HomeMy WebLinkAbout90-0912 Clark Dietz RESOLUTION
AUTHORIZING EXECUTION OF AN AGREEMENT WITH
CLARK DIETZ, INC.
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF ELGIN, ILLINOIS,
that George VanDeVoorde, Mayor, and Dolonna Mecum, City Clerk, be and are hereby
authorized and directed to execute an agreement on behalf of the City of Elgin with
Clark Dietz, Inc. for water distribution system improvements, a copy of which is
attached hereto and made a part hereof by reference.
s/ George VanDeVoorde
George VanDeVoorde, Mayor
Presented: September 12, 1990
Adopted: September 12, 1990
Vote: Yeas 7 Nays 0
Recorded:
Attest:
s/ Dolonna Mecum
Dolonna Mecum, City Clerk
Vi
CITY OF ELGIN
WATER DISTRIBUTION SYSTEM IMPROVEMENTS
ENGINEERING SERVICES AGREEMENT
Clark Dietz, Inc. (called "CDI" herein) , hereby propose to furnish to the
City of Elgin, Illinois (called the "OWNER" herein) the professional
engineering services for the water distribution system improvements
(hereinafter called the "PROJECT") .
SERVICES OF CDI
CDI will serve as the OWNER'S professional engineering representative in those
phases of the PROJECT to which this Agreement applies, and will give
consultation and advice to the OWNER during the performance of his services.
CDI agrees to perform the following professional services in connection with
the PROJECT.
Meet with the OWNER'S staff to review the scope of work and to gather all
information available including reports, plans, etc.
Review previously prepared studies, reports, plans and specifications with
regard to the current projects.
Prepare preliminary project cost estimate to be used for budget purposes.
Perform topographical survey and utility survey for all water main locations.
Meet with the OWNER to establish the actual water main location for each
segment of the PROJECT based on utility locations, right-of-way, connections,
etc.
Prepare final design drawings and specifications for each water main segment in
the form of bidding documents. The documents will be prepared to provide
separate bids for each segment.
Submit review plans to the OWNER.
After OWNER review, make final revisions to plans and specifications.
Submit final plans and specifications to the Illinois EPA and to other
appropriate agencies for their review. All work will be performed in
accordance with the appropriate regulations and standards.
1
CITY OF ELGIN
WATER DISTRIBUTION SYSTEM IMPROVEMENTS
Prepare final cost estimate.
During bidding, answer questions, prepare addendums, correspondence, etc.
After receipt of bids, evaluate all proposals and make recommendation for
construction contract awards.
Conduct a pre-construction meeting for all appropriate parties.
During construction, provide review of shop drawings, pay requests, change
orders, correspondence, etc. Make periodic (once a month) trips to review
construction.
Provide 120 mandays of full time Resident Project Representative inspection.
The duties, responsibilities and limitations of the authority of the Resident
Project Representative is included as Exhibit A of this Agreement.
Perform final inspection of the PROJECT and recommend acceptance, if
appropriate, to the OWNER.
Make known changes as a result of construction on mylars and turn over to
OWNER.
ADDITIONAL SERVICES OF CDI
If authorized in writing by the OWNER, prior to the rendering of such service,
CDI will furnish supplementary services of the following types which will be
paid for by the OWNER as described under PAYMENTS TO CDI.
Additional services due to significant changes in scope of the PROJECT or its
design including, but not limited to, changes in size, complexity, character of
construction or due to time delays, except those delays beyond the control of
the Client such as Acts of God, strikes, unavailability of parts, etc. , for
completion of construction work beyond December 31, 1991.
Revising previously approved studies, reports, design documents, Drawings or
Specifications.
Furnishing more than five (5) copies of Drawings and Specifications.
Additional services and responsibilities requested by the OWNER including
services normally furnished by the OWNER as described herein and services not
referred to in this Agreement will be performed by CDI for additional charges.
Preparing to serve and serving as an expert witness for the OWNER in any
Protest, Litigation or other proceeding involving the PROJECT.
2
CITY OF ELGIN
WATER DISTRIBUTION SYSTEM IMPROVEMENTS
Assistance with or negotiations for acquisition of easements and court
appearances or other assistance with condemnation proceedings for easement
acquisition or services associated with the preparation of property surveys,
right-of-way surveys or other legal surveys associated with the description or
acquisition of project sites or easements.
Providing renderings, exhibits or models for the PROJECT.
Preparing documents for alternate bids requested by the OWNER or documents for
out-of-sequence work.
Additional services resulting from the PROJECT involving more than four
separate construction contracts.
THE OWNER'S RESPONSIBILITIES
The OWNER will :
Provide full information as to his requirements for the PROJECT.
Designate in writing a person to act as the OWNER'S representative with respect
to the work to be performed under this Agreement; and such person shall have
complete authority to transmit instructions, receive information, interpret and
define the OWNER'S policies and decisions with respect to materials, equipment
elements and systems pertinent to the work covered by this Agreement.
Guarantee access to and make all provisions for CDI to enter upon public and
private lands as required for CDI to perform his work under this Agreement.
Examine all studies, reports, sketches, addenda, estimates, specifications,
drawings, proposals and other documents presented by CDI and shall render
decisions pertaining thereto with a reasonable time so as not to delay the work
of CDI.
Furnish CDI maps showing all existing utilities in the PROJECT areas.
Submit documentation provided by CDI to all governmental authorities having
jurisdiction over the PROJECT and such other individuals or bodies as may be
necessary for completion of the PROJECT.
Furnish, or direct CDI in writing to provide at the Client's expense, necessary
additional services or other services as which the Client and CDI agree are
required for project completion.
Pay all costs incidental to advertisement for bids and obtaining bids or
proposals from contractors.
3
CITY OF ELGIN
WATER DISTRIBUTION SYSTEM IMPROVEMENTS
PAYMENTS TO CDI
Payments for Engineering Services
The OWNER will pay CDI the lump sum amount of Seventy Seven Thousand and No/100
($77,000.00) .
Additional Services
Payment of direct labor costs times a factor of 2.90 for services rendered by
employees working on the project.
Payment for outside consulting and/or professional services performed by a
Subconsultant at actual invoice cost to CDI plus 15 percent for administrative
costs. Written client approval will be obtained before authorizing these
services.
Payment of in-house computer software used on behalf of the project at CDI
standard rates.
Payment for direct expenses incurred on behalf of the project at actual cost to
CDI plus 10 percent for administrative costs.
Methods and Times of Payment.
Payment to CDI shall be monthly based upon estimated percentages of completion
and the Additional Services. All monies not paid the Engineer within 60 days
of when due hereunder shall bear interest at the rate of 12% per annum.
Estimates.
Since CDI has no control over the cost of labor, materials or equipment, or
over the Contractor's methods of determining prices, or over competitive
bidding or market conditions, the estimates of construction cost provided for
herein are to be made on the basis of his experience and qualifications and
represent his best judgment as a design professional familiar with the
construction industry, but CDI cannot and does not guarantee that bids or the
PROJECT construction cost will not vary from cost estimates prepared by him.
Clark Dietz, Inc. hereby certifies that they are not barred from making an
offer to Contract as a result of a violation of Section 33E-3 or 33E-4 of
Chapter 38 of the Illinois Revised Statutes.
4
CITY OF ELGIN
WATER DISTRIBUTION SYSTEM IMPROVEMENTS
IN WIT K WHEREOF the ,rta'es hereto have 9made and executed this Agreement
thi s WIT
day of o Y ct , ( 90
CLIENT: ENGINEER:
CITY OF LGIN CLARK DIETZ, INC.
/� � ',�
By -B'2 .6. ,' i�/7z4 B �_ ./, _ AP /1.
U Mayor .r•►-
/1 4 ATTEST: ` A (74: ,e,),./e9ety..e, ,.,
ATTEST: 1►�,►tl.., I ', .�
Clerk
S:080890KI
5
EXHIBIT A CITY OF ELGIN
WATER DISTRIBUTION SYSTEM IMPROVEMENTS
EXHIBIT A
DUTIES, RESPONSIBILITIES AND LIMITATIONS OF THE AUTHORITY
OF THE RESIDENT PROJECT REPRESENTATIVE
A. GENERAL
1. The Resident Project Representative is CDI's Agent and shall
act under the supervision and direction of CDI. He shall
confer with CDI regarding his actions, and shall generally
communicate with the OWNER only through CDI.
B. DUTIES AND RESPONSIBILITIES
The Resident Project Representative shall :
1 . Schedule: Review the construction schedule prepared by the
Contractor for compliance with the contract and give written
advice to CDI concerning the contractor's construction
progress.
2. Conferences: Attend preconstruction conferences. Arrange a
schedule of progress meetings and other job conferences as
required in consultation with CDI and notify those expected
to attend in advance. Maintain and circulate copies of
records of the meetings.
3. Liaison: (a) Serve as CDI's liaison with the Contractor
working principally through the Contractor's field
superintendent.
(b) Assist CDI in obtaining from the OWNER additional
details or information, when required at the job site for
proper execution of the work.
4. Approvals: When required, assist CDI in obtaining from the
Contractor a list of his proposed suppliers and
subcontractors.
A-1
EXHIBIT A CITY OF ELGIN
WATER DISTRIBUTION SYSTEM IMPROVEMENTS
5. Samples: Assist CDI in obtaining field samples of materials
delivered to the site which are required to be furnished, and
keep record of actions taken by CDI .
6. Shop Drawings
(a) Receive approved shop drawings and other submissions
from CDI; record data received, maintain a file of the
drawings and submissions, and check construction for
compliance with them.
(b) Alert the Contractor's field superintendent when he
observes materials or equipment being installed before
approval of shop drawings or samples, where such are
required, and advise CDI when he believes it is necessary to
disapprove work as failing to conform to the Contract
Documents.
7. Review of Work, Inspections and Tests
(a) Conduct on-site observations of the work in progress for
CDI as a basis for determining that the PROJECT is proceeding
in accordance with the Contract Documents.
(b) Verify that tests, including equipment and systems
start-up, which are required by the Contract Documents, are
conducted and that the Contractor maintains adequate records
thereof; observe, record and report to CDI appropriate
details relative to the test procedures and start-ups.
(c) Accompany visiting inspectors representing public or
other agencies having jurisdiction over the PROJECT, record
the outcome of these inspections and report to CDI.
8. Records
(a) Maintain at the job site orderly files for
correspondence, reports of job conferences, shop drawings and
other submissions, reproductions of original contract
documents including all addenda, change orders and additional
drawings issued subsequent to the award of the contract,
CDI's interpretations of the Contract Documents, progress
reports, and other PROJECT related documents.
A-2
EXHIBIT A CITY OF ELGIN
WATER DISTRIBUTION SYSTEM IMPROVEMENTS
(b) Keep a diary or logbook, recording hours on the job
site, weather conditions, list of visiting officials, daily
activities, decisions, observations in general , and specific
observations in more detail as in the case of observing test
procedures.
(c) Record names, addresses and telephone numbers of all
Contractors, subcontractors, and major material suppliers.
(d) Maintain a set of drawings on which authorized changes
are noted and deliver to CDI at the completion of the
PROJECT.
9. Reports
(a) Furnish CDI periodic reports as required of progress of
the PROJECT and the Contractor's compliance with the approved
construction schedule.
(b) Consult with CDI in advance of scheduled major tests or
start of important phases of the PROJECT.
10. Payment Requisitions: Review applications for payment with
the contractor for compliance with the established procedure
for their submission and forward them with recommendations to
CDI, noting particularly their relation to the work completed
and materials and equipment delivered at the site.
11. Guarantees, Certificates, Maintenance and Operation Manuals:
During the course of the work, assemble Guarantees,
Certificates, Maintenance and Operation Manuals and other
required data to be furnished by the Contractor and upon
acceptance of the PROJECT, deliver this material to CDI for
his approval and forwarding to the OWNER.
12. Completion:
(a) Prior to final inspection, submit to the Contractor a
list of observed items requiring correction and verify that
each correction has been made.
(b) Conduct final inspection in the company of CDI and the
OWNER and prepare a final list of items to be corrected.
A-3
EXHIBIT A CITY OF ELGIN
WATER DISTRIBUTION SYSTEM IMPROVEMENTS
(c) Verify that all items on final list have been corrected
and make recommendations to CDI concerning acceptance.
C. LIMITATIONS OF AUTHORITY
Except upon written instructions of CDI the Resident Project
Representative:
1. Shall not authorize any deviation from the Contract
Documents.
2. Shall not undertake any of the responsibilities of the
Contractor, the subcontractors or the Contractor's field
superintendent.
3. Shall not expedite the work for the Contractor.
4. Shall not advise on or issue directions relative to any
aspect of the construction technique or sequence.
5. Shall not authorize the OWNER to occupy the PROJECT in whole
or in part prior to final acceptance of the work.
6. Shall not participate in specialized field or laboratory
tests.
S:080890K1