HomeMy WebLinkAbout92-0212 Skander Constructon Inc. RESOLUTION
APPROVING CHANGE ORDER NO. 1 IN THE CONTRACT WITH
SKENDER CONSTRUCTION, INC. FOR THE ELGIN FIRE STATIONS
WHEREAS, the City of Elgin has heretofore entered into a
contract with Skender Construction, Inc. for the Elgin Fire
Stations; and
WHEREAS, it is necessary and desirable to modify the
terms of the contract as is described in Change Order No. 1,
attached hereto.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE
CITY OF ELGIN, ILLINOIS, that Larry L. Rice, City Manager, be
and is hereby authorized and directed to execute Change Order
No. 1, a copy of which is attached hereto and made a part
hereof by reference.
s/ George VanDeVoorde
George VanDeVoorde, Mayor
Presented: February 12, 1992
Adopted: February 12, 1992
Omnibus Vote: Yeas 7 Nays 0
Recorded:
Attest:
s/ Dolonna Mecum
Dolonna Mecum, City Clerk
•
Attachment #1
KALTEN BACH AND FERENC
ARCHITECTS 17 DOUGLAS AVENUE, ELGIN. ILLINOIS 60120 $ e-741-1050
708
CHARLES F. KALTENBACH.A. I.A.
THOMAS V. FERENC.A.I.A.
December 12, 1991
CHANGE ORDER NUMBER ONE
CONTRACTOR
Skender Contruction, Inc.
10101 South Roberts Road
Palos Hills, IL 60465
PROJECT TITLE
Elgin Fire Stations
Elgin, IL
OWNER
City of Elgin
150 Dexter Court
Elgin, IL 60120
Changes in the plans and specifications for the above captioned project,
as approved by Kaltenbach and Ferenc, Architects, are authorized as
follows:
1. To remove underground storage tanks uncovered at
Villa Street site.
ADD $ 4,128.00
2. Furnish and install 100 ampere circuit breaker for panel
EM in each station.
ADD $ 699.00
3. Furnish red and green exterior lighting fixtures at each
station.
ADD $ 576.00
4. To furnish and install four inch PVC conduit for telephone
lines to stations as requested by telephone company.
ADD $ 4,320.00
5. Install a wet automatic fire suppression system in each
station in lieu of the dry system specified.
DEDUCT $ 3,000.00
6. Furnish and install twelve Link photo electric controls
at overhead doors.
ADD $ 5,206.00
7. Remove unsuitable soil encountered at the Villa Street site
and replace with approved fill.
ADD $ 917.00
Elgin Fire Stations Page 2
CHANGE ORDER NUMBER ONE
8. Finished hardware selected for the three stations purchased
from the hardware allowance.
DEDUCT $13,425.00
9. Change color of water closet and lavatory in Women's Rooms.
ADD $ 1,100.00
10. Furnish and install conduit for traffic signal preemption
devices at each site.
ADD $ 849.00
11. Add under sink garbage disposers in three kitchens.
ADD $ 835.00
12. Revise kitchen cabinet sizes and layouts to accommodate
appliances selected for the three stations.
ADD $ 490.00
13. Supply connections to dishwashers, exhaust hoods, ranges,
water coolers, washers and dryers.
ADD $ 933.00
14. To change sequence of operation on vehicle exhaust systems.
ADD $ 1,088.00
15. Delete communication conduits and add television outlets.
NO CHARGE
16. Add water tank fill stations at the ceiling of Apparatus Room
in all stations.
ADD $ 2,644.00
17. Apply epoxy paint on walls of Hose Rooms.
ADD $ 666.00
18. To remove underground monolithic curb encountered in
driveway construction at Villa Street site.
ADD $ 3,690.00
19. To repaint ceiling color in various rooms at McLean
Boulevard station.
ADD $ 1,249.00
20. Raise north subgrade at Royal Boulevard site due to site
plan revisions.
ADD $ 1,580.00
21. Eliminate two coats of concrete sealer specified for the
Apparatus Room floor at the three buildings.
DEDUCT $ 1,000.00
Elgin Fire Stations Page 3
CHANGE ORDER NUMBER ONE
22. Extend the natural gas line from the Work Room to the Lawn
Equipment Room for future emergency generator at each building.
ADD $ 685.00
23. Furnish and install receivers and transmitters to match the
Elgin system.
ADD $ 1,920.00
24. Cost of face brick selected for the three buildings from the
brick allowance subject to confirmation of suppliers invoices.
DEDUCT $ 5,888.00
TOTAL ADD: $10,262.00
For which payment to be made to you under Contract dated December 14,
1990, shall be revised as follows:
Original Contract Amount $1,761,000.00
Change Order Number One 10,262.00
Revised Contract Amount $1,771,262.00
AUTHORIZ D BY O'‘ _
City of Elt'n
- c--u
RECOMMENDED B ARCHITECT
Kaltenbach and Ferenc
•
• PTED ,BY COQ, ACTOR
Sken s er Co, -.tr �f�' , Inc.
, 10 ��'�
•
MEMORANDUM
January 15, 1992
To: Larry Rice, City Manager / /
From: John Henrici, Fire Chief 6'
Subject: Change Order For New ire Stations
599 S. McLean
804 Villa Street
2455 Royal Blvd.
Attached is a listing of changes that were authorized to bring con-
struction of our three (3) new fire stations to successful comple-
tion. These changes were all reviewed by our Architect and my office
prior to your review and approval .
There are twenty-four (24) specific items that needed to be addressed
during construction. Some of the items that were changed added to
the cost, some had no effect on the cost, and some gave us a cost
credit. I will address each item and the reason for the change.
The changes will be addressed by number 1, 2, 3, etc. as listed on
the attached letter (attachment #1) from our Architect Mr.
Kaltenbach, dated 12/12/91 .
Item 1
During excavation for foundations, underground storage tanks were
uncovered. We did not know they existed nor were they detected dur-
ing soil borings . This was not foreseeable at the time the contract
was signed. Added cost of $4, 128.
Item 2
During construction of these buildings, it was determined from a
recommendation by the electrical contractor that the circuit breaker
specified in the original contract would be marginal in performance
for our emergency circuit panel . A 100 ampere circuit breaker was
recommended. This change is germane to the original contract and
also in the best interest of the City. Added cost of $699 .
Item 3
Furnish red and green exterior lighting fixtures on the fire stations
was an oversight in the initial specification. These lights are a
standard used as exterior running lights on fire stations . Added
cost of $576 .
Item 4
This item was not called for in the specifications . We were notified
by Illinois Bell Telephone Company that it is a new requirement on
their part and had to be provided before they would install their
lines . This was not foreseeable at the time of the contract sign-
ing. Added cost of $4,320 .
Item 5
The specifications call for a dry pipe sprinkler system. This type
of system is a costly maintenance problem. It was decided that the
change to a wet pipe system was germane to the original specification
and also in the best interest of the City. Cost savings $3,000 .
Item 6
Link photo electric controls were not foreseen for inclusion in the
original specifications . They were added as a operating safety fea-
ture and is in the best interest of the City. Added cost $5.206 .
Item 7
Unsuitable soil was encountered at the Villa Street site and re-
placed. This was not foreseeable in the original contract and was
needed to be completed. Added cost $917 .
Item 8
The contract called for a fixed hardware allowance to be included in
each bid. The hardware selected was less costly than the allowance.
Cost savings $13,425 .
Item 9
Colored plumbing fixtures were not established in the original speci-
fications . All fixtures were bid in white. It was decided that
colored fixtures would be appropriate for total aesthetics within the
buildings . Added cost $1, 100 .
Item 10
Conduit for traffic signal preemption was not foreseen in the origi-
nal specifications . It was suggested by Engineering that it would be
cost effective and in the best interest of the City to install the
conduit during construction rather than at a latter date. Added cost
$849 .
Item 11
This item was overlooked in the original specification and had to be
added. Added cost $835 .
•
Item 12
When the specifications were written, they did not include applianc-
es. The bidders included standard residential cabinet sizes . It was
the City' s intent to purchase commercial appliances which we did.
When the catalog sheets for our appliances were given to the contrac-
tor, it was determined that a cabinet modification needed .to be
made. Added cost $490 .
Item 13
The specifications called for the owner (City) to provide dishwash-
ers, exhaust hoods, ranges, water coolers, washers and dryers . The
bidders left these items off of the bid along with the proper elec-
tric, water and natural gas connections. These had to be added in
the best interest of the City. Added cost $933.
Item 14
The vehicle exhaust system included in our specification did not
include an interface relay between the overhead doors and the exhaust
system. The electrical contractor thought the door people provided
it, the door people thought the exhaust system people provided it,
the exhaust system people thought the electrical contractor provided
the relay. In order to make the system function, this had to be an
added on. Added cost $1,088 .
Item 15
This change was germane to the original contract, at no cost.
Item 16
The water tank fill stations were not included in the specifica-
tions . This was an oversight on the City' s part, but needed to be
included for our best interest. Added cost $2,644 .
Item 17
After the specifications were written it was determined and recommend-
ed that due to the large amount of moisture used on the apparatus
floor area, it was in our best interest to use an epoxy paint on the
hose room area. Added cost $666 .
Item 18
During construction and completing site work at Villa Street Station
the paving contractor ran into unforeseen underground conditions with
the street and curb connection. This was unforeseen within our speci-
fication and scope of work under our contract. It was completed in
the best interest of the City. Added cost $3,690 .
Item 19
Our specifications and color selections did not differentiate sepa-
rate colors for walls and ceilings . The contractor use the same
color for both. In the best interest of the City for aesthetics,
employee working conditions and room size differentiation it was
changed two (2) white ceilings . Added cost $1,249 .
Item 20
We were instructed by the City Engineer to change the originally
approved sub-grade at the Royal Street Station. This was done for
water drainage reasons in the best interest of the City. Added cost
$1,749 .
Item 21
The elimination of the specified floor sealer was made in the best
interest of the City and allowed by the existing contract. Cost
savings $1,000 .
Item 22
The natural gas line to the lawn equipment room was not correctly
specified in the original contract. This was not detected until
after the bids were accepted. This change is in the best interest of
the City. Added cost $685 .
Item 23
It was determined that the receiver and transmitters installed accord-
ing to the specifications and contract were not in the best interest
of the City. They were changed to make them compatible with our
other facilities and equipment. Added cost $1,920 .
Item 24
Face brick for the three (3) stations was specified and bid as an
allowance in the contract. The actual selection by the City came in
below the allowance, this was germane to the contract. Cost savings
$5,888 .
Of these 24 items there is a net increase in the original overall
contract for the three (3) fire stations of $10,262 .
st
•
1n
r /;=s-. OF tic. Agenda Item No.. 't, 0.,a
01.opgTLD Ft81
November 12 , 1991
To: Mayor and Members of the City Council
From: City Manager
Subject: Change Order #1 For Construction of Fire Stations
Purpose:
Council 's approval is needed to modify our contract to Skender
Construction Company for the three (3) fire stations.
Background:
Over the past 10 months, certain modifications have occurred to our
original construction plans for the three (3) new fire stations.
Owlso we have had several extras added to the buildings for items that
.are over looked in the initial bid. Several changes were also need-
ed to make the buildings complete for operational needs .
Attached is a summary of the changes that were made, along with the
additional cost or credit for the change. Exhibit #1 will be a
change order to Skender Construction Company, the general contrac-
tor for the project. Exhibit #2 will be a purchase order to Artlow
Systems for the sealing of all exposed concrete floor in the appara-
tus bays and equipment rooms .
Financial Impact:
The additional cost for the two items are as follows :
1. Change order to Skender Construction for $10,262 .
2. Purchase order to Artlow Systems for $6,790.41 .
This represents an increase to the overall project cost of $17,053 or
less than one percent ( 1%) . The original bid price for the three (3)
stations is $1,761,000.
The cost will be spread over the three (3) buildings equally from the
following bond accounts .
389-993-9916
389-993-9917
390-993-9916
Recommendation:
Staff has been completely involved in the review and negotiations of
these changes . It is our recommendation that Council approve the
changes .
`. . _4
ity ager
Exhibit #1
,.ender Construction Company
CHANGE ORDER LOG
Project Name: Elgin Fire Stations
Project Number: 6109016
AMOUNT DAYS DATE TO AMOUNT DAYS
NO. DESCRIPTION REQUESTED REQUESTED ARCH STATUS APPROVED APPROVED COI
1 Remove underground storage $4,128 0 82/18/91 approved $4,128
tanks at Villa
2 Furnish and install Map $699 4 83/18/91 approved $699 I
circuit breaker for panel EM
3 Furnish and install flange trims $4,236 1 43/18/91 rejected $8
for light fixtures
4 Furnish and install red i green $576 1 03/18/91 approved $576 $
fixtures outside Apparatus Room
5 Furnish and install 4' pvc $4,321 I 13/18/91 approved $4,321
conduit for Illinois Bell
6 Wet sprinkler system in leiu of ($3,111) 1 14/11/91 approved ($3,111) 1
fpftdry system
7 Furnish and install (12) link $5,246 I 13/18/91 approved $5,216 0
photo electric controls
8 Furnish and install Co—Ray—Vac $9,495 1 14/11/91 rejected $1 1
infra—red heating system
9 Unsuitable soil encountered at $917 0 14/12/91 approved $917 1
Villa on April 4
11 Credit for unused hardware ($13,425) I 14/15/91 approved ($13,425) I
allowance
11 Water closet and lav in Womens $1,111 1 16/17/91 approved $1,111 1
Room to be almond
12 Traffic preemption conduit at $849 $ 16/28/91 approved $849
all three stations
13 Add under sink garbage disposal $835 1 17/29/91 approved $835
in kitchen
14 Kitchen cabinet layout revisions $491 1 08/01/91 approved $491 1
supply power to dishwasher, hood $933 I 08/12/91 approved $933 I
range, water cooler, washer/dryer
Skender Construction Company
CHANGE ORDER L06
Project Name: Elgin Fire Stations
Project Number: 6119116
AMOUNT DAYS DATE TO AMOUNT DAYS
NO. DESCRIPTION REQUESTED REQUESTED ARCH STATUS APPROVED APPROVED COI
16 Vehicle exhaust sequence of $1,188 1 18/12/91 approved $1,188
operation change
17 Delete communication conduit and $1 1 18/12/91 approved $1
add TV and Television outlets
18 Add tank fill station at the $2,644 I 18/12/91 approved $2,644
ceiling of Apparatus Room
19 Epoxy paint walls of Hose Room $666 1 88/12/91 approved $666 1
21 Additional costs to remove $3,691 I 11/28/91 approved $3,691
monolithic curb at Villa
21 Change existing paint color $1,249 I 11/28/91 approved $1,249
in various room at Mclean
22 Raise subgrade at Royal Station $1,588 1 18/28/91 approved $1,581
due to site plan revision
23 Eliminate two coats sealer on ($1,111) I 11/14/91 approved ($1,111) 1
Apparatus floor at 3 stations
24 Extend gas line from Work Room $685 1 11/14/91 approved $685 I
to Lawn Equipment Room
25 Furnish and install receivers $1,921 I 11/14/91 approved $1,921
and transmitters to match Elgin
26 Brick cost difference from ($5,888) I 11/14/91 approved ($5,888) I
allowance to actual cost
TOTAL $18,262
105 S. Fairbank St. •Addison, IL 60101•(708)543-8111• 1(800)5-ARTLOW•Fax(708)543-8171 ,
•
a- "The Concrete Protectors"...Serving The Nation Since 1963
ARTLO UV) Exhibit #2
PROPOSAL
•
elk .,,,, ,_. DIVISION OF AHCHEM.INC - - - October 29, 19 91
• Chief John Henrici
City Of Elgin Fire Department
550 Summit Street
Elgin, IL 60120
Re: 3 Fire Stations
Dear Chief Henrici: 3300 sq. ft. each
We respectfully submit herewith our proposal for furnishing all labor, equipment and material for
PREPARATION COATING .- ;1;MISCELLANEOUS: I
f?S Scrape ❑Arprime ❑ Pressure Wash
fx Spot Grind ❑Arthane 400 ❑ Dock(s)
M Hand Sweep ❑Arthane 600 ❑Wall(s)
❑Machine Sweep ❑Arthane 1000 ❑ Ceiling
6'c Hand Scrub ❑Arpoxy ❑Water Sandblast
R Machine Scrub ❑Arcrete ❑Arblast
❑Strip w/Arstrip to remove x Aqua–Poxy Primer–lst Coat ❑Grit Screen
❑ Painted Lines ❑Glue x Glazon Utility–Top Coat ❑Sand
❑Old Coating ❑ Latex ❑ ❑Solvent Tack
❑Mastic ❑ ❑Tile Removal
&Strip w/Arsolve to remove k Clear ❑
❑ Rubber Marks F Curing agent ❑Color see(c)below ❑
/Acid Etch x, Hand Apply 2 Coats ❑
k Normal ❑ Mild ❑ Spray Coats ❑
U Scrub wlArdition k Anti-slip Between Coats ❑
U Rinse w/Clear Water
A) PREP/COATING/MISC. (Per Above) 9.900 sq ft @ $ _722 per sq ft $7.147_80
B) CURING—If Compound Other Than Water Based Was Used — It Must Be Removed At $ sq ft
C) COLOR (Per Above) sq ft @ $ per sq ft $
-JO f/SAW CUTS . . . }_-' t - I
Prepare And Install To Manufacturer Specifications...
❑ Control Joints x fill with lin ft @ $ per in ft ... $
❑Saw Cuts x fill with in ft @ $ per lin ft ... $
_CRACKS/JOINT REPAIR
Rout Cracks—Sand Or Grind To Grade.. .
❑Fill with Epoxy Matrix in ft @ $ per in ft $ •
❑Fill with Cementious Material lin ft @ $ per in ft $
❑Patch holes @ $ ea. $
OVERLAYMENT/COVE OR SEAMLESS SEEDED SYSTEMS - <- ,, s'-I
Overlayment sq ft @ " Depth @ $ sq ft $
Continuous Cove in ft @ " Height @ $ lin ft $
Seamless sq ft @ " Depth @ $ sq ft $
❑Arblast ❑Saw Cut Keyways ❑Scarify ❑Scabble ❑Waterblast
MISCELLANEOUS ;x 4 : -- I
❑Undersealing ❑Mudjacking ❑ Epoxy Injection
❑ Holes @ $ per hole $
❑ Bags Fly Ash/Portland Cement Mix @ $ per bag $
❑ Men @ $ per hour $
❑ Epoxy @ $ per gallon $
FOOTAGES ARE APPROXIMATE FOR BIDDING AND WILL BE FIELD MEASURED AT TIME OF SAID WORK...
M To be completed in 1 phase(s), 4 day(s) per phase.
X Price based on X Weekday ❑Weekends Add for Weekends, Nights& Holidays
fX Price includes the removal and disposal of 2 drums of waste stripper.
See important EPA information on the reverse side of this proposal.
MS AYMENT - Net 30 Days...11% will be added to invoice after 30 days if payment in full is not received.
5 0o ..,scount if payment, in full, is received within (5) working days of completion of said work. $6,790.41
($.686)
NOTE: Price based on all three stations being completed in conjunction
with each other.