HomeMy WebLinkAbout88-0727 GF Structures Corp ELGIN, ILLINOIS
LORD'S PARK MIDDLE DAM
CHANGE ORDER NO. 1
SCOPE: This Change Order No . 1 covers the additional
concrete required to complete the side walls of the
middle dam underneath the foot bridge at Lord ' s Park .
The general contractor operating under contract to the
City of Elgin is G. F. Structures Corp . of Dundee,
Illinois 60118-0279.
REASONS FOR CHANGE: This change order is required in order
to complete the proposed improvement at the middle dam site.
Engineering staff noticed that after the site was dredged ,
the existing flagstone wall conditions differed from the
prepared plan. Instead of a straight vertical wall , the
bottom of the wall extended out at the base to serve as a
footing . Since there were no original construction plans for
the site, this condition was discovered after the excavation
at the site.
In addition, the condition of the flagstone wall was poor and
any breaking off or cutting of the protruding flagstone could
result in the wall collapsing . Therefore, the design was
altered to compensate for a wider base of the 10" concrete
wall . The new design provides a slanted wall extending out
at the base and tapering in towards the top of the wall . The
contractor , G. F. Structures, proposed that this work would be
done at a cost of the additional concrete to complete this
work..
SUMMARY OF CHANGES IN CONTRACT AMOUNT: The amount of the contract
will be revised as follows:
ITEM ADD
10" Concrete Walls; Cubic Yard $4,699.50
7.23 cubic yards a $650.00
DEDUCT
Dowels Across Cracks $ 40.00
2 each a $20.00
The present contract with G. F. Structures Corp . is for
$59,597.50. By reason of this Change Order No . 1 , the contract
for the Lord 's Park Middle Dam will be increased in the
amount of Four Thousand Six Hundred Fifty-Nine and 50/100 Dollars
($4,659.50) , the total contract value being Sixty-Four Thousand
Two Hundred Fifty-Seven and 00/100 Dollars ($64,257.00) .
F
CHANGE ORDER NO. 1
July 1 , 1988
Page 2
OTHER CONTRACT PROVISIONS: All other contract provisions shall
remain the same.
Agreed to this c 7 day of (TVt41 , 1988.
Recommended:
ENGINEERING DIVISIO
411111)111111111."1111. IffilL
Date: l 1,
Accepted:
G. F. STRU RES CORP.
Party of = d - (, , , tractor )
/ / / ,/
By: / ,,.� IAlik / -
Title: • ./1)/
Qom'
Date: /0/ /- i✓�
Approved:
CITY OF ELGIN
Party of the First Part (Owner )
By:: 4 ,t,A.t.g '„2fZ36
Title: )t--1
Date: 7`� '`.. /.7. 3
July 6 , 1988
MEMORANDUM
TO: Mayor and Members of the City Council
FROM: City Manager
SUBJECT: Lord' s Park Middle Dam
Contract Change Order #1
PURPOSE: This memorandum will provide the Mayor and Council
with information to consider the subject Change Order.
BACKGROUND: The City Council awarded the Lord' s Park Middle Dam
Rehabilitation project to G.F. Structures at the Council meeting
on September 9 , 1987 .
This Change Order is required in order to complete the proposed
improvement at the middle dam site. Engineering staff noticed
that after the site was dredged, the existing flagstone wall
conditions differed from the prepared plan. Instead of a
straight vertical wall, the bottom of the wall extended out at
the base to serve as a footing. Since there were no original
construction plans for the site, this condition was discovered
after the excavation at the site.
In addition, the condition of the flagstone wall was poor and
any breaking off or cutting of the protruding flagstone could
result in the wall collapsing. Therefore , the design was
altered to compensate for a wider base of the 10 inch concrete
wall. The new design provides for a slanted wall extending out
at the base and tapering in towards the top of the wall. The
contractor, G.F. Structures, proposed that this additional work
would be done at the unit cost for, 10 inch concrete walls, to
complete this work.
The work for the rehabilitation of the middle dam has already
been completed. If the additional quantity of concrete for the
new walls was not used, the project would not have been able to
be completed.
FINANCIAL IMPACT: The original awarded contract was in the
amount of $59 ,597 . 50 . By reason of this Change Order No. 1 , the
contract will be increased in the amount of $4 ,659 .50 , for a
total estimated cost of $64 ,257 .00 . The additional funds to
cover the cost of this change order can come from the savings
16 ,370 .00) resulted from the Lord' s Park Lagoon Dredging
projtect which was completed at a cost of 22% under the budgeted
amount of $75 ,000 .00 . A copy of the Change Order is attached
for your consideration.
Mayor and Members of
the City Council
July 6 , 1988
Page 2
RECOMMENDATION: It is recommended that the City Council approve
this Contract Change Order No. 1 to G.F. Structures Corporation
in the amount of $4 ,699 .50 for the Lord' s Park Middle Dam
project.
Ai
O-Fes J. C•ok City Manager
ELGIN, ILLINOIS
LORD'S PARK MIDDLE DAM
CHANGE ORDER NO. 1
SCOPE: This Change Order No. 1 covers the additional
concrete required to complete the side walls of the
middle dam underneath the foot bridge at Lord 's Park .
The general contractor operating under contract to the
City of Elgin is G. F. Structures Corp. of Dundee,
Illinois 60118-0279.
REASONS FOR CHANGE: This change order is required in order
to complete the proposed improvement at the middle dam site.
Engineering staff noticed that after the site was dredged,
the existing flagstone wall conditions differed from the
prepared plan. Instead of a straight vertical wall , the
bottom of the wall extended out at the base to serve as a
footing . Since there were no original construction plans for
the site, this condition was discovered after the excavation
at the site.
In addition, the condition of the flagstone wall was poor and
any breaking off or cutting of the protruding flagstone could
result in the wall collapsing. Therefore, the design was
altered to compensate for a wider base of the 10" concrete
wall . The new design provides a slanted wall extending out
at the base and tapering in towards the top of the wall . The
contractor , G. F. Structures, proposed that this work would be
done at a cost of the additional concrete to complete this
work .
SUMMARY OF CHANGES IN CONTRACT AMOUNT: The amount of the contract
will be revised as follows:
ITEM ADD
10" Concrete Walls; Cubic Yard $4,699.50
7.23 cubic yards a $650.00
DEDUCT
Dowels Across Cracks $ 40.00
2 each a $20.00
The present contract with G. F. Structures Corp . is for
$59,597.50. By reason of this Change Order No. 1 , the contract
for the Lord ' s Park Middle Dam will be increased in the
amount of Four Thousand Six Hundred Fifty-Nine and 50/100 Dollars
($4,659.50) , the total contract value being Sixty-Four Thousand
Two Hundred Fifty-Seven and 00/100 Dollars ($64,257.00) .
• CHANGE ORDER NO. 1
July 1 , 1988
Page 2
OTHER CONTRACT PROVISIONS: All other contract provisions shall
remain the same.
Agreed to this day of , 1988.
Recommended :
ENGINEERING DIVISION
/I ' ./ Ia /I .J
Date: J l la46
Accepted:
G. F. STRUCTURES CORP.
Party of the Second Part (Contractor )
By:
Title:
Date:
Approved:
CITY OF ELGIN
Party of the First Part (Owner )
By:
Title:
Date:
May 18 , 1988
MEMORANDUM
TO: Mayor and Members of the City Council
FROM: City Manager
SUBJECT: Lord' s Park Middle Dam
PURPOSE: This memorandum will provide the Mayor and Council
with an update on the subject project.
BACKGROUND: As earlier presented to the City Council in execu-
tive session on April 26 , 1988 , there were concerns in regards
to the quality of some concrete work. These concerns were
expressed to the contractor along with a request to correct the
situation.
The contractor, G.F. Structures, hired a private testing company
which took five core samples from the concrete wall which had
severe honeycombing. The contractor met with City staff on May
4 , 1988 and presented the results of the tests for review.
These tests indicated that the concrete wall was not constructed
as specified. The test results revealed that the honeycombing
(lack of consolidation) extended through the outer six (6)
inches of the wall. Also, it was revealed that the honeycombing
was along some of the reinforcement steel and that some of the
steel, both grids , were located in the outer six inches of the
wall. Repair of the honeycombing will not produce a satisfacto-
ry wall.
G.F. Structures was notified that they are required to remove
and replace the wall . Also, a new footing shall be constructed
on top of the existing footing. This new footing shall be
constructed as specified on the project plans. The new
footings are complete , construction will progress to the con-
crete walls.
FINANCIAL IMPACT: Once the work which was included on the first
pay estimate is completed and approved, we shall issue the first
payment to G.F. Structures. All other payments to the contrac-
tor will be made as satisfactory work has been completed.
CONCLUSION: Now that work has continued on the project, there
will be increased inspection on the job and all completed work
will be approved prior to progressing with the next stage . It
is anticipated that construction should be completed within five
weeks .
40111F es J. i •k, City Manager
GF. Structures Corp. d , , ,
P.O. Box 279 • Dundee, IL 60118-0279 • 312/669-3676
May 10, 1988
CERTIFIED MAIL
RETURN RECEIPT REQUESTED
City of Elgin
150 Dexter Court
Elgin, Illinois 60120-5555
Attention Mr. Melford A. Dahl, P.E.
Dear Mr. Dahl: Re: Lords Park - Middle Dam
Relative to your letter dated May 6, 1988, G. F. Structures Corporation
will begin removing the existing forms on May 13, 1988, in order to
remove the existing poured in pla retaining wall and then begin to
construct a new footing on the existing one. This is all in accordance
with your letter as mentioned above.
We are sorry for the inconvenience that we have caused you and I assure
you that this project will be completed in a timely manner.
Very truly yours,
G. F', 1% k ' S C• 9RATI0N
/ ��
'ichard C. Cran.all, Jr.
President
1111?1g2ElY -1) ;Id
MRr 1 ;,:_
CITY OF ELGIN
ENGINEERING DEFT.
April 27 , 1988
MEMORANDUM
TO: Mayor and Members of the City Council
FROM: City Manager
SUBJECT: Lord' s Park Middle Dam Renovations
PURPOSE: This memorandum will provide the Mayor and Council
with an update on the construction delays with the subject
project.
BACKGROUND: G. F. Structures Corporation of Dundee, Illinois, is
the contractor performing the renovations at the Lord' s Park
middle dam. This work mainly involves the pouring of new steel
reinforced concrete footings , walls and wingwalls . This project
is located between the upper and lower lagoons at the park and
will be affected constantly by the water flow between the
lagoons.
On April 11 , 1988 , the City staff became aware that the rein-
forcement steel apparently had not been installed as specified
in the plans for the project. During an indepth inspection, it
was discovered that the specified reinforcement steel was not
used and that the one concrete wall that was poured had severe
honeycombing.
This honeycomb condition resulted from the lack of use of a
concrete vibrator during the concrete pour. The vibrator
agitates the concrete and minimizes the voids in the concrete.
Upon seeing these unconformities with the project, work was
stopped and a meeting was called with G.F. Structures to discuss
the construction conditions . Members of G.F. Structures met
with City staff on April 12 , 1988 , and stated that all reinforc-
ing steel was properly located, but one of the specified bar
types was not of the proper width. The staff requested the
contractor to remove a section of the poured footing to expose
the steel so we could determine if the steel was properly
located and of the type specified and the contractor agreed.
After one week of not breaking open the footing, the contractor
again met with City staff on April 18 , 1988 and stated that the
bars used were not the correct ones as previously stated. It
was decided at this meeting that the design engineer from
Donohue and Associates would be contacted with respect to
developing an adjusted wall and footing design which shall meet
the requirements of the project. G.F. Structures would hire
their own structural engineer and testing services to complete
the study of the existing wall and footings.
Mayor and Members of
the City Council
April 27 , 1988
Page 2
A private testing company was onsite on April 22 , 1988 to take
five core samples from the concrete wall. These samples will be
inspected and tested to determine the condition of the wall and
a report will be made available to the City and Donohue and
Associates for review.
FINANCIAL IMPACT: The first payment to the contractor for this
project has been processed, but the payment is being held until
the unconformities of this project are rectified to the satis-
faction of the Engineering Division.
CONCLUSION: It is the opinion of the staff that the poured
concrete wall be removed because of the servere honeycombing and
improper placement of the reinforcing steel which we feel will
be verified by the test work. The condition of the footings and
any recommended design changes will be reviewed by the staff and
implemented as necessary. Periodic reports will be made to the
City Council regarding the progress and status of the project.
/!
. . . -s J. Coo City Manager