HomeMy WebLinkAbout88-0225 Plote • gg- oaaS
EXCAVATION AND/OR DREDGING OF
LOWER LAGOON AT LORD'S PARK
ELGIN, ILLINOIS
CHANGE ORDER NO. 1
SCOPE' This Change Order No . 1 covers the dredging of the Lower
Lagoon at Lord ' s Park . The lagoon dredged is the most southeasterly
one adjacent to Bode Road . The contractor for this project was Plote,
Inc . of Elgin.
REASONS FOR CHANGE: At two locations in the lagoon there was above
normal depth of silt deposits . This was not detected during the
survey work .
SUMMARY OF CHANGES IN THE CONTRACT: The amount of the contract will
be revised as follows:
ITEM ADD DEDUCT
Earth Excavation - 583 Cu. Yd . a $10.50 6, 121 .50
P.C.C. Sidewalk
Removal & Replacement - 40 Sq .Ft . a $ 6.00 240.00
P.C.C. Curb & Gutter
Removal & Replacement
Type B-6. 12 - 20 Lin.Ft . a $33.50 670.00
Top Soil & Seeding 60 Sq .Yd . a $ 6.00 360.00
TOTALS $6, 151 .50 $1 ,270.00
Net addition to $4 ,851 .50
contract
The original contract with Plote, Inc . of Elgin was for $73,303.00.
By reason of this Change Order No . 1 , the contract for the dredging of
the Upper Lagoon will he inL_reased in the amount of Four Thousand
Eight Hundred Fifty-one and 50/ 100 ($78, 154 .50) .
OIHEB_CONIBACI_EBQVISIQNS= All other contract provisions shall remain
the same.
Recommended : Approved :
ENGINEERING DIVISION CITY OF ELGIN
Party of the First
By44e54;2C-^:j(7:21-0_ Part (Owner )
12 �� B •' / . / / (�
Date %,--%•-%-• � � y_
die
T e• ity ty M na er
a g
Date:
EXCAVATION AND/OR DREDGING OF
LOWER LAGOON AT LORD ' S PARK
CHANGE ORDER NO. 1
Accepted :
PLDIE,` I N
Title G =r. Manager
Date 3/4/88
April 5, 1988
MEMORANDUM
TO: Mayor and Members of the City Council
FROM: City Manager
SUBJECT: Change Order No.1 , Excavation and/or
Dredging of Upper Lagoon at Lord' s Park
PURPOSE: This memorandum will provide the Mayor and Council
with information for considering the attached Change Order.
BACKGROUND: There was a long delay after the award of the
Middle Dam to G.F. Structures to start the repair work. This
delay was due to the excessive flow of water through the gate.
Without diverting the flow of water, it was impossible to pour
the concrete for the floor slab and the wing walls.
After the lagoon project was awarded, it became evident that
without another outlet, the dredging operation would be ham-
pered. The flow line at the gate is one and one half foot
higher than the proposed low point of the lagoon after dredging.
A decision was made to install a diversion pipe west of the
Middle Dam. The contractor agreed to install the pipe for only
the cost of the material.
FINANCIAL IMPACT: The original contract with Ed R. Beltz
Excavating & Grading, Inc. was for $61 ,717 .00 . With this Change
Order, the project cost will be increased by $1 ,978 .00 to a
total of $63 ,695 .00 . There is $75,000 .00 budgeted for this
project in the 1988 Parks Maintenance Budget.
RECOMMENDATION: It is recommended that the City Council author-
ize the execution of Change Order No. 1 for the Excavation and/or
Dredging of Upper Lagoon in the amount of $1 ,978.00.
A copy of the Change Order is attached for your consideration.
ames J4iprok, City Manager
SA:do
Attachment
3 -J
EXCAVATION AND/OR DREDGING OF
UPPER LAGOON AT LORD'S PARK
ELGIN, IL
CHANGE ORDER NO. 1
SCOPE: This Change Order No. 1 covers the dredging of the Upper
Lagoon at Lord' s Park. The lagoon being dredged is the second
one north from Bode Road. The contractor for this project is Ed
R. Beltz Excavating & Grading, Inc. of South Elgin.
REASONS FOR CHANGE: There was an excessive amount of water, a
combination of surface run off from points north and the spring
water at the lagoon. The flow line at the only outfall, the
Middle Dam, which is under repair is one and one half foot
higher than the proposed low point of the lagoon.
Due to the situation described above it became a necessity to
install a pipe to drain the water. Without this pipe there
would have been a collection of water inside the lagoon and this
would have hampered the dredging operation. Also, G.F. Struc-
tures, contractor for the repair of the Middle Dam was not able
to do the repair work due to the continuous flow of water
through the gate. It would have been impossible to pour the
concrete for the floor slab and the wing wall without diverting
the water away from the Middle Dam.
Due to the ease and convenience of the dredging operation, Ed.
R. Beltz agreed to install the 15 inch PVC pipe for only the
cost of material. It was installed west of the Middle Dam. The
pipe will be capped at the north end. When the lagoon is
dredged next time, the cap will simply be removed to drain the
lagoon.
SUMMARY OF CHANGES IN THE CONTRACT: The amount of the contract
will be revised as follows:
ITEM ADD
15 Inch PVC Pipe to drain water from Upper Lagoon $1 ,978.00
to lower Lagoon, Material Only, Lump Sum
TOTAL $1 ,978 .00
Net addition to contract $1 ,978 .00
The original contract with Ed R. Beltz Excavating & Grading,
Inc. was for $61 ,717.00. By reason of this Change Order No. 1 ,
the contract for the dredging of the Upper Lagoon will be
increased by One Thousand Nine Hundred and Seventy Eight Dollars
($1,978.00) to a total of Sixty Three Thousand Six Hundred
Ninety Five and 00/100 Dollars ($63,695.00) .
Excavation and/or Dredging of Upper
Lagoon at Lord' s Park
Change Order No.1
Page 2
OTHER CONTRACT PROVISIONS: All other contract provisions shall
remain the same.
Recommended: Approved:
ENGINEERING DIVISION CITY OF ELGIN
By Party of the First
Part (Owner)
Date
By
Title
Date
Accepted:
ED R. BELTZ EXCAVATING & GRADING, INC.
By
Title
Date