RESOLUTION
ADOPTING A MINING PLAN FOR 1994 FOR THE ELGIN SPORTS COMPLEX
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY -OF ELGIN,
ILLINOIS, that it hereby adopts- the• -Mi-n1ng Plan for 1994 for
the Elgin Sports Complex prepared by Road Materials
Corporation, a copy of which is- attached- hereto.
sl George VanDeVoorde
George VanDeVoorde, Mayor
Presented: April 27, 1994
Adopted: April 27, 1994
Omnibus Vote: Yeas 6 Nays 0
Attest:
sl Dolonna Mecum
Dolonna Mecum, City Clerk
Lt_ .cE—ROUTE 68 8 PENNY ROAD CORPORATE OFFICE ELBURN—LORANG 6 MAIN STREET
708-426-3732 ALGONQUIN 708-557-2396
ELGIN—S.ROUTE 31 708458-4541 MARENGO—S.ROUTE 23
708 931.1552 815-588-5554
Road Materials Corporation
P.O. BOX 609
ALGONQUIN, ILLINOIS 60102-0609
Mining Plan for 1994
Hopefully the addendum to the original mining agree-
ment will be approved at the city council meeting in March,
1994. If this happens, we will start the stripping operation
as soon as the frost in the ground becomes manageable, which
won ' t be long. Most of the planning has already been done
so this will not cause any delay . The removal of the gas
line is also critical . Northern Illinois Gas Company has
most of their planning done and are awaiting the approval
to proceed along with the $22 ,000 check to pay for this
work. We will give them the approval to proceed and the
• check immediately after we receive the approval from the
city council.
The stripping operation will begin in cell one (draw-
ing attached) , and then continue into cell two. This has
been the plan from the very beginning for many reasons ,
such as the location of the crushing plant , the need to
build the reservoir and the location of the FAA building.
Also, considering that three months. have disappeared al
ready, this is very important to all concerned to get the
crushing operation and sales going as quick as possible.
Because the quantity of earth stripping is so large, we
cannot pin down an exact time the crushing will actually
start . The crushing will begin in cell one for 1994 and
part of 1995 , and then continue into cell two. . The crush- .
ing plant will be under construction very soon and we will
be ready when the stripping is ready. Our guesstimate at '
• this time is to start crushing in September. or October.
PROCESSORS OF ALL TYPES OF SAND AM GRAVEL PRODUCTS
Soon after the initial stripping operation is under
way, we will also start the stripping and construction of
the soccer fields . The earth material needed for this area
will be removed from cells ten and eleven. Here again, the
quantity of earth needed to construct the soccer fields is
very large, approximately 700, 000 cubic yards, so we cannot
pin down an exact time this work will be completed. We under-
stand there are time constraints on the construction of these
fields , so we will expend a great effort to get this work
done as soon as . possible. What is really needed is a mild
winter so the stripping operation can continue through the
winter months . The plan at this time is to start on the
four north fields first because they require substantially
less work than the south fields .
Because this is the start-up stage, no reclamation
work will be done in 1994 .
•
WMIrc
Page Two -
EXTENT OF OVERBURDEN REMOVAL
11
CEMETER 1 U
Otto
5
9
•
•
Q
3 7
6
A. BOTTOM OF 2
A WILL BE
TEMPORAR Y ONVEY ORS
1 '
PRODUCTION
TIO
N
EQUIPMENT
Q MENT
ELGIN
MAINTENANCE
x
:Y
BUILDING ---��
>'