HomeMy WebLinkAbout92-0527 Elgin Builders ca-0S-3.1
RESOLUTION
APPROVING CHANGE ORDER NO. 3 IN THE CONTRACT WITH
ELGIN BUILDERS, INC. FOR THE LORD' S PARK PAVILION
WHEREAS, the City of Elgin has heretofore entered into a
contract with Elgin Builders, Inc. for the Lord' s Park
Pavilion; and
WHEREAS, it is necessary and desirable to modify the
terms of the contract as is described in Change Order No. 3,
attached hereto.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE
CITY OF ELGIN, ILLINOIS, that Larry L. Rice, City Manager, be
and is hereby authorized and directed to execute Change Order
No. 3, a copy of which is attached hereto and made a part
hereof by reference.
s/ George VanDeVoorde
George VanDeVoorde, Mayor
Presented: May 27, 1992
Adopted: May 27, 1992
Omnibus Vote: Yeas 7 Nays 0
Recorded:
Attest:
s/ Dolonna Mecum
Dolonna Mecum, City Clerk
ELGIN, ILLINOIS
RENOVATION OF THE LORD' S PARK PAVILION
CHANGE ORDER NO. 3
SCOPE: This Change Order No. 3 covers additional work required
to complete construction changes for renovation of the
Lord's Park Pavilion.
The Contractor for this project is Elgin Builders ,
Inc. , of Elgin, Illinois .
REASONS FOR CHANGE:
This Change Order is required for the costs associated with the
items requested by staff to complete the following work.
1 . Delete the emergency fire service for the elevator. Provide
an enameled elevator door in lieu of plastic laminate.
The circumstances necessitating this change were that the
fire service for a two story building was not required by
the elevator inspector. The enameled door was an economical
option available without reducing the quality of the
application. This change is in the best interest of the
City
2 . Provide new door frames and trim for Doors 1 and 2 .
The circumstances necessitating this change were
unforeseeable. The existing door frames and trim were
rotten. This became evident upon removal of the adjacent
masonry wall .
3 . Revision of door hardware.
The circumstance necessitating this change is that it is in
the best interest of the City. As the project proceeded
under construction, it became evident that the specified
hardware would not be required.
4. Removal of the existing rubble stone wall adjacent to the
relocated Elevator Equipment Room. The scope of work
included removal of the existing wall , cutting the existing
concrete floor slab, pouring a new concrete footing and
floor, and laying up a new masonry wall .
The circumstances necessitating this change were due to
unforeseeable existing conditions . The existing wall was in
a deteriorated condition and needed to be repaired.
5 . The installation of curbs , planters , and paving patches on
the east side of the Pavilion. This will provide for a
landscape buffer from the driveway on the east side of the
building and provide protection at the bottom of the ramp
leading up to the main level of the Pavilion. This is the
logical time to do this work since it eliminates tearing out
of new work when the landscape surrounding the Pavilion is
designed.
The circumstance necessitating this change is that it is in
the best interest of the City.
6. Relocate telephone conduit stubbed into the floor to the new
telephone board location. This is related to the
elimination of the interior stair previously discussed.
Install additional telephone conduit and outlet boxes in
Rooms 111 ,104 and 202 . This represents additional telephone
locations requested by the Parks and Recreation Department .
The circumstance necessitating this change is that it is in
the best interest of the City.
7 . Construct a concrete retaining wall beneath the transformer
pad on the south side of the Pavilion. This is a result of
field conditions relative to the existing grades .
The circumstance necessitating this change is that it is in
the best interest of the City.
8 . Provide additional bathroom partitions as requested by the
Parks and Recreation Department . The additional screens
provide for further privacy in the bathrooms .
The circumstance necessitating this change is that it is in
the best interests of the City of Elgin.
9 . Remove the exposed toilet vent from the north meeting room
and conceal it in the wall . This eliminates the viewing of
a unsightly intrusion.
The circumstance necessitating this change is that it is in
the best interest of the City.
10 . Replace rotten floor joists over the Room 101 .
The circumstance necessitating this change is that the
condition of these joists was unforeseeable until the
ceiling beneath the joists was removed, exposing their
existing rotten condition.
11 . Replace rotten wood base along the floor in Room 101 .
The circumstance necessitating this change is that the
existing base was rotten. This was unforeseen until the
base was removed, thus exposing the rotten condition evident
from the back side .
SUMMARY OF CHANGES IN CONTRACT AMOUNT:
The amount of the contract will be revised as follows :
ITEM COST CHANGE
Item 1 Delete ($825 .00)
Item 2 Add $420 .00
Item 3 Delete ($102 .00)
Item 4 Add $1 , 484.00
Item 5 Add $5, 499.00
Item 6 Add $683 .00
Item 7 Add $1 ,014 .00
Item 8 Add $531 .00
Item 9 Add $679. 00
Item 10 Add $547 .00
Item 11 Add $524.00
Total Net Cost Add $10 ,454.00
The present contract with Elgin Builders , Inc. is for
$949,511 .00 . By reason of Change Order No. 3 the contract for
the Renovation of the Lord's Park Pavilion will be increased in
the amount of Ten Thousand Four Hundred Fifty Four Dollars
($10 , 454.00) . The new revised contract total will be Nine
Hundred Fifty Nine Thousand Nine Hundred Sixty Five Dollars
($959, 965. 00) .
OTHER CONTRACT PROVISIONS: All other contract provisions shall
remain the same.
Agreed to this . Y ,2(17(.-
day of "7 , 1992 .
Recommended:
PAR D P M' T
By: Amm
Date:
Accepted:
ELGIN BUILDERS, INC.
Party of the Second Part (Contractor)
By:
Title:
Date: 5-7777,7„.,—
Approved:
City of Elgin
Party of t e `_ Owner)
By: 04111
Title: _ rc ( z„..-ct 4 . �
Date: I /NW .Z
• .� 4
PAO=7 Ixi /Keen Ire,Gm*Man 014/1.b pe.PHONE IOIE FREE I+KO-225.3N
ADDITIONAL WORK AUTHORIZATION
ELGIN BUILDERS INC.
1801 Larkin Avenue
ELGIN, ILLINOIS 60123
Phone (708) 742-0090
Fax (708) 742-0185
OWNER'S PHONE DATE
NAME
Ilahl yri ct Ai Lut7ow JOB 742- 4063 May 6, .1 q92 BER
STREET
472 N. •McLean Blvd. Lord's Park Pavilion 520
CITY STATE STREET
Elgin llinois 100 Oakwood Blvd_
EXISTING CONTRACT NO. DATE OF EXISTING CONTRACT CITY STATE
8-30-91 Elgin IL
You are hereby authorized to perform the following specifically described additional work:
Delete emergency fire service and enameled
door in lieu of plastic lamina/e,.
(_$.7_8G`OD_)
G.C.O.H. & P. (.39.00)
(3.825__0.0_)
ADDITIONAL CHARGE FOR ABOVE WORK IS: $ (825.00) CREDIT REVISED
Payment will be made as follows: Applied to contract
Above additional work to be performed under same conditions as specified in original contract unless otherwise stipulated.
Date 19 Authorizing Signature
(OWNER SIGNS HERE)
We hereby agree to furnish labor and materials-complete in accordance with the above specifications,at above stated price.
Authorized Signature Date May 6th 1992
(CONTRACTOR SIGNS HERE)
THIS IS CHANGE OR ER NO_ 1 (one) Revised
• y ,.j .J
'4„! -.. Q5...' .*..: vt -.l - ,..
PRot*ET120 PVETigikc.Gookti Mas.01411.To Order PHONE IOU.FREE l+M425 360
-
V
ADDITIONAL WORK AUTHORIZATION.
ELGIN BUILDERS INC.
1801 Larkin Avenue
ELGIN, ILLINOIS 60123
Phone (708) 742-0090
Fax (708) 742-0185
OWNER'S PHONE DATE
NAME Dahlquist & Lutzow 742-4063 May 6i 1992
STREET JOB NAME JOB NUMBER
472 N. McLean Blvd. Lord's Park Pavilinn 520
CITY STATE STREET
Elgin Tllinnic 100 Oakwood Blvd.
EXISTING CONTRACT NO. DATE OF EXISTING CONTRACT CITY STATE
8-30-91 Elgin IL
You are hereby authorized to perform the following specifically described additional work:
New door frames and trim for doors 1 and 2.
Materials --_^--_-`--��_ $365.00
Labor to install N/C
G.C.O.H. & P. (15%) 55.00
I _-. _______.___ �_�.__._ $420.00
ADDITIONAL CHARGE FOR ABOVE WORK IS: $ 420 on RFVTSFD
Payment will be made as follows: come as contract
Above additional work to be performed under same conditions as specified in original contract unless otherwise stipulated.
Date 19 Authorizing Signature
(OWNER SIGNS HERE)
We hereby agree to furnish labor and materials-complete in accordance with the above specifications,at above stated price.
Authorized Signature , Date May 6th 1992
(CONTRACTOR SIGNS HERE)
! THIS IS CHANGE ORDER NO. 2 (two) Revised _
(;, !• tL
MODULI 120 /N€eshlet,Colo.Um OWI.G Order 11011E 301E FEE 1+100.1250300
ADDITIONAL WORK AUTHORIZATION
• ELGIN BUILDERS INC.
1801 Larkin Avenue
ELGIN, ILLINOIS 60123
Phone (708) 742-0090
Fax (708) 742-0185
OWNER'S PHONE DATE
NAME
Dahlquist & Lutzow 742-4063 May 6, 1992
STREET JOB NAME JOB NUMBER
472 N_ McLPan Blvd lord' s Park Pavilion 5?0
CITY STATE STREET
Elgin Illinois 100 Oakwood Blvd.
EXISTING CONTRACT NO. DATE OF EXISTING CONTRACT CITY STATE
8-30-91 Elgin IL
You are hereby authorized to perform the following specifically described additional work:
-Furni-sh-ha.rdwa.re-for--door-#18--not-Listed-on-hardware-schedule_
_ $286-.-00 _-
G-.-G-.-0•.H.-&-P-._-1.5. _ _.-.._..-. 43.00
�._�- --- $329-.-00_ .._-...-
Doors 31, 32, 38, 43, 46, and 47 were scheduled with two
closures each. Only one is required.
Six closures at $62.50 each ($375.00)
G.C.O.H. & P. 15% (56.00) - -
($431.00)
1
I
ADDITIONAL CHARGE FOR ABOVE WORK IS: $ (102.00) CREDIT REVISED
Payment will be made as follows: Applied to contract
Above additional work to be performed under same conditions as specified in original contract unless otherwise stipulated.
Date 19 Authorizing Signature
1 (OWNER SIGNS HERE)
We hereby agree to furnish labor and materials-complete in accordance with the above specifications.at above stated price.
Authorized Signature421' Date May 6th 1992
(CONTRACTOR SIGNS HERE)
THIS IS CHANGE 0 DER ILIO_ 9 (nine) Revised
MAW IX) Fviaiq Mc.Woo.tl . I471.M Wet Mil III IAll I+ 21•,ON
ELGIN BUILDERS INC.
1801 Larkin Avenue
ELGIN, ILLINOIS 60123
Phone (708) 742-0090
Fax (708) 742-0185
OWNER'S PHONE DATE
NAME Dahl qui st & Lutzow 742-4063 Febru 7,_1992
STREET JOB NAME JOB NUMBER
472 N_ f4cLean vd_ I Par-k—P-a 2.0
CITY STATE STREET
Elgin Illinois 100 Oakwood Blvd.
EXISTING CONTRACT NO. DATE OF EXISTING CONTRACT CITY STATE
8-30-91 Elgin Il
You are hereby authorized to perform the following specifically described additional work:
Relocate Elevator Equipment Room SK8
-Saw cut floor remove concrete - wall demolition $ 260:00 .
_Concrete footing and floor- 386.00
Masonry........ ..._ 409.00
--Hollow metal door and frame 233.00
_..._._....._.._..
$1,290.00
G.C.0.H. & P. 15% 194.00
$1,484.00. . .
ADDITIONAL CHARGE FOR ABOVE WORK IS: $
Payment will be made as follows: Same as Contra('t
Above additional work to be performed under same conditions as specified in original contract unless otherwise stipulated.
Date 19 Authorizing Signature
(OWNER SIGNS HERE)
We hereby agree to furnish labor and materials-complete in accordance with the above specifications,at above stated price.
Authorized Signature
v Date February 7th 19 92
(CONTRACTOR SIGNS HERE)
17 (seventeen) -'
ADDITIONAL WORK AUTHORIZATION
ELGIN BUILDERS INC.
1801 Larkin Avenue
ELGIN, ILLINOIS 60123
Phone (708) 742-0090
Fax (708) 742-0185
•
OWNER'S PHONE DATE
" E Dahlquist & Lutzow 742-4063 February 25, 1992
STREET JOG NAME JOD NUMOER
472 N Mri pan 111 yr! Lord's Park Pavilion 520
CITY STATE STREET
Elgin Illinois 100 Oakwood Blvd.
EXISTING CONTRACT NO. DATE OF EXISTING CONTRACT CITY STATE
8-30-91 Elgin TI
You are hereby authorized to perform the following specifically described additional work:
Install curbs, planters and paving patches as per SK-9
Excavation, CA6 stone base and topsoil $1,142.00
204 lin. ft. "B" curb at $14.40jer lin. ft: 2,938.00
450 sq. ft. of paving at $1.56 702.00 .
$4,782.00
G.C.O.H. & P. 15% 717.00
$5,499.00
•
ADDITIONAL CHARGE FOR ABOVE WORK IS: $ 5,499.00
Payment will be made as follows:
Same as contract
Above additional work to be performed under same conditions as specified in original contract unless otherwise stipulated.
i -
Date 19 Authorizing Signature
(OWNER SIGNS HERE)
We hereby agree to furnish labor and materials—complete in accordance with the above specifications,at above stated price.
Authorized Signature Date February 25th 19 92
IS��** e� (CONTRACTOR SIGNS HERE)
IS
THIS CHANGE ORDER NO. 21 (twenty-one)
NOTE:This Revision becomes part of,and In conformance with,the existing contract.
•
_ �'+r �..e •bra �.✓ \'' 'v �J '.� 't.J' �✓ '-./
MUCCIIN �ivULLlee.Cooke.r..mul.Milk PIarcrourlrcL1+aoo.m.ww
•
ADDITIONAL WORK AUTHORIZATION
. ELGIN BUILDERS INC.
1801 Larkin Avenue
ELGIN, ILLINOIS 60123
Phone (708) 742-0090
Fax (708) 742-0185
OWNER'S PHONE DATE
NAME Dahlquist & Lutzow 742-4063 May 6, 1992
STREET JOB NAME JOB NUMBER
472 N. McLean Blvd. Lord's Park Pavilion 520
CITY STATE STREET
E1r�in llinois 100 Oakwood Blvd_
EXISTING CONT CT NO. DATE OF EXISTING CONTRACT CITY STATE
8-30-91 Elgin IL
You are hereby authorized to perform the following specifically described additional work:
Re_l_o_ca_t.et.e.l ep.hone.__..condui..t.,_a.l_re.ady_i.ns.tali..ed..,_.to-_new__te_l..ep.hone._.boa.r...d.. location_
$4.50_._0.0___
Install p.hone_.co.n du i..t_.and._..o u tl..e.t_.boxes_i.n.__.r...00ms__11.1,_104.._.a.n d_202-.-
-- -- —$200...00
$650.00-----
G.. __.......33.,..00._—_.__
$683...00
ADDITIONAL CHARGE FOR ABOVE WORK IS: $ 683.00 REVISED
Payment will be made as follows: Same as contract
Above additional work to be performed under same conditions as specified in original contract unless otherwise stipulated.
Date 19 Authorizing Signature
(OWNER SIGNS HERE)
We hereby agree to furnish labor and materials-complete in accordance with the above specifications.at above stated price.
Authorized Signature ..2d- Date May 6th 19_92
CHANGE
C p ER
(CONTRACTOR SIGNS HERE)
THIS•
IS CHANGE OR NO. l?_(_twenty-twnl Rev_i_cPd
101•
PRODUCT 170 AL/E175. had.Wa 01471.H Ode NUM TOLL IME I+A00d16-4 0
ADDITIONAL WORK A .. 'Tr R ZATEON
ELGIN BUILDERS INC.
1801 Larkin Avenue
ELGIN, ILLINOIS 60123
Phone (708) 742-0090
Fax (708) 742-0185
OWNER'S PHONE DATE
NAME
Oahlquict & Iut7ow 742-4063 April 0, 1992
STREET JOB NAME JOB NUMBER
472 N. McLean Blvd. Lord' s Park Pavilion 520
CITY STATE STREET
Elgin Illinois 100 Oakwood Blvd.
EXISTING CONTRACT NO. DATE OF EXISTING CONTRACT CITY STATE
8-30-91 Flgin TI
You are hereby authorized to perform the following specifically described additional work:
Construct retaining wall - foundation under transformer Pad,......_............_.._..... . ..._......._.............._......._.......__..._....-._..__._._
- -Excavation....-. 2..hrs.. at .$80 $.... ...16.0_...00 .............................__. ..........-.......-............... ... —_
- ._......_.__.__Concrete......._-_....._3..._1/2 yds........_at $60 ..... . _.... ._.. 210.00.......
Steel reinforced bar 32..00 .
_..__........_..... -Labor......-_..._1.2.-.hrs....at $40................ .. ........... .......... ... .. 480.00 . ._...................... .._._..... ........... ..........
_._ —._......_......... - $.........882.00........... .. ....... ....._.
G.C•0.N•.......&....._P..............15%... .. ..-_.................... 132.00 ......................._.. . ....._...................._._. -. -.
_.. ..........._._._.._._......................................................... .......................... .... . ...
$1,014..00
ADDITIONAL CHARGE FOR ABOVE WORK IS: $ 1,014.00
Payment will be made as follows: Sam- . .
Above additional work to be performed under same conditions as specified in original contract unless otherwise stipulated.
Date_._ 19 Authorizing Signature
(OWNER SIGNS HERE)
We hereby agree to furnish labor and materials-complete in accordance with the above specifications,at above stated price.
uz �' �-�
April 10th2
19 92
Authorized Signature Date
(CONTRACTOR SIGNS HERE)
u n C t'x '?' - CIA L ,R `)R 1 tt.inntv_fnuv.)
•
•
IWOIICI Im /nrc'esj Mt,Cote l ra 01471.10 ae.ROIl TOLL TREE I+eoo-:254310
ADDITIONALWORKU (:s 1:O., ,a ,:,
ELGIN BUILDERS INC.
1801 Larkin Avenue
ELGIN, ILLINOIS 60123
Phone (708) 742-0090
Fax (708) 742-0185
OWNER'S PHONE DATE
NAME Dahlquist & Lutzow 742-4063 April 14, 1992
STREET JOB NAME JOB NUMBER
472 N MOIpan Rlvd lord's Park Pavilion 520
CITY STATE STREET
Elgin Illinois 100 Oakwood Blvd.
EXISTING CONTRACT NO. DATE OF EXISTING CONTRACT CITY STATE
8-30-91 Elgin IL
You are hereby authorized to perform the following specifically described additional work:
Additional bathroom partitions as per drawing SK-13A.
$462.00
G.C.O.H. & P. 15% 69.00
$531.00
ADDITIONAL CHARGE FOR ABOVE WORK IS: $ 531.00
Payment will be made as follows: Same as contract
Above additional work to be performed under same conditions as specified in original contract unless otherwise stipulated.
Date 19 Authorizing Signature
(OWNER SIGNS HERE)
We hereby agree to furnish labor and materials-complete in accordance with the above specifications.at above stated price.
Authorized Signature Date April 14th 19 92
(CONTRACTOR SIGNS HERE)
Tg—i!S ( H Pa. 7''7, F , Pr \712 2F (twenty-fivra)
ADDITIONAL WORK AUTHORIZATION
ELGIN BUILDERS INC.
1801 Larkin Avenue
ELGIN, ILLINOIS 60123
Phone (708) 742-0090
Fax (708) 742-0185
OWNER'S PHONE DATE
NAME Dahlquist & Lutzow 742-4063 April 15, 1992
STREET JOB NAME JOB NUMBER
472 N. McLean Blvd. Lord's Park Pavilion 520
CITY STATE STREET
Frain llinnic 10n Oakwood Blvd_
EXISTING CONTRACT NO. DATE OF EXISTING CONTRACT CITY STATE
8-30-91 Elgin IL
You are hereby authorized to perform the following specifically described additional work:
Remove ve_n_t r_om_n.ot th__meati.ng........r...oom_a.nd_r..ece.ss__i_n._.waEL.
________ •
edais ...... --_...-.— --____.--100..00.-..._.___._..
•__ ._.__. ._.____. ___._.150.00... — _
________
_____.$67_9..._00_
ADDITIONAL CHARGE FOR ABOVE WORK IS: $ 679.00
Payment will be made as follows: Same as contract
Above additional work to be performed under same conditions as specified in original contract unless otherwise stipulated.
Date 19 Authorizing Signature
(OWNER SIGNS HERE)
We hereby agree to furnish labor and materials-complete in accordance with the above specifications,at above stated price.
Authorized Signature ��c Date April 15th 19 92
9'14-4 (CONTRACTOR SIGNS HERE)
THIS IS CHANGE ORDER NO. 2.6 Uwe nty si )
\ NOTE:This Revision becomes part o1,and In conformance with,the existing contract
ADDITIONAL WORK AUTHORIZATION
ELGIN BUILDERS INC.
1801 Larkin Avenue
ELGIN, ILLINOIS 60123
Phone (708) 742-0090
Fax (708) 742-0185
OWNER'S •PHONE DATE
NAME Dahlquist & Lutzow 742-4063 April 16, 1992
STREET JOB NAME JOB NUMBER
472 N. McLean Blvd. Lord's Park Pavilion 520
CITY STATE STREET
Elgin Illinois 100 Oakwood Blvd.
EXISTING CONTRACT NO. DATE OF EXISTING CONTRACT,CITY STATE
8-30-91 Elgin IL
You are hereby authorized to perform the following specifically described additional work:
Rep].ace_r._otted_f_.l..o o.r___j o.i..s.t..._o v e r.___..r.o u n d_.r..o.om..._...._...._.._____..._............._.-._____—...__-_
$.1.56...00_
8Mbo.r_.a_t_.$40_ _320.00.._.
$476..00._---..._-.......__._._
7.1.00- ---
- 454.7.....00. --
ADDITIONAL CHARGE FOR ABOVE WORK IS: $ 547.00
Payment will be made as follows: Same as contract
Above additional work to be performed under same conditions as specified in original contract unless otherwise stipulated. •
Date 19 Authorizing Signature
(OWNER SIGNS HERE)
We hereby agree to furnish labor and materials-complete in accordance with the above specifications,at above stated price.
*414
Authorized SignatureDate April 16tb 19-92—
(CONTRACTOR SIGNS HERE)
THIS IS CHANGE ORDER NO. 27--twen-t,-se-v-en>
NOTE:This Revision becomes part of,and In conformance with.the existing contract.
ADDITIONAL. WORK AUTHORIZATION
ELGIN BUILDERS INC.
1801 Larkin Avenue
ELGIN, ILLINOIS 60123
Phone (708),742-0090
Fax (708) 742-0185
OWNER'S PHONE DATE
NAME Dahlquist & Lutzow 742-4063 April 23, 1992
STREET JOB NAME JOB NUMBER
472 N. McLean Blvd. Lord's Park Pavilion 520
CITY STATE STREET
Flgin T1 Innis 100 Oakwood Blvd.
EXISTING CONTRACT NO. DATE OF EXISTING CONTRACT CITY STATE
8-30-91 Elgin IL
You are hereby authorized to perform the following specifically described additional work:
__Re.pl.ace._r_ott.ed_.ba.s.e_i_n.._r_o.om_1.0.1_..._ __.._... ____...___..__.....-.-.-.-.----._ _.__.._.._._--
Mat.eri..a1s_o.n_l.y
13.'.at.__$..3._38.__.p.er l i..ne.a.r__f....t..___...._._..._._.._._......._..._.._--- ___.._._.$..4..5.6_...0.0 ___
G._C,_0 H_.__&_P._.-___.1.5.%___ ___ ..._....._..__.__—._._.__-_.-.-----.___........._......68.00_....--.-.-.-.--__ ..
_._ ________ .____.____-.____.._.__.________._.- --._......$.52.4...00___.._...____.—..._.__.__..—__
ADDITIONAL CHARGE FOR ABOVE WORK IS: $ 524.00
Payment will be made as follows: Same as contract
Above additional work to be performed under same conditions as specified in original contract unless otherwise stipulated.
Date 19 Authorizing Signature
(OWNER SIGNS HERE)
We hereby agree to furnish labor and materials-complete In accordance with the above specifications.at above stated price.
0Authorized Signature 2///�- Date April 23rd 19 92
(CONTRACTOR SIGNS HERE)
THIS IS CHANGE 0 DER NO. 29 (twenty-nine)
NOTE:This Revision becomes part of.and In conformance with,the existing contract. j
•
(;:bi
OF
41, Agenda Item No.
04,4I[D SERI
40
May 7 , 1992
TO: Mayor and Members of the City Council
FROM: Larry L. Rice, City Manager
SUBJECT: Remodeling of Lords Park Pavilion
PURPOSE
The purpose of this memorandum is to forward to the
Mayor and City Council recommendations concerning the remodel-
ing of the Lords Park Pavilion.
BACKGROUND
eikArchitects, Dahlquist & Lutzow prepared plans and speci-
fications for the remodeling of the pavilion last summer.
Subsequently, a contract was awarded to Elgin Builders for
the construction work which was begun on September 9 . At-
tached is a change order from Dahlquist & Lutzow regarding
the remodeling work. The change order includes 11 items with
a net total cost of $10,454. Several of the items can be
attributable to conditions that were unforeseen until the
renovation work began. The proposed changes will also add to
the aesthetics of the building as well as improving its opera-
tional function.
FINANCIAL IMPACT
The changes recommended by the architects will result in
a $10,454 increase in the contract with Elgin Builders from
$949,511 to $959,965 . There are sufficient funds available
in the 1991 bond fund and the 1992 Parks budget to finance
the proposed work.
RECOMMENDATION
It is recommended the staff be directed to prepare a
resolution authorizing execution of Change Order No. 3 for
the Lords Park Pavilion project.
Lairy L. Rie, CitAr Majnager
LLR:amp
Attachment
ELGIN, ILLINOIS
RENOVATION OF THE LORD'S PARK PAVILION 410
CHANGE ORDER NO. 3
SCOPE: This Change Order No. 3 covers additional work required
to complete construction changes for renovation of the
Lord's Park Pavilion.
The Contractor for this project is Elgin Builders,
1 Inc. , of Elgin, Illinois .
REASONS FOR CHANGE:
This Change Order is required for the costs associated with the
items requested by staff to complete the following work.
1. Delete the emergency fire service for the elevator. Provide
an enameled elevator door in lieu of plastic laminate.
The circumstances necessitating this change were that the
fire service for a two story building was not required by
the elevator inspector. The enameled door was an economical
- option available without reducing the quality of the
application. This change is in the best interest of the
City
2. Provide new door frames and trim for Doors. 1 and 2 .
410
The circumstances necessitating this change were
unforeseeable. The existing door frames and trim were
rotten. This became evident upon removal of the adjacent
masonry wall .
3. Revision of door hardware.
The circumstance necessitating this change is that it is in
the best interest of the City. As the project proceeded
under construction, itbecame evident that the specified
hardware would not be required.
4. Removal of the existing rubble stone wall adjacent to the
relocated Elevator Equipment Room. The scope of work
included removal of the existing wall , cutting the existing
concrete floor slab, pouring a new concrete footing and
floor, and laying up a new masonry wall .
The circumstances necessitating this change were due to
unforeseeable existing conditions. The existing wall was in
a deteriorated condition and needed to be repaired.