINEERING SERVICES AGREEMENT
AMENDMENT NO. 5
THIS AGREEMENT AMENDMENT NO. 5 entered into this_day of , 1999,
by and between the City of Elgin, an Illinois municipal corporation (hereinafter referred to
as the "CITY") and Baxter & Woodman, Inc., Consulting Engineers, an Illinois Business
Corporation, (hereinafter referred to as "ENGINEER"), shall modify that Agreement dated
27 March, 1997 and amended 2 September, 1997, 20 March, and 31 August, 1998, and 16
August, 1999, whereby the ENGINEER was engaged by the CITY to perform certain
professional services in connection with the preparation of plans, specifications, estimates
of cost, and construction related engineering services for the Tyler Creek Interceptor Sewer
- Phase V (hereinafter referred to as "PROJECT").
WHEREAS, the payment to the ENGINEER for construction related services for the
Tyler Creek Interceptor— Phase VI and the lateral sanitary sewer to serve a portion of the
area north of Big Timber Road, commonly known as the Chicago White Metal properties
was not included in the Agreement,
AND
WHEREAS, the CITY desires to include the payments to the ENGINEER to provide
construction administration, construction observation and quality control of the construction
phase for said interceptor sewer and lateral sewer.
In response to these additional services, certain revisions must be made to the
Agreement. In compliance, therefore, the terms and conditions of the Agreement are
modified as specifically set out below. All other parts of the Agreement remain unchanged.
SECTION IV of the AGREEMENT is hereby amended to replace Paragraph
B and C with the following:
B. The CITY shall reimburse the ENGINEER for professional services,provided
for the Interceptor Sewer— Phase VI as described in Paragraphs I.C.3 and
BAXTER
— 1 - Pr.
WOODMAN
rnulrrn�l., ,.
I.C.4,based on the ENGINEERS' hourly rates of compensation for work time
performed plus expenses.
1. The ENGINEERS' fee including travel and out-of-pocket expenses
shall not exceed $60,000, regardless of actual costs incurred by the
ENGINEER unless substantial modifications to the PROJECT are
authorized in writing by the CITY, ENGINEERS' Project No.
980040.
2. The CITY shall make periodic payments to the ENGINEER based
upon actual progress within thirty(30)days after receipt and approval
of invoice. The total value of said periodic payments to the
ENGINEER shall not exceed the amounts shown in the following
schedule, and the final payments for each task shall not be made until
the task is completed and accepted by the DIRECTOR.
Preliminary and Final Design Documents $55,000
Assistance During Bidding 5,000
Total $60,000
3. The ENGINEER shall make necessary arrangements and employ
qualified subconsultants, subject to approval of the DIRECTOR, for
the following work:
a. Geotechnical and soils investigations
b. Wetlands delineation and consultation
c. Registered Land Surveyor
d. Subsurface Investigator
The CITY shall reimburse the ENGINEER for the direct cost of the
professional subconsultant services, an amount not-to-exceed fifty-
two thousand ($52,000) dollars without a modification to this
Agreement by a change order or amendment, ENGINEERS' Project
No. 990040.01.
BAXTER
- 2 - IW%
WOODMAN
( .riwl'r rr�l rr�mrr
4. The total payments by the CITY under this Agreement for services
described in Paragraphs IV.B.1 and IV.B.3 shall not exceed one
hundred twelve thousand dollars ($112,000) unless this Agreement
is modified by a change order or amendment.
5. The ENGINEERS' fee for the construction related services for the
Tyler Creek Interceptor Sewer — Phase VI and the lateral sewer to
serve the Chicago White Metal properties shall be a reimbursement
for all actual direct employee compensation, overhead, and expenses
plus 14 percent of the sum of the direct costs, overhead, and non-
payroll expenses for readiness to serve and profit. The costs,
expenses and profit for such services are estimated not-to-exceed
$140,000, ENGINEERS' Project No. 991051.
6. The compensation for engineering services set forth in Paragraph 5
above does not include any overtime hours for Resident Project
Representatives. In the event the Contractor works more than eight
(8)hours on any weekday, or works any time on Saturdays, Sundays
or holidays, during which time Resident Project Representatives are
required to be present, the CITY shall pay the ENGINEERS extra
compensation at the ENGINEERS'hourly rates on a time-and-a-half
basis for all time of more than eight(8)hours on any weekday and all
time on Saturdays, and on a double time basis for all time on Sundays
and holidays. Note: The Supplementary Conditions of the
construction contract documents state that the CITY can deduct
overtime engineering costs from payments to the construction
contractor.
7. The compensation set forth in Paragraph 5 above does not include any
engineering services after the original construction contract
completion date for the PROJECT. In the event the CITY approves
and authorizes an extension of time for the Contractor to complete the
construction work, the compensation for engineering services set
forth in Paragraph E shall be increased for the additional services
required of the ENGINEERS. In the event the Contractor does not
complete the construction work within the contract completion time
including any extensions thereof granted by the CITY, the CITY shall
pay the ENGINEERS extra compensation at the ENGINEERS'hourly
rates until the PROJECT construction work has been accepted by the
CITY.
�B A X T E R
- 3 -
.
WOODMAN
roan/6,/ rrr
8. The compensation set forth in Paragraph 5 does not include any
engineering services regarding warranty work by the Contractor after
the PROJECT, or parts thereof, has been accepted for operational use
by the CITY. In the event that warranty work is required of the
Contractor, the CITY shall pay the ENGINEERS extra compensation
at the ENGINEERS'hourly rates to assist the CITY in enforcing the
Contractor's guaranty to repair or replace defective work within the
warranty time stated in the Construction Contract Documents.
C. Summary of fees:
I. Tyler Creek Interceptor Sewer—Phase V
Design and Bidding Services
Engineering Fees $ 90,000
Subconsultants 70,000
Subtotal $160,000
Construction Services $180,000
Total $340,000
2. Tyler Creek Interceptor Sewer—Phase VI
Design and Bidding Services
Engineering Fees $ 60,000
Subconsultants $ 52,000
Subtotal $112,000
Construction Services $140,000
Total $252,000
BAXTER
- 4 - Wi_
WOODMAN
All other provisions of the Agreement shall remain in full force and effect.
IN WITNESS WHEREOF, the undersigned have placed their hands and seals upon
and executed this Agreement in triplicate as though each copy hereof was an original and that
there are no other oral agreements that have not been reduced to writing in this statement.
For the CITY:
ATTEST: THE CITY OF ELGIN, ILLINOIS
By5-irt4zt--,-1( <` Gl/�� By .�L..40 &� s
City Clerk Ci 1 Manager
(SEAL)
For the ENGINEER:
Dated this 2nd day of December, A.D., 1999.
ATTEST: BAXTER & WOODMAN, INC.
--B
—
By��Cdr t� �� ` By 4 =- �z�->
Deputy Secr ary President/CEO
(SEAL)
12/2)99
DRG cf
H PROJELGNC 991051 AMENDMENT NO 5 doc
BAXTER
WOOD M A N
1 OF E,C _ \
Agenda Item No.
City of Elgin
n
°R4TCD( 5_.
December 15, 1999
TO: Mayor and Members of the City Council
FROM: Joyce A. Parker, City Manager
SUBJECT: Amendment No. 5 to an Agreement with Baxter & Woodman
for the Tyler Creek Interceptor Sewer - Phase V/
Phase VI (TCIS-V/VI)
PURPOSE
The purpose of this memorandum is to provide the Mayor and members
of the City Council with information to consider Amendment No. 5 to
an agreement with Baxter & Woodman for construction-related
engineering inspection services for the TCIS VI Project .
BACKGROUND
At its meeting on March 5, 1997 , the City Council authorized an
agreement with Baxter & Woodman for the preparation of plans,
specifications, estimates of cost and bidding engineering services
for the TCIS-V project . Amendment No. 1 for additional design
services for TCIS-V, Amendment No. 2 for design services for TCIS-
VI, Amendment No. 3 for construction engineering services for TCIS-
V and Amendment No. 4 for design services for the Chicago White
Metal (CWM) lateral sanitary sewer were added at subsequent meetings.
Amendment No. 5 will add construction engineering services to the
agreement with Baxter & Woodman for the TCIS-VI project and the
Chicago White Metal lateral sanitary sewer. The cost for
inspection services for the lateral sanitary sewer will be paid by
Chicago White Metal. These funds will be deposited directly to the
City. A copy of Amendment No. 5 is attached as Exhibit A.
The award of the contract for construction of the TCIS-VI project
is included on the regular agenda.
COMMUNITY GROUPS/INTERESTED PERSONS CONTACTED
None.
rk. Amendment Number 5 with Baxter & Woodman
December 15, 1999
Page 2
FINANCIAL IMPACT
Amendment No. 5 totals $140, 000 and covers construction-related
fees for the TCIS-VI project and the Chicago White Metal lateral
sanitary sewer. The Chicago White Metal portion for the lateral
sanitary sewer is $20, 000 and these funds will be deposited by
Chicago White Metal in account number 399-0000-605 . 52-00 prior to
City Council approval . Monies for this facet of the TCIS-VI sewer
are budgeted in account number 399-4200-795 . 92-41, project number
339584 (sewer portion of the 1999 Bond Sale) . The City portion for
construction inspection services will total $120, 000 .
A summary of the original contract and amendment with Baxter &
Woodman are stated below:
. Original Agreement (TCIS-V Design) $164 , 000
. Amendment No. 1 (Design Scope Addition 16, 000
TCIS-V)
. Amendment No. 2 (Design Scope Reduction - (20 , 000)
TCIS-V)
. Amendment No. 2 (TCIS-VI Design) 98, 000
. Amendment No. 3 (TCIS-V Construction 180, 000
Services)
. Amendment No. 4 (Chicago White Metal 14 , 000
Sewer Design)
. Proposed Amendment No. 5 (TCIS-VI/Chicago 140, 000
White Metal
Constr. Services)
TOTAL $592 , 000
LEGAL IMPACT
Yf Jul
None.
ALTERNATIVES
None .
RECOMMENDATION
It is recommended that City Council approve Amendment No. 5 in the
amount of $140, 000 with Baxter & Woodman and authorize staff to
execute the necessary documents .