HomeMy WebLinkAbout83-0909 West Side Plant Change Order No1 Man-Pe yeektlilamu
ELGIN, ILLINOIS
WATER WORKS IMPROVEMENTS
CONTRACT NO. 5
WEST SIDE PLANT IMPROVEMENTS
CHANGE ORDER NO. 1
SCOPE. This Change Order No. 1 covers additions and modifications to
the above contract as follows:
Item 1. Unsuitable material at the northwest corner of the new
chlorine building foundation shall be removed and replaced with
crushed limestone.
Item 2. Additional work shall be performed to field locate the
existing bubbler air piping at the existing clear water reservoir
No. 2.
Item 3. A credit adjustment shall be given the Owner for the relo-
cation and installation of the new 3/4 inch reservoir bubbler air
piping utilizing an existing 8 inch yard conduit. Bubbler air
piping material shall be changed from copper to PVC for piping
installed within the conduit.
Item 4. The basin equipment for each clarifier basin shall be
cleaned and repainted. The equipment shall be cleaned and the sur-
faces prepared for painting by sandblasting to white metal. The
equipment shall then be given a primer coat and multiple intermediate
and finish coats of a vinyl paint system to produce a minimum total
paint dry film thickness of 6 mils. The type and color of paint
and the method of applications shall be acceptable to the Engineer
and Owner.
The cost of the above work shall be based on the not-to-exceed
figures as provided hereinafter. The actual cost for basin cleaning
and sandblasting work shall be determined on the basis of the cost
of the work (time and material costs) plus a Contractor's fee for
overhead and profit in accordance with the general conditions. The
actual cost for painting the basin equipment shall be the lump sum
price shown unless fewer finish coats are required than originally
anticipated. If the required minimum dry film thickness can be
provided with fewer paint coats than originally anticipated, a
credit will be offered to the Owner for this work.
Item 5. The specified clarifier basin crack repair work shall be
modified and expanded as follows. Areas where delamination appears
shall be repaired by removing all loose and delaminated concrete
and rebuilding the areas using the shotcrete process. Where basin
wall cracks are through the wall type cracks, the repair shall be
(ELGIN, ILLINOIS )
(WATER WORKS IMPR.) CO1-1
(CONTRACT NO. 5 )
as originally specified. However, if the width of a "veed-out"
crack becomes excessively wide, the crack shall be repaired using
the shotcrete process. Shotcrete areas larger than one square foot
shall have reinforcing mesh placed under the shotcrete, providing
the depth of concrete removed is sufficient to allow its installation.
In preparation for the crack repairs, the complete interior wall
surface of each basin shall be cleaned by sandblasting.
In addition to the above repairs the top of the basin walls at the
equipment bearing points and lime trough penetrations shall be
repaired. Cracked and loose concrete shall be removed and replaced
with new concrete as required.
The existing basin handrail shall be separated from the basin
equipment supports and the ends sealed. The handrail post connections
to the basin walls shall be repaired. The handrail posts shall be
removed, the post and sleeve repaired as required, and the handrail
reset with post sleeves sealed to prevent moisture from entering.
The top 6 inches of the basin walls and the top horizontal surfaces
of the walls and adjoining slabs shall be sealed with two coats of
a neoprene-hypalon roof covering.
All of the above work shall be in accordance with applicable sections
of the contract documents. The materials, methods, and limits for
the above repairs shall be acceptable to the Engineer and Owner.
The additional basin repair work shall be performed on a time and
material basis with a not-to-exceed figure as provided hereinafter.
The actual cost shall be determined on the basis of the cost of the
work plus a Contractor's fee for overhead and profit in accordance
with the general conditions. Credit for work deleted under the
original contract shall be included in determining the actual cost.
REASON FOR CHANGES.
Item 1. Excavation for the foundation for the new chlorine building
revealed unsuitable material near the northwest corner of the founda-
tion. The existing material would not provide proper support for the
new structure. The unsuitable material was removed and replaced with
compacted crushed limestone.
Item 2. The Contractor was not able to locate the existing bubbler
air piping at the existing clear water reservoir No. 2 based on conformed
to construction drawings for the facilities. It was necessary for the
Contractor to perform additional exploratory excavation to locate the
existing piping.
Item 3. The Contractor was allowed to utilize an existing 8 inch under-
ground conduit to install a portion of the two new 3/4 inch bubbler air
piping to the existing reservoirs. To facilitate the installation of this
air piping through the conduit, PVC piping was substituted for the specified
copper piping. The revised installation and change in pipe material resulted
in a reduction in the amount of work and cost to the Contractor and an
overall credit for the Owner.
(ELGIN, ILLINOIS )
(WATER WORKS IMPR. ) CO1-2
(CONTRACT NO. 5 )
Item 4. The existing basin equipment is in need of normal preventative
maintenance painting. The Owner requested that the painting of the
existing equipment be coordinated with the other basin work. Performing
this work at the same time the basins are being repaired reduces the
equipment down time and takes advantage of cost savings from performing
basin and equipment cleaning and sandblasting at the same time.
Item 5. The clarifier wall investigation report specified to be com-
pleted prior to beginning basin crack repairs indicated that areas of
the exterior surface of the basin walls may be more severely damaged
than originally thought. The report referred to areas of "delamination"
or areas where the outside 1-1/2 to 2 inches of concrete has cracked
and separated from the balance of the wall. From the surface these
areas are defined by extensive random hairline cracks. The full extent
of the severity of the delamination is difficult to determine. However,
each area should be investigated and repaired prior to installation of
the metal paneling.
Additional cracking and loose concrete was found at the basin equipment
bearing supports and lime trough penetrations. The repair of the
handrail posts and sleeves and the installation of the neoprene-hypalon
roof covering will help prevent further deterioration of the top of the
basin walls and slabs from moisture penetration and freeze-thaw action.
SUMMARY OF CHANGES IN CONTRACT AMOUNT. The contract amount shall be revised
on the following basis:
Add Deduct
$ $
Item 1. Removal and replacement of un-
suitable material.
Removal and replacement $466.00
10% Overhead and profit 47.00 513.00
Item 2. Field location of reservoir bubbler
air piping.
Additional work $882.00
5% Overhead and profit 44.00 926.00
Item 3. Credit for reservoir bubbler
air piping modifications. 581.00
Item 4. Clean and repaint basin
equipment of each clarifier basin.
Cleaning and sandblasting,
not-to-exceed 4,200
Painting,
not-to-exceed 11,000
5% Overhead and profit 760
15,960.00
(ELGIN, ILLINOIS; )
(WATER WORKS IMPR.) CO1-3
(CONTRACT NO. 5)
Add Deduct
$ $
Item 5. Additional clarifier basin
repair work.
Additional work, not-to-exceed 20,000.00
Totals $37,399.00 $ 581.00
Net Addition to the Contract Amount: $36,818.00
By reason of this Change Order No. 1, the contract cost shall be increased
in the amount of Thirty-Six Thousand Eight Hundred Eighteen and 00/100
Dollars ($36,818.00).
OTHER CONTRACT PROVISIONS. All other provisions of the contract shall remain
the same. ,�- �
AGREED to this Cl � '' "'day of Q7 /l 1983.
Recommended by: Approved:
BLACK & VEATCH CITY OF ELGIN, ILLINOIS
Part. of the F rst rt (Owner)
By er 4 c9 By . J . .�
•
Date: September 6, 1983 Title A!
— , — 83
Accepted:
SEAGREN/SALES, INC.
Party o the Second Part (Contractor)
By r2
Title -)sz_¢-�
(ELGIN, ILLINOIS )
(WATER WORKS IMPR. ) CO1-4
(CONTRACT NO. 5 )
October 4, 1983
MEMORANDUM
TO: Leo Nelson, City Manager
FROM: Gary W. Miller, Engineering Supervisor
RE: Contract No.5
West Side Plant Improvements
Change Order No. 1
The City Council approved the subject change order on September 12,
1983 at a Committee of the Whole Meeting. Attached is a copy of Change
Order No. 1 in final form which has been signed by the engineer and
contractor.
Items 1 ,2 and 3 have already been completed. Items 4 and 5
involve work to be performed with not-to-exceed figures. It is
recommended that the City Council pass a resolution accepting this change
order and authorizing execution by the City Manager.
Final adjustments in the actual costs involving items 4 and 5 will
be included in a future change order.
GWM:do
cc: Mel Dahl
Ron Zegers
Marie Yearman✓
Mike Sarro
Ery Jentsch
Bob Renfrow
Monte Wilson
•f
ELGIN, ILLINOIS
WATER WORKS IMPROVEMENTS
CONTRACT NO. 5
WEST SIDE PLANT IMPROVEMENTS
CHANGE ORDER NO. I
SCOPE. This Change Order No. 1 covers additions and modifications to
the above contract as follows:
Item 1. Unsuitable material at the northwest corner of the new
chlorine building foundation shall be removed and replaced with
crushed limestone.
Item 2. Additional work shall be performed to field locate the
existing bubbler air piping at the existing clear water reservoir
No. 2.
Item 3. A credit adjustment shall be given the Owner for the relo-
cation and installation of the new 3/4 inch reservoir bubbler air
piping utilizing an existing 8 inch yard conduit. Bubbler air
piping material shall be changed from copper to PVC for piping
installed within the conduit.
Item 4. The basin equipment for each clarifier basin shall be
cleaned and repaintd. The equipment shall be cleaned and the sur-
faces prepared for painting by sandblasting to white metal. The
equipment shall then be given a primer coat and multiple intermediate
and finish coats of a vinyl paint system to produce a minimum total
paint dry film thickness of 6 mils. The type and color of paint
and the method of applications shall be acceptable to the Engineer
and Owner.
The cost of the above work shall be based on the not-to-exceed
figures as provided hereinafter. The actual cost for basin cleaning
and sandblasting work shall be determined on the basis of the cost
of the work (time and material costs) plus a Contractor's fee for
overhead and profit in accordance with the general conditions. The
actual cost for painting the basin equipment shall be the lump sum
price shown unless fewer finish coats are required than originally
anticipated. If the required minimum dry film thickness can be
provided with fewer paint coats than originally anticipated, a
credit will be offered to the Owner for this work.
Item 5. The specified clarifier basin crack repair work shall be
modified and expanded as follows. Areas where delamination appears
shall be repaired by removing all loose and delaminated concrete
and rebuil4ing the areas using the shotcrete process. Where basin
wall cracks are through the wall type cracks, the repair shall be
(ELGIN, ILLINOIS )
(WATER WORKS IMPR.) C0I-1
(CONTRACT NO. 5 )
.
as originally specified. However, if the width of a "veed-out"
crack becomes excessively wide, the crack shall be repaired using
the shotcrete process. Shotcrete areas larger than one square foot
shall have reinforcing mesh placed under the shotcrete, providing
the depth of concrete removed is sufficient to allow its installation.
In preparation for the crack repairs, the complete interior wall
surface of each basin shall be cleaned by sandblasting.
In addition to the above repairs the top of the basin walls at the
equipment bearing points and lime trough penetrations shall be
repaired. Cracked and loose concrete shall be removed and replaced
with new concrete as required.
The existing basin handrail shall be separated from the basin
equipment supports and the ends sealed. The handrail post connections
to the basin walls shall be repaired. The handrail posts shall be
removed, the post and sleeve repaired as required, and the handrail
reset with post sleeves sealed to prevent moisture from entering.
The top 6 inches of the basin walls and the top horizontal surfaces
of the walls and adjoining slabs shall be sealed with two coats of
a neoprene-hypalon roof covering.
All of the above work shall be in accordance with applicable sections
of the contract documents. The materials, methods, and limits for
the above repairs shall be acceptable to the Engineer and Owner.
The additional basin repair work shall be performed on a time and
material basis with a not-to-exceed figure as provided hereinafter.
The actual cost shall be determined on the basis of the cost of the
work plus a Contractor's fee for overhead and profit in accordance
with the general conditions. Credit for work deleted under the
original contract shall be included in determining the actual cost.
REASON FOR CHANGES.
Item 1. Excavation for the foundation for the new chlorine building
revealed unsuitable material near the northwest corner of the founda-
tion. The existing material would not provide proper support for the
new structure. The unsuitable material was removed and replaced with
compacted crushed limestone.
Item 2. The Contractor was not able to locate the existing bubbler
air piping at the existing clear water reservoir No. 2 based on conformed
to construction drawings for the facilities. It was necessary for the
Contractor to perform additional exploratory excavation to locate the
existing piping.
Item 3. The Contractor was allowed to utilize an existing 8 inch under-
'ground conduit to install a portion of the two new 3/4 inch bubbler air
piping to the existing reservoirs. To facilitate the installation of this
air piping through the conduit, PVC piping was substituted for the specified
copper piping. The revised installation and change in pipe material resulted
in a reduction in the amount of work and cost to the Contractor and an
overall credit for the Owner.
(ELGIN, ILLINOIS )
(WATER WORKS IMPR. ) CO1-2
(CONTRACT NO. 5 )
.1
Item 4. The existing basin equipment is in need of normal preventative
maintenance painting. The Owner requested that the painting of the
existing equipment be coordinated with the other basin work. Performing
this work at the same time the basins are being repaired reduces the
equipment down time and takes advantage of cost savings from performing
basin and equipment cleaning and sandblasting at the same time.
Item 5. The clarifier wall investigation report specified to be com-
pleted prior to beginning basin crack repairs indicated that areas of
the exterior surface of the basin walls may be more severely damaged
than originally thought. The report referred to areas of "delamination"
or areas where the outside 1-1/2 to 2 inches of concrete has cracked
and separated from the balance of the wall. From the surface these
areas are defined by extensive random hairline cracks. The full extent
of the severity of the delamination is difficult to determine. However,
each area should be investigated and repaired prior to installation of
the metal paneling.
Additional cracking and loose concrete was found at the basin equipment
bearing supports and lime trough penetrations. The repair of the
handrail posts and sleeves and the installation of the neoprene-hypalon
roof covering will help prevent further deterioration of the top of the
basin walls and slabs from moisture penetration and freeze-thaw action.
SUMMARY OF CHANGES IN CONTRACT AMOUNT. The contract amount shall be revised
on the following basis:
Add Deduct
$ $
Item 1. Removal and replacement of un-
suitable material.
Removal and replacement $466.00
10% Overhead and profit 47.00 513.00
Item 2. Field location of reservoir bubbler
air piping.
Additional work $882.00
5% Overhead and profit 44.00 926.00
Item 3. Credit for reservoir bubbler
air piping modifications. 581.00
Item v . Clean and repaint basin
equipment of each clarifier basin.
Cleaning and sandblasting,
not-to-exceed 4,200
Painting,
not-to-exceed 11,000
5% Overhead and profit 760
• 15,960.00
(ELGIN, ILLINOIS )
(WATER WORKS IMPR.) CO1-3
(CONTRACT NO. 5)
Add Deduct
$ $
Item 5. Additional clarifier basin
repair work.
Additional work, not-to-exceed 20,000.00
Totals $37,399.00 $ 581.00
Net Addition to the Contract Amount: - $36,818.00
By reason of this Change Order No. 1, the contract cost shall be increased
in the amount of Thirty-Six Thousand Eight Hundred Eighteen and 00/100
Dollars ($36,818.00) .
OTHER CONTRACT PROVISIONS. All other provisions of the contract shall remain
the same.
AGREED to this day of , 1983.
Recommended by: Approved:
BLACK & VEATCH CITY OF ELGIN, ILLINOIS
Party of the First Part (Owner)
By : By
Date: September 6, 1983 Title
Accepted:
SEAGREN/SALES, INC.
Party of the Second Part (Contractor)
7 ,
By r' k
Title
(ELGIN, ILLINOIS )
(WATER WORKS IMPR. ) CO1-4
(CONTRACT NO. 5 )
September 7, 1983
MEMORANDUM
TO: Leo Nelson, City Manager
FROM: Gary W. Miller, Engineering Supervisor
RE: Contract No. 5
West Side Plant Improvements
Change Order No.1
Attached is a four page document which represents Change Order No.1
for the referenced project. This change order includes several additions
and one deletion from the contract. The changes have been discussed with
Black &Veatch and we are in agreement with the items as listed.
The proposed change order contains five items with a total increase
of $36,818.00 in the contract amount. Each item is described within the
change order, including the reason for the changes. We are requesting
that the City Council review this material at the next Committee of the
Whole meeting on September 12, 1983 so that the work covered under items
4 and 5 may be authorized. The work covered in items 1 ,2 and 3 was
relatively minor and has already been completed.
Item 4 involves cleaning and painting clarifier basin equipment.
During the preparation of the plans some time ago, Black and Veatch was
directed to exclude this normal preventative maintenance from this contract.
It was felt that the necessary work could be completed by City forces at a
later date.
However, after further examination of the equipment, the scope of work
has been expanded to include extensive sandblasting and several coats of
paint, which is much more time consuming and more costly for City crews than
had been anticipated. Therefore, due to the above, and the fact that we can
reduce equipment down time, it is recommended that this work be added to the
contract.
Costs relative to Item 4 are not-to-exceed figures and may be less than
the listed amount of $15,960.00. Should this work be authorized, final
costs would be included in a final change order for the project.
Item 5 involves clarifier basin wall crack repairs. A detailed
investigation report was specified in the contract to be completed prior
to the beginning of those repairs. That report was completed and reviewed
and it indicates that the walls may be more severely damaged than originally
thought. Therefore, an alternate repair method has been recommended
utilizing the shotcrete process. The originally specified process will be
utilized where applicable.
Page 2
The cost relative to item 5 is a not-to-exceed figure and may be
less than the listed amount of $20,000. Should this work be authorized,
the final cost shall be included in a final change order for the project.
For your information, the approval of Change Order No.1 would
increase the total amount of Contract No.5 with Seagren/Shales, Inc.
from $758,200 to $795,018.
GWM:do
Attachment
cc: Mel Dahl
Ron Zegers
Marie Yearman
Mike Sarro
Ery Jentsch
Bob Renfrow
Monte Wilson
ELGIN, ILLINOIS
WATER WORKS IMPROVEMENTS
CONTRACT NO. 5
WEST SIDE PLANT IMPROVEMENTS
CHANGE ORDER NO. 1
SCOPE. This Change Order No. 1 covers additions and modifications to
the above contract as follows:
Item 1 . Unsuitable material at the northwest corner of the new
chlorine building foundation shall be removed and replaced with
crushed limestone.
Item 2. Additional work shall be performed to field locate the
existing bubbler air piping at the existing clear water reservoir
No. 2.
Item 3. A credit adjustment shall be given the Owner for the relo-
cation, and installation of the new 3/4 inch reservoir bubbler air
piping utilizing an existing 8 inch yard conduit. Bubbler air
piping material shall be changed from copper to PVC for piping
installed within the conduit.
Item 4. The basin equipment for each clarifier basin shall be
cleaned and repainted. The equipment shall be cleaned and the sur-
faces prepared for painting by sandblasting to white metal. The
equipment shall then be given a primer coat and multiple intermediate
and finish coats of a vinyl paint system to produce a minimum total
paint dry film thickness of 6 mils. The type and color of paint
and the method of applications shall be acceptable to the Engineer
and Owner.
The cost of the above work shall be based on the not-to-exceed
figures as provided hereinafter. The actual cost for basin cleaning
and sandblasting work shall be determined on the basis of the cost
of the work (time and material costs) plus a Contractor's fee for
overhead and profit in accordance with the general conditions. The
actual cost for painting the basin equipment shall be the lump sum
price shown unless fewer finish coats are required than originally
anticipated. If the required minimum dry film thickness can be
provided with fewer paint coats than originally anticipated, a
credit will be offered to the Owner for this work.
Item 5. The specified clarifier basin crack repair work shall be
modified and expanded as follows. Areas where delamination appears
shall be repaired by removing all loose and delaminated concrete
and rebuilding the areas using the shotcrete process. Where basin
wall cracks are through the wall type cracks, the repair shall be
(ELGIN, ILLINOIS )
(WATER WORKS IMPR.) C01-1
(CONTRACT NO. 5 )
as originally specified. However, if the width of a "veed-out"
crack becomes excessively wide, the crack shall be repaired using
the shotcrete process. Shotcrete areas larger than one square foot
shall have reinforcing mesh placed under the shotcrete, providing
the depth of concrete removed is sufficient to allow its installation.
In preparation for the crack repairs, the complete interior wall
surface of each basin shall be cleaned by sandblasting.
In addition to the above repairs the top of the basin walls at the
equipment bearing points and lime trough penetrations shall be
repaired. Cracked and loose concrete shall be removed and replaced
with new concrete as required.
The existing basin handrail shall be separated from the basin
equipment supports and the ends sealed. The handrail post connections
to the basin walls shall be repaired. The handrail posts shall be
removed, the post and sleeve repaired as required, and the handrail
reset with post sleeves sealed to prevent moisture from entering.
The top 6 inches of the basin walls and the top horizontal surfaces
of the walls and adjoining slabs shall be sealed with two coats of
a neoprene-hypalon roof covering.
All of the above work shall be in accordance with applicable sections
of the contract documents. The materials, methods, and limits for
the above repairs shall be acceptable to the Engineer and Owner.
The additional basin repair work shall be performed on a time and
material basis with a not-to-exceed figure as provided hereinafter.
The actual cost shall be determined on the basis of the cost of the
work plus a Contractor's fee for overhead and profit in accordance
with the general conditions. Credit for work deleted under the
original contract shall be included in determining the actual cost.
REASON FOR CHANGES.
Item 1. Excavation for the foundation for the new chlorine building
revealed unsuitable material near the northwest corner of the founda-
tion. The existing material would not provide proper support for the
new structure. The unsuitable material was removed and replaced with
compacted crushed limestone.
Item 2. The Contractor was not able to locate the existing bubbler
air piping at the existing clear water reservoir No. 2 based on conformed
to construction drawings for the facilities. It was necessary for the
Contractor to perform additional exploratory excavation to locate the
existing piping.
Item 3. The Contractor was allowed to utilize an existing 8 inch under-
,grcund conduit to install a portion of the two new 3/4 inch bubbler air
piping to the existing reservoirs. To facilitate the installation of this
air piping through the conduit, PVC piping was substituted for the specified
copper piping. The revised installation and change in pipe material resulted
in a reduction in the amount of work and cost to the Contractor and an
overall credit for the Owner.
(ELGIN ILLINOIS )
(WATER WORKS IMPR. ) CO1-2
(CONTRACT NO. 5 )
. •
Item 4. The existing basin equipment is in need of normal preventative
maintenance painting. The Owner requested that the painting of the
existing equipment be coordinated with the other basin work. Performing
this work at the same time the basins are being repaired reduces the
equipment down time and takes advantage of cost savings from performing
basin and equipment cleaning and sandblasting at the same time.
Item 5. The clarifier wall investigation report specified to be com-
pleted prior to beginning basin crack repairs indicated that areas of
the exterior surface of the basin walls may be more severely damaged
than originally thought. The report referred to areas of "delamination"
or areas where the outside 1-1/2 to 2 inches of concrete has cracked
and separated from the balance of the wall. From the surface these
areas are defined by extensive randum hairline cracks. The full extent
of the severity of the delamination is difficult to determine. However,
each area should be investigated and repaired prior to installation of
the mLltal paneling.
Additional cracking and loose concrete was found at the basin equipment
bearing supports and lime trough penetrations. The repair of the
handrail posts and sleeves and the installation of the neoprene-hypalon
roof covering will help prevent further deterioration of the top of the
basin walls and slabs from moisture penetration and freeze-thaw action.
SUMMARY OF CHANGES IN CONTRACT AMOUNT. The contract amount shall be revised
on the following basis:
Add Deduct
$ $
Item 1. Removal and replacement of un-
suitable material.
Removal and replacement $466.00
10% Overhead and profit 47.00 513.00
Item 2. Field location of reservoir bubbler
air piping.
Additional work $882.00
5% Overhead and profit 44.00 926.00
Item 3. Credit for reservoir bubbler
air piping modifications. 581.00
Item 4. Clean and repaint basin
equipment of each clarifier basin.
Cleaning and sandblasting,
not-to-exceed 4,200
Painting,
not-to-exceed 11,000
5% Overhead and profit 760
15,960.00
(ELGIN, ILLINOIS )
(WATER WORKS IMPR.) C01-3
(CONTRACT NO. 5)
s • e
Add Deduct
$ $
Item 5. Additional clarifier basin
repair work.
Additional work, not-to-exceed 20,000.00
Totals $37,399.00 $ 581.00
Net Addition to the Contract Amount: $36,818.00
By reason of this Change Order No. 1, the contract cost shall be increased
in the amount of Thirty-Six Thousand Eight Hundred Eighteen and 00/100
Dollars ($36,818.00) .
OTHER CONTRACT PROVISIONS. All other provisions of the contract shall remain
the same.
AGREED to this day of , 1983.
Recommeaded by: Approved:
BLACK 6 VEATCH CITY OF ELGIN, ILLINOIS
Party of the First Part (Owner)
By By
Date: September 6, 1983 Title
Accepted:
SEAGREN/SALES, INC.
Party of the Second Part (Contractor)
By
Title
(ELGIN, ILLINOIS )
(WATER WORKS IHPR. ) CO1-4
(CONTRACT NO. 5 )