RESOLUTION
APPROVING CHANGE ORDER NO. 3 IN THE CONTRACT WITH
DAHLQUIST AND LUTZOW ARCHITECTS, LTD. FOR THE
LORD' S PARK PAVILION
WHEREAS, the City of Elgin has heretofore entered into a
contract with Dahlquist and Lutzow Architects, Ltd. for the
Lord' s Park Pavilion; and
WHEREAS, it is necessary and desirable to modify the
terms of the contract as is described in Change Order No. 3,
attached hereto.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE
CITY OF ELGIN, ILLINOIS, that Larry L. Rice, City Manager, be
and is hereby authorized and directed to execute Change Order
No. 3, a copy of which is attached hereto and made a part
hereof by reference.
s/ George VanDeVoorde
George VanDeVoorde, Mayor
Presented: April 14, 1993
Adopted: April 14, 1993
Omnibus Vote: Yeas 6 Nays 0
Recorded:
Attest:
s/ Dolonna Mecum
Dolonna Mecum, City Clerk
ELGIN, ILLINOIS -
RENOVATION OF THE LORD'S PARK PAVILION
FEE ADJUSTMENT NO. 3 FOR CHANGE ORDERS NO. 2, 3, 4, 5 and 6 AND
FIELD SUPERVISION/COORDINATION OF THE SECURITY/FIRE ALARM SYSTEM
(UNDER SEPARATE CONTRACT) .
SCOPE: This Fee Adjustment No. 3 covers additional work
required to complete the preparation of plans for
subsequent construction administration for the
renovation of the Lord's Park Pavilion.
The Architect for this project is Dahlquist and Lutzow
Architects, Ltd. , of Elgin, Illinois.
REASONS FOR CHANGE: This Fee Adjustment is required for the
costs associated with the items requested by the staff to
complete the following work. The extra work contemplated in
this change order was unforeseen but brought about by the
conditions uncovered as the design work continued:
Change Order No. 2 :
1. Support the existing wood beams under the round porch with
steel beams. Add joist hangers to all existing notched
floor joists in this area.
2 . Remove four existing columns in the meeting rooms in the
lower level, enlarge footings and replace the existing wood
beams with steel beams.
3 . Additional floor joists are required and extra solid wood
blocking is needed between floor joists.
4. Substitute the electrical switch gear to another
manufacturer previously not specified.
5. Sewer system has been redesigned.
6. Replace the windows in the lower level masonry wall.
Change Order No. 3 :
7. Delete the emergency fire service for the elevator. Provide
an enameled elevator door in lieu of plastic laminate.
8. Provide new door frames and trim for Doors 1 and 2 .
9 . Revision of door hardware.
10. Removal of the existing rubble stone wall adjacent to the
relocated Elevator Equipment Room. The scope of work
included removal of the existing wall, cutting the existing
concrete floor slab, pouring a new concrete footing and
floor, and laying up a new masonry wall.
11. The installation of curbs, planters, and- paving patches on
the east side of the Pavilion. This will provide for a
landscape buffer from the driveway on the east side of the
building and provide protection at the bottom of the ramp
leading up to the main level of the Pavilion. This is the
logical time to do this work since it eliminates tearing out
of new work when the landscape surrounding the Pavilion is
designed.
12. Relocate telephone conduit stubbed into the floor to the new
telephone board location. This is related to the
elimination of the interior stair previously discussed.
13 . Construct a concrete retaining wall beneath the transformer
pad on the south side of the Pavilion. This is a result of
field conditions relative to the existing grades.
14. Provide additional bathroom partitions as requested by the
Parks and Recreation Department. The additional screens
provide for further privacy in the bathrooms.
15. Remove the exposed toilet vent from the north meeting room
and conceal it in the wall. This eliminates the viewing of
a unsightly intrusion.
16. Replace rotten floor joists over the Room 101.
17 . Replace rotten wood base along the floor in Room 101.
Change Order No. 4 :
18. Removal of a deteriorated portion of the stone wall in the
Basement between the elevator and the toilets.
19. Revision of Toilet accessories and amenities.
20. Provided additional exterior receptacles around the porch.
21. Remove the existing concrete retaining wall at the north end
of the Pavilion and the adjacent sidewalk.
22. Installation of below grade roof drainage piping around the
Pavilion on all sides.
23 . Removal of weathered and previously damaged porch deck
around the exterior of the Pavilion.
24. Structural repairs required to brace and straighten the
roofs of the north and south wings.
25. Relocation of the downspout drainage of the round roof on
the west side of the Pavilion. This involves tearoff and
rebuilding the roof and patching/repair of the fascia to
accommodate the revised drainage. This work also includes
related clapboard siding replacement. The City staff and
the Architect requested this change in the roof system to
accommodate the roof runoff in a more efficient and
aesthetic manner.
Chance Order No. 5:
26. Additional wainscoting required in the lower level.
27. Substitution of vinyl base in lieu of wood base in the lower
level.
28. Round roof repairs.
29 . Handrails at exterior stairs.
30. Reframe pocket door openings to plumb door openings.
31. Structural revision of the North end stairs.
32 . Flashing of the existing cupola base.
33 . Additional insulation required at overhead doors in the
north and south winds and portions of the east wall.
34. Replumb exterior exit doors.
35. Additional structural framing at the cupola.
36. Ceiling repairs in all upper rooms.
37. Additional waterproofing installation on exposed parts of
porch deck.
38. Additional labor for hardwood floor nailing.
Change Order No. 6:
39. Additional hardware equipment was required to be substituted
to complete the full operation of the doors.
40. Replacement of porch deck in the south east corner.
41. Porch deck replacement under columns (two separate
occasions) .
42 . Level floor in the round warming room.
43 . Install fan relay shut down switches.
44. Replacement of cracked stained glass.
45. Replace the sprinkler system flow switch.
46. Additional work on round roof.
Additional Work Not Per Contract:
47. Supervision and coordination of the security and fire
alarm. The security and fire alarm system was purchased and
installed by a separate contract.
SUMMARY OF CHANGES IN CONTRACT AMOUNT: The amount of the
contract will be revised as follows:
CHANGE ORDER NO. 2
ITEM COST CHANGE
Item #1 ADD $ 3,900.00
Item #2 ADD $ 6,797.00
Item #3 ADD $ 5,972 . 00
Item #4 DEDUCT ($ 500.00)
Item #5 DEDUCT ($ 595. 00)
Item #6 ADD $ 2 ,864. 00
SUBTOTAL $ 18,438.00
CHANGE ORDER NO. 3
ITEM COST CHANGE
Item #7 DELETE ($ 825.00)
Item #8 ADD $ 420.00
Item #9 DELETE ($ 102.00)
Item #10 ADD $ 1,484. 00
Item #11 ADD $ 5,499.00
Item #12 ADD $ 683 . 00
Item #13 ADD $ 1, 014. 00
Item #14 ADD $ 531. 00
Item #15 ADD $ 679.00
Item #16 ADD $ 547.00
Item #17 ADD $ 524.00
SUBTOTAL $ 10,454. 00
CHANGE ORDER NO. 4
ITEM COST CHANGE
Item #18 ADD $ 6,706. 00
Item #19 ADD $ 3 ,432 .00
Item #20 ADD $ 3 ,570.00
Item #21 ADD $ 1,996.00
Item #22 ADD $ 4,377.00
Item #23 ADD $ 459.00
Item #24 ADD $70,510.00
Item #25 ADD $ 3 ,846.00
SUBTOTAL $ 94,896. 00
CHANGE ORDER NO. 5
ITEM COST CHANGE
Item #26 ADD $ 69. 00
Item #27 DEDUCT ($ 193 .00)
Item #28 ADD $ 6, 305. 00
Item #29 ADD $ 1,389.00
Item #30 ADD $ 909. 00
Item #31 ADD $ 1, 525. 00
Item #32 ADD $ 1,254.00
Item #33 ADD $ 1,212 . 00
Item #34 ADD $ 2, 231. 00
Item #35 ADD $ 1,024. 00
Item #36 ADD $ 7,000.00
Item #37 ADD $ 405. 00
Item #38 ADD $ 528. 00
SUBTOTAL $ 23, 658. 00
CHANGE ORDER NO. 6
ITEM COST CHANGE
Item #39 ADD $ 1, 394 . 00
Item #40 ADD $ 1, 138. 00
Item #41 ADD $ 357.00
Item #42 ADD $ 1, 150. 00
Item #43 ADD $ 2, 520. 00
Item #44 ADD $ 458. 00
Item #45 ADD $ 445.00
Item #46 ADD $ 542 . 00
SUBTOTAL $ 8, 004.00
SUBTOTAL - ITEMS 1 - 46: $155,450. 00
ITEM COST CHANGE
Item #47 ADD $ 2 ,475.00
Total Costs of All Changes
Items 1 - 46 ($155,450 x 8-1/2%) = $ 13 , 213 .00
Item #47: $ 2, 475. 00
TOTAL COST: $ 15, 688. 00
The Contract states the fee for this work shall be calculated as
8-1/2% of the cost of construction. The additional work, not in
this contract, is based on an hourly fee.
The present contract with Dahlquist and Lutzow Architects, Ltd.
is for $81,997.38. By reason of the Fee Adjustment No. 3, the
Contract for the Renovation of the Lord's Park Pavilion will be
increased in the amount of Fifteen Thousand Six Hundred
Eighty-eight and 00/100 Dollars ($15, 688. 00) , the total contract
value being Ninety Seven Thousand Six Hundred Eighty-five and
38/100 Dollars ($97, 685. 38) .
Other Contract Provisions: All other contract provisions shall
remain the same.
Agreed to this /S-Y4 day of CUly..
� , 1993 .
Recommended:
PARKS DEP: 'TMENT
BY:
;
Date: Z3
Accepted:
DAHLQUIST AND LUTZOW ARCHITECTS, LTD.
Party of the Second Part (Architect)
By: 44zir-c. 12J
Title: A�C-SIDF.T
Date: 3/a/4.2.
Approved:
CITY OF ELGIN
Party of the Fi Part (Owner)
By:
Title: ch i / fru
Date: YA/9 3
Elm n
' OF f Agenda Item No.
„_,,,
March 17, 1993
TO: Mayor and Members of the City Council
FROM: Larry L. Rice, City Manager
SUBJECT: Change Order No. 3 to the Contract With
Dahlquist and Lutzow
PURPOSE
This memorandum will provide the Mayor and City Council
with information to consider Change Order No. 3 to the con-
tract with Dahlquist and Lutzow Architects, Ltd. for architec-
tural services involving the Lords Park Pavilion.
BACKGROUND
Architects Dahlquist and Lutzow prepared plans and speci-
fications for the remodeling of the Lords Park Pavilion.
Subsequently a contract was awarded to Elgin Builders for the
construction work which has now been substantially completed.
During the rehabilitation work, several unforeseen condi-
tions were exposed which resulted in additional design work
by the architects and Change Orders in the contract with
Elgin Builders . The contract with Dahlquist and Lutzow pro-
vides that the architects are entitled to additional compensa-
tion based on 8 1/2 percent of changes in construction
costs. The attached Change Order No. 3 covers the Change Or-
ders No. 2 through 6 to the contract of Elgin Builders, plus
supervision and coordination of the installation of the Pavil-
ion's security and fire alarm system. The above Change Or-
ders with Elgin Builders resulted in an increase in the con-
struction cost of $155,450. The architect's fee for the work
involved in these Change Orders is calculated to be $13,213.
With the additional charge for the alarm system work, the
total amount of additional compensation due the architects is
$15,688.
FINANCIAL IMPACT
Change Order No. 3 to the contract with Dahlquist and
Lutzow will result in an additional design fee of $15,688.
Mayor and Members of the City Council
March 17, 1993
Page 2
r
There are sufficient funds available in the project budget to
cover the above payment.
RECOMMENDATION
It is recommended staff be directed to prepare a resolu-
tion authorizing the execution of Change Order No. 3 to the
contract with Dahlquist and Lutzow.
Larry ,L Rice, Ci Manager
LLR:daw
Attachment